Pricing Schema for Project System

Dear Sappers,
I'm configuring Pricing Schema for Project System(PS) module.
The requirement is, the schema will be in such a way that it supports both excise, CST, VAT and service tax.
In PS module the user raises a Purchase Order having procurement of material as well as taking service from Vendor.For this in PO he will maintain both material as well as service.
I'm configuring the Pricing schema in MM - Purchasing - Condition.
My question is for materials procurement, everything is working fine.But for service respect to activity number I want to maintain service tax and other cess in condition record.
But to maintain service tax & other cess for activity number, I want the access sequence of sevice to be in Purchasing.I've taken the standard table for Plant, Vendor, Purchase Organinzation and activity number combination from External Service management and making a new access sequence in MM - Purchasing.All fields are coming but for Activity number, it not taking the document structure and showing error.
How to overcome this??
Any suggestions will be highly appreciated.
Warm Regards
PKB

Hi Pankaj,
Thanks for your suggestions.
As per you reply, the access sequence is already maintain in External Service Management.But I want to bring the same combination Plant, Vendor, Purchase Organizartion and Activity number that is Table 97 to MM - Purchasing - Conditions- Access Sequence.
I've tried to do it, but when I'm creating in MM - Purchasing, all document structure is copying except activity number.What I analyse the error is due to application area.Activity number is MS (External Service Management) area but i'm trying to do in M(Purchasing)
Even though when I enter manually MS for the access sequence system is not taking.
Suggest me.
Warm Regards
PKB
Edited by: Pranaya Barik on Dec 11, 2009 12:09 PM

Similar Messages

  • Pricing schema for purchase info records

    hi guys!
    does anyone knows either SAP standard got function to define pricing schema for PIR? if yes, can you please tell me how to set it up step by step?
    Thanks a lot,
    crystal.

    Hi,
    there is no separate pricing schema for reading info records.
    When creating PO, the system first searches for a purchasing                
    info record with the combination of vendor/material at purchasing           
    organization/plant level. If there is no such info record, the system       
    then search at purchasing organization level. If there is no such           
    info record here either, you must enter it manually.                                                                               
    If the purchasing info record exist, then valid conditions have             
    priority during price determination. If an info record does not             
    contain any conditions or invalid conditions, the system read from          
    last purchasing document in the info record and then suggest the price      
    from here. The price determined in this way are default values that         
    can be changed by the buyer if necessary.                                                                               
    You can save useful quotation data for a material in purchasing             
    info record. The info record can be created automatically by                
    setting the info update indicator during quotation maintenance              
    in the item detail.                                                                               
    Please first check is there any valid info record exist for this            
    material/vendor. You can always create/change/view it manually              
    via Ta ME11/ME12/Me13.                                                      
    Please read also the notes 392988, 456691.
    Regards,
    Edit

  • Pricing schema for steel industries

    Hi Friends,
    Kindly help me on following issue..
    I am working on a pricing schema (additional information : steel industries and material is being used with varient configuration)
    take a example --there are three vendors suppling different grades of steel , having different material composition..( contains of AL, SL, PH, Mo etc in %)
    suppose supplies will be as -- 0<x<1.2% x .85(multiplication factor)
    0 .12<x<2%x.90
    0.23<x<10%x.98
    If the supplies meets any of the above combination then system should pick pricing schema for that material ..
    I could not able to understand how to link these formulas with a pricing schema and how to trigger if supplies falls under these categories.
    Your earliest response on above is highly appricable
    thanks

    Hi ,
    Thanks for your reply , in the same mail i wish to thank all who has spare their time for ansering to my quires.
    Is it possible in the following way...
    Suppose i ask the quoations from the different vedors ( say Q1 , Q2 and Q3 theree different quoation for a same grade of a material or we can say for which falls in a specified material composition range)
    I will create one ABAP program where in , while creating a PO, system will pick the price from the quotation ( the final quotation - the best one) along with a source of supply , material and the validity period .
    Sytem will do the pricising based on the price picked from the quotation .
    Is it possible .......?
    kindly suggest me if it is possible .. then which thing or table etc need to consider while defining the schema.
    thanks

  • Trabsfer Pricing Treatment in Project System

    Hi,
    Can someone provide me with a brief overview of how transfer pricing work in Project System?
    Do we need to have profit center activated for this?
    In my business scenario, I will have projects which perform work to support other project.
    Under this circumstance, the service provider project would like to charge the service receiver project with certain profit margin.
    I would like to understand how this will work in project system environment and will the margin be charged from one project to the other project as and when the transfer of service happen or this will be charged only periodically?
    If then what will be the basic the calculate the transfer price and margin?
    Thanks for the help in advance.
    Regards,
    Cheah

    hi gurus
    any reply
    regards
    vijay
    Edited by: vijju489 on Jun 2, 2011 11:25 AM

