Pricing Procedure determination for Quotation,Contract,Scheduling Agreement

Hello All,
             Plz let me know,how the pricing procedure(Both Item & Header Level) can be determined for Quotation,Contract,Scheduling Agreement.
Do let me know with configuration details.
Thanks
JP

Hi Jyoti ,
There isn't any separate pricing procedure for Quotaions , Contracts , Scheduling Agreement s..
The pricing which u normally find in PO derived from Vendor Master ( Based on Vendor Schema ) , hold good for the above purchasing documents.
Regards
Ramesh Ch

Similar Messages

  • Pricing procedure determination for complaint document with reference to billing

    Hello Guys,
    I am configuring complaint process for project purpose and I got stuck. I need to change the pricing procedure which is determined for complaint
    document . Right now the pricing procedure is copied from Billing Document for which complaint refers to.
    I am searching a place in configuration where I could change the pricing procedure determination for complaint document with reference to billing doc.
    Could you please advise where I can find it ?
    Thank you in advance!
    Br,
    Frederic

    Hello Frederic,
    I would check the following in SPRO:
    - CRM
    - Basic Functions
    - Pricing
    - Pricing in the Business Transaction
    - Determine Pricing Procedures
    Here the pricing procedure depends on sales organization, division, distribution channel, document pricing procedure and and customer pricing procdure.
    Best regards,
    Thomas Wagner

  • Inbound delivery for Sub-Contracting Scheduling Agreement

    Hi All,
    I am working on inbound delivery creation --> PGR for sub-assembly (Semi-finished product) which we receive from sub-contracting vendor through scheduling agreement. At time of PGR, it should do MVT#101 for sub-assembly and 543-O for raw components.
    I already created JIT/FRC releases and did PGI (MVT # 541-O) for raw components. Now I am manually creating inbound delivery (VL31n) to post PGR. When I am doing PGR with VL60, I am getting below error.
    Any help or suggestion please ?
    As observation, I have seen that in inbound delivery I am only seeing sub-assembly (semi-finished) product. I am not able see "SC Component" tab which I have seen on other environment (ECC 6.0 with EHP4). Is it related to system limitation where we can't do PGR for sub-contracting ?
    Thanks.

    Hi AKPT,
    Sorry if i miss understood but note 352243 says to refer note: 338119
    "In the current release, it is not possible to process the components to be cleared when you post the goods receipt for the inbound delivery. (See Notes 338119, 197864 and 199703 also).
    However when you implement these corrections, the error log is also displayed for the subitems to be cleared and further processing can be carried as described in Note 338119."
    When I refer note : 338119, there is no correction. Am I missing anything ?
    Again my issue is I am not able to perform Post Goods Receipt. Even after doing PGR, if system do 543 for raw component, I am fine.
    Thanks.
    Regards,
    Ravi

  • TPM-FM: pricing procedure determination for budget postings

    Hi Experts,
    We are setting up Funds management for trade promotions in CRM 7.0
    We have set up fund plans and funds with attributes like account/account hierarchy and product hierarchy. When we try to create a budget posting (transaction type BPUP) we get the error message that a price procedoure could not be determined.
    In the IMG we have set up price determination up for procedure 0CRMBP  with condition type 0BPO and checked that the document and customer pricing procedures are correctly stated.
    When we look at the error message we can see that the system is not able to determine an attribute for the customer pricing procedure as we don't have an account/account hierarchy ID on the budget posting transaction. This is only stated on the fund transaction type.
    Any ideas what's missing?
    BR,
    Anne

    Thanks for posting a resolution.
    Regards,
    Anik Roy
    SAP Moderator

  • Pricing Procedure Determination in Service Contract

    Hi,
    When I am creatiing Service contract. I am Getting a Dump  RFC_VMC_COMMUNICATION_ERROR         in the Transaction. I think it is trying to communicate with the IPC Server. I need to deactivate IPC as we are not using pricing or this particular scenario.
    I want to wether there are any BADI for deactivating IPC.
    Thank You

    Hi,
    Plz check the following link.
    Re: RFC_VMC_COMMUNICATION_ERROR
    If helpful kindly reward me.
    Thanks & Regards,
    Anirban

  • Multiple pricing procedure determination problem

    Dear Experts,
    I have a situation in pricing procedure determination. Please advice. The details are given below.
    Pricing procedure is determined for the combination of Sales Org,
    Division, Distribution Channel, Customer Pricing Procedure and Document
    Pricing procedure.
    Say there is a sale happening through following organizational units.
    Company Code: 4260
    Sales Org: 3260
    Division: 02
    Distribution Channel: D1
    Customer: 9000000
    But the material is delivered from the plant that belongs to a different
    company code.
    Plant company code: 4262
    The customer 9000000 has customer pricing procedure maintained as 1 in
    the customer master.
    This will create following documents
    Sales order OR from 3260 to 9000000
    LF delivery
    F2 invoice from CC 4260 to customer 9000000.
    IV inter-company invoice from 4262 to 4260 through following sales area.Sales org: 3262
    Division: 04
    Distribution Channel: 99 (inter-company)
    Here the payer is 4260 which will have a customer pricing procedure
    maintained in the customer master (say 1-standard). The document pricing
    procedure is A.
    The pricing procedures determined for F2 invoice and IV invoice will be
    as per the below assignment.
    3260 02 D1 A 1 PRIPRO1
    3262 04 99 A 1 PRIPRO1
    The requirement is to determine another pricing procedure say PRIPROF
    which is specific to formula average pricing for both the invoice types
    i.e. F2 and IV. The determination will happen from below assignment.
    3260 02 D1 A F PRIPROF
    3262 04 99 A F PRIPROF
    The problem here is that we can not maintain two different customer
    pricing procedures (1 and F) for a single inter-company customer 4260.
    Therefore 3262 04 99 A F PRIPROF assignment is not possible as 4260 can
    either have 1 or F as Customer pricing procedure.
    And 3262 04 99 A 1 PRIPRO1 assignment is already in use so we can not
    replace 1 with F and change the pricing procedure from PRIPRO1 to
    PRIPROF.
    Can you please advice how can we resolve the issue of having multiple
    customer pricing procedure requirements for same customer to determine
    different pricing procedures?
    Thank you.
    WIth regards,
    Sahir Gaulkar

    Hi Ashish,
    Refer this links to understand links b/w the tables.
        http://www.sap-img.com/general/sap-r3-tables.htm.
        http://www.sap-img.com/sap-sd/important-tables-for-sap-sd.htm
    Thanks,
    Swamy H P

  • Shipment cost pricing procedure determination

    Hi experts
    During shipment creation VT01N, system automatically determines shipment cost pricing procedure as SDFC00.
    How does shipment determine this? where can we see customizing settings for this?
    thank you

    Hi Manish,
    The pricing procedure for shipment cost will be determined based on these combination
    Transportation planing point+ Item determination procedure group+ Service agent procedure group+ Shipping type procedure group-->Shipment cost pricing procedure  
    IMG path to do the settings
    SPRO>Logistics Execution>Transportation>Shipment costs>Pricing>Pricing control->Define and assignPricing procedures-->
    Define and assign shipping type procedu
    Define and assign item procedure
    Define service agent procedure
    Maintain pricing proce
    Define pricing procedure determination for shipment. 
    I hope it will help you,
    Regards,
    Murali.
    Edited by: Murali Mohan.Tallapaneni on Jul 9, 2008 5:19 AM

  • Pricing procedure determination in contract.

    Hi,
    I have assigned Pricung Procedure ZRM000 to scema grp of vendor and scema grp of purchasing organization. I can see the pricing procedure in PO and can maintain the pricing conditions.
    But when I am creating a Contract against same vendor and using the same purchasing organization I am not able to see the conditions type which are there in Pricung Procedure ZRM000 and when I am maintaining the condition manually in contract error message is coming as 'Pricing condition is not maintained in pricing procedure RM0000'.
    Why I am not able to see the same pricing procedure or condtionin contract.
    How Pricing procedure determination happens in case of contract.
    Regards,
    Edited by: Sachin on Dec 22, 2010 3:03 PM

    in M/06 , assign ZRM002 to PB00 (or your Z gross price condition) Condition type in "master data" tab ->pricing procedure Field

  • Contract , scheduling agreement and service order

    Hi all,
          Can anybody tell me about the contract scheduling  agreement and when we can suggest our client to go for schedule or contract agreement ?
    Pls tell me elaborately .
    Also Pls explain me about service order and when can i go for service order . whether it is restricted to AMC ?
    Pls explain me elaborately.
    pls explain me steps for creating contract or scheduling agreement and service order..........................
    points to be rewarded.
    Regards,
    Girish.