  • Pls give the menu path for pricing schema for PO

    Pls give the menu path for pricing schema for PO
    Thanx
    Vikas Chhabra

    Hi,
    we assign account assignment category in PO.Here is the path
    IMG>Materials Management>Purchasing>Account Assignment>Maintain Account Assignment Categories OME9
    Based on account assignment category you use in PO, it will ask you cost object in PO
    E.g P (project) you need to enter G/L and WBS element
          N Network     G/L and Network
    Like in SD account determination,  OMWB is MM and FI integration.
    Regards,
    Chandra

  • Changing the data in DataSource in R/3 System for Project System

    Can we change the data of DataSource which is extracted from R/3 sYSTEM for Project System Module?

    Hello Rajesh,
    You can modify it in PSA. Or write the routines or rules logic as per your requirement.
    Could you please elaborate more on what kind of changes you are interested for.
    San.

  • Report Painter Drilldown on Cost Element for Project Systems

    I am currently working on a report for Project Systems. I am trying to copy the functionality of the Internal Order summary (60I2-001) into report group 6P3. I was able to copy the whole layout and also the values of 6oI2-001 into a copy of 6PP4-001 but when I double click on "Balance" it is bringin up the ALV report that 6PP4-001 is using. I would like to call another report which looks like 6LS0-001 but contains Project System info made in report painter when I double click on Balance. Is this possible? Please let me know how.

    Hi Avinash,
    See my replies below.
    1 a & B: You are planning Qty on NWA and capturing costs - labor & Equipment on NWA elements.
    When  you are having elaborated to NWA-Element level, split your total work on each NWA-element and post labor cost. Thus you will have planned Vs actual costs at one place.
    coming to equipment cost - are you capturing using PO through GR?.
    2.a : Option1- create a separate WBS elements for materials and plan cost at WBS level. That value would be your total planned cost of material procurement as estimated. Under this WBS elements create NWAs and assign the materials. With this set up you can assign material and procure so that will have actual costs coming from GR.
    Option 2: Create a one General Cost activity and assign the total planned cost of material on this NWA.
    When you assign the material components, diligently you have to reduce the equivalent amount from the general costs activity. Also note that on component screen, you have to check box "Cost relevant" so that material cost will add to Cost NWA. Let the different materials  have their own valuation class and have default CEs accordingly. that would not be big issue.
    Please discuss with your MM team to get more information. Also my suggestion is to leave blank CE field in configuration.
    The option2 is very cumbersome and high risk but one have to be very cautious to reduce the value from Cost NWA in order to sustain the planned material costs whenever they added.
    3. I have answered the relevance of Cost relevance check box in above.
    Hope above makes sense.
    Thanks,
    Sudhakar

  • Planning Profile for Project System

    Dear All,
    In planning Profile (T Code OPSB) for Project System we can find  RElem.f.billing plan ..field, in this field which cost element we have to assign wheather it is sales revenue or secondary cost element cat.31 or else..plz adives me..
    Thanks and regards

    Mr. Sridhar,
    Thanks for ur reply, here my querry is, i have types of sales revenues like domestic, export, industrial etc.. there is only option is there to maintain revenue cost element, so which revenue cost element i have to maintain in planning profile.
    Regards
    Ramesh

  • Business packages for Project systems

    i,
    I wanted to know if there is a business package for Project systems which include transactions like CJ20N, CN33, CN41N, DP81,VA23, VA25. I checked in SDN Portal content portfolio and found there is a BP for Projects 5.3 and BP for Project self service. I checked out the content which is present but not sure whether it suits my requirements.
    Appreciate if any one can point to the right Business package.
    Regards
    PN

    Hi,
    Chk out this link, it points to Project Self Service.
    http://help.sap.com/erp2005_ehp_01/helpdata/en/3f/a197422836c76ae10000000a155106/content.htm
    You can find the prerequisites & the configuration required in the above link.
    For this Business Package you have to install the following software components:
    SAP PSS 600
    BP ERP05 PROJ SELF-SERV 1.0
    Regards,
    Abhishek