    Hi,
    Contract is outline purchasing agreement where you have a contract with the vendor,may be a for a predetermined quantity or predefined value. So everytime you need the matl,  you need to make PO ref the contract asking for the delivery of the matl. In such instance when PO is ref with contract its called contract release orders or call off orders. So Process are ME01, ME11, ME31K with aggnrement type, ME51,ME21 & MIGO,
    Scheduling agreement is a long term purchase agreement, where you will keep issuing the delivery schedules whenever there is a change in requirement or at predetermined time intervals. The delivery schedule can be on hour/daily/weekly/monthly basis. SA is also an agreement with the vendor for the supply of matl, may be a quanity or value. The delivery dates will be maintained in ME38 ref the SA which are called delivery schedules.So you can maintain the delivery schedule and communicate the vendor on Forecase basis or JIT basis. And when you need some more matl then will only create SA deliveries using ME38. SA could be of 2 types:- without release documentation-system will transmit the delivery info to the vendor once you save the document.
    With release documentation- after creating the delivery schedules you need to create SA release using ME84.So Process are ME01, ME11, ME31K with aggnrement type, ME38 & MIGO,
    Service order or service PO is created with item Category "D" and an account assignment category as per ur requirement. U can not enter ur material here only u have to maintain short text of material. Example: You want to clean the boiler and u given contract to your Vendor. Vendor sends quotation mentioning that Rs.100/hr/Man head. Now how you will measure the cleaning activities of furnace? You can pay to contractor based on the hourly basis/ man head spent in cleaning activities. So in this case create the Purchase Order mentioning "Cleaning" in the short text in Item overview(Acc assignment ' K' or “C” or “P” and Item category 'D) and item details " Man Head" Service No , Gross price - Rs.100.00 and unit - hour ( or pick from Service master) and Quantity-number of hours spent by all man head.
    The steps to create Service PO are:
    1) Maintain Item Category as D & account assignment such as cost center “K”or slaes order”C”
    2) Keep material code field blank.
    3) Enter description of service & other fields in the PO Item Overview level. Press Enter.
    4) System will prompt you to maintain services at Item Level. Maintain your service master number / service description & other fields (quantity / rate /)
    5) Save the PO.
    For more follow the links;
    For more follow the link;
    http://esoadocu.sap.com/socoview(bD1lbiZjPTgwMCZkPW1pbg==)/render.asp?packageid=DBBB6D8AA3B382F191E0000F20F64781&id=EB65A89F1AFD4C46AB61C6161BAF
    http://www.sap-img.com/sap-sd/sap-sd-scheduling-agreement-vs-contract.htm
    http://www.copacustomhelp.state.pa.us/infopak/nav/procurement/contracting/file1499/index.htm
    http://www.sap-img.com/materials/what-is-outline-and-scheduling-agreement.htm
    Regards,
    Biju K

  • BAPI for creating sales scheduling agreement

    Hi All,
    I have a scenario where i need to create a sales scheduling agreement using VA31. I have tried using a function module "SD_SALESDOCUMENT_CREATE". I am able to create the document by inserting the correct data in "SALES_HEADER_IN", "SALES_ITEMS_IN", "SALES_PARTNERS" and using the update flag as " I ".
    When I try to insert data in "SALES_SCHEDULES_IN" the function module returns error message "No schedule line category could be determined during quantity adjustment".
    please provide help in finding out the right procedure for creating the scheduling agreement with schedule lines data.
    Regards.
    Anurag

    Hi,
    Did you shown this to your functional team.
    Regards,
    Madhu.
    Edited by: madhurao123 on Nov 21, 2011 3:29 PM

  • Creation of PO/Contract/Scheduling agreement with ref to PR using IDOC

    Hi Experts,
    Is it possible to <b>create PO/Contract/Scheduling agreement</b> <b>with reference to PR</b> <b>using inbound IDOC ?</b>
    If yes, please let me know the segment type and field to be populated for referencing PR in the IDoc .
    Thanks in Advance,
    Best Regards,
    Mitesh Desai

    Hi Aarif,
    Thanks for taking time to reply .
    We are palnning to integrate SAP and non SAP systems.
    The business Process is as under .
    (1) PR will be generated in ERP (Manaul/MRP)
    (2) PR will be coverted into RFQ (for which there is no appropriate source of supply
         in ERP)
    (3) Sourcing will be done in non SAP system. RFQ will be created with dummy vednro (for example say "source") to identify RFQs to be sent to another system.
    These RFQs needs to be sent using IDOC alonwith reference PR numbers and line item numbers.
      Multiple PRs will be combined into one RFQ as multiple line items.
    (4) Non SAP system will do sourcing and generates either PO or master outline agreement and have reference PR/RFQ numbers and line item numbers.
    No SAP system will send PO/outline agreement information to SAP system in XML file format to generate inbound IDOC in SAP .
    (5) This inbound idoc will generate PO/outline agreement in SAP.
    From SAP functionality point of view, I ca createPO/outline agreement with reference to PR but <b>My Question is how I can generate PO/outline agreement in SAP through IDOC and using "Reference PR or RFQ numbers".</b>
    Looking forward to help ASAP.
    Regards,
    Mitesh Desai

  • Pricing procedure determination in sales order

    Hi Experts,
    In our business scenario, we have three plants and all plants have different pricing procedure. And we are using same sales area and sales document type for all plants.
    Currently one customer is purchasing goods from only one plant. So in our system, pricing procedure determination in sales order based on customer pricing procedure.
    Now as per new requirement, same customer will purchase goods from different plant. And we can’t change or create new sales area and sales document type as per our existing system design.
    So can we change customer pricing procedure at a time of SO creation level? If yes than how?
    Regards,
    Haresh

    Are you a functional or developer?
    Hope are aware that as per SAP standard,  pricing procedure(OVKK) is determined based on
    (1)
    Sales Org
    (2)
    Distribution Channel
    (3)
    Division
    Customer Pricing Procedure
    (5)
    Document Pricing Procedure
    Sales area determined in your sales order or billing doc
    Determines from Sales Data of Customer Master
    Determines from sales(VOV8)/billing(VOFA) doc type
    In addition to that sales order is created for only sales area, which you select based on your customer sales area while creating the sales order.
    Now, keeping above facts in mind, can elaborate your requirement again.
    Thanks, JP

  • Condition Type in Pricing Procedure Determination

    Dear All,
    I want some clarity in Pricing Procedure determination. As I know in IMG we determine pricing procedure by the combination of Sales Org, Dist. Channel, Division,  Cust. Pricing procedure and document Pricing procedure. There is additional tab Condition type. I just wanted to know the use of that particular field(Condition Type). Please help me to clear this point. Please also give any example if possible.

    Hi Nitesh,
    As u rightly said we determine P. procedure in combination of Sales Area (Org, Dist.+ Channel + Division), Cust. Pricing procedure & document Pricing procedure, in condition Type we need to assign basic price condition type. U may have multiple pricing procedure in combination with sales Area & Doc PP, Cust pp so there u can assign basic price c type which is applicable to that P. procedure.
    Here we assign PP to Condition type, ultimately it captures it in Sales Order condition tab.
    Ex. 1000 10 10 A 1 ZDOMPP PR00 (Basic Price C. Type for Domestic)
          2000 20 20 A 1 ZEXPPP ER00 (Basic Price C. Type for Export)
    Regards,
    Dhananjay

  • Re:Problem in Pricing Procedure Determination

    Dear All,
    I have a problem in Define Pricing Procedure Determination.
    I am getting an error message " Condition Type BP04 is not in procedure ZBP04A A V".
    The condition type has been copied from K007.
    Access Sequence is BP04.
    In Maintain Pricing Procedure, I have selected RVAA01 and copied it as ZBP04A.
    Please let me know how to rectify this error.
    Thanks,
    Amba Prasanna

    hi Prasanna,
    am getting an error message " Condition Type BP04 is not in procedure ZBP04A A V".
    It means in the pricing procedure ZBP04A  the condition type BP04 has not been maintained. So go to V/08, select conrtol data on the left side, click new entries and maintain this conditino type.
    The condition type has been copied from K007.
    You might have copied K007 but forgot to put it in the above mentioned pricing procedure.
    Access Sequence is BP04.
    Also make sure that for your condition type BP04, you have maintained the access also as BP04 in V/06, since you wanted it.
    In Maintain Pricing Procedure, I have selected RVAA01 and copied it as ZBP04A.
    This is fine, in OVKK- no error.
    regards
    sadhu kishore

  • Pricing procedure determination

    Dear Gurus,
    Pricing procedure determination :
    IMG-> SD-> Basic Functions-> Pricing-> Pricing control-> Define and assign pricing procedure-> Define pricing procedure determination
    Sales Org + Dis. Ch. + Div + Customer Pricing Procedure + Document Pricing Procedure => Pricing procedure
    Question :
    When we do the above assignment there is one more column "CType" (condition type) is available.
    What is the significance of this field and how it is helpful?
    Please commnet soon with example.
    Thank you very much in advance.
    Regards,
    Ashish

    Hi Ashish,
    Refer this links to understand links b/w the tables.
        http://www.sap-img.com/general/sap-r3-tables.htm.
        http://www.sap-img.com/sap-sd/important-tables-for-sap-sd.htm
    Thanks,
    Swamy H P