  • Differentiating of pricing schema for each purchasing document type

    Dear colleagues,
    This topic could be discussed before but I need to clarify some points.
    We would like to differentiate pricing schema per purchasing document types (e.g. AA and ZZ). These purchasing documents are not like domestic and import types.
    There some condition(s) where purchasing document type AA should not be able to maintain whereas ZZ should be able to.
    In this case shall use one unique pricing schema for both purchasing document types if so how can I hide some conditions for document type AA or if I use separate pricing schema how can I set different pricing schemas for different purchasing document types because both document types have same purchasing organization, vendor etc. 
    Regards
    Metin

    Hi,
    Why to have two different schema groups! Is procurement process is completely different, so use to have!
    (have thought of separate condition types for each Calculation Schema)
    Based on Schema Group Of Vendor in the vendor master, the PO for vendor with respective Schema Group Of Vendor will populate the assigned condition typesu2019. Follow path:
    SPRO->MM->Purchasing->Conditions->Define Price determination process ->Define Schema Determination
    Under segment:
    Determine Calculation Schema for Standard Purchase Orders
    Here you can assign Schema Group Purchasing Organization, Schema Group of Vendor and Calculation Schema
    Under segment:
    Determine Schema for Stock Transport Orders
    Here you can assign Schema Group Purchasing Organization, PO document type and Calculation Schema
    Regards,
    Biju K

  • BTE's used for project systems master data.

    Hi ,
    Can anyone tell me what are the BTE's used for project systems master data.
    Tcode used are CJ01,  Cj02,  CJ20N,  CJ12,  CNMASS
    When master data is changed or created BTE should trigger.
    Regards
    Subin

    I don't think there are any open_fi BTE available for PS master data.
    you can use classic subs/vals using GGB0 and GGB1 transaction codes.

  • Result Analysis for Project Systems

    Hi all
    Does any1 have any documentation relating to Resut Analysis for Project Systems incl POC calculation and other basic concepts. Any help would be highly appreciated.
    Regards
    Hrishi

    Hi,
    Please follow the link below: it has all the details for the POC methods:
    http://help.sap.com/saphelp_46c/helpdata/en/90/ba6f37446711d189420000e829fbbd/content.htm
    Hope its useful.
    Reward points if found useful.
    thanks..

  • Billing for Project Systems without using Sales Orders

    Hello All,
    We are using project systems in our project and we are not creating any sales orders for the same, however I am creating delivery using t-code CNSO and hence the outbound delivery is getting created, my question is can I create a billing document for this delivery and if yes how can I create the same.
    Kind Regards
    Atul

    Hi,
    Yes you can create billing document for this delivery
    Make sure following pre requsites
    In VOFA for your billing type assign document pricing procedure under account assignment/pricing tab
    In XD02 for customer under sales area data >> Billing assign customer pricing procedure
    And last in OVKK in combination of
    sales organization + distribution channel + division + document pricing procedure + customer pricing procedure = Price procedure
    kapil

  • Technical spec for Project systems report

    Hi all,
    My requirement is to create technical spec's on this Project Systems monthly and yearly budget and actual tracking with drill down capability
    And the char and KF are:-
    Char
    Project Definition
    WBS Element
    Cost Element
    Vendor
    Purchase Order No.
    Purchase Order Item
    Requester
    Created On
    PO Description
    Final Delivery
    KF
    PO Value
    Value - Quantity Delivered
    Amount Invoiced
    To be invoiced - Value
    To be Delivered - Value
    Can anyone help me that which standard query is suitable for this requirement.

    Hi,
    Check the below business content queries:
    0PM_MC01_Q0001     Budget Comparison (Actual Costs) 
    0PM_MC01_Q0002     Budget Comparison (Planned Costs)
    0PM_C06_Q0002       Budget Proposal (Periodic)
    0PM_C06_Q0003       Budget Proposal (Objects)
    Check this might be useful:
    http://help.sap.com/saphelp_nw2004s/helpdata/en/e8/858f40f5767d17e10000000a1550b0/frameset.htm
    Hope this helps.......
    Rgs,
    Ravikanth

  • Pricing schema for Quotation

    Hi,
    I have copied the standard pricing schema and done changes according to the business requirement. I have done all other required configurations. The new schema is effective for purchase order, but while maintaining quotation still the standard schema's conditions only appearing in quotation.
    Please advice
    Regards,
    Sattuj

    Hi,
    Check your Gross price condition type in M/06- remove the pricing procedure in it and maintain your new pricing procedure in that field. Or you can define your new supplementary pricing procedure with required conditions and maintain in the base price condition. Then you can able to maintain your other conditions in Quotation or inforecord.
    Umakanth R