Print out confirmation after entering confirmation in CO11n

Hello,
we need to automatically print out an confirmation slip or some kind of document that shows the amount of confirmed materials every time we have confirmed operation 0150 (Co11n) which is always our last production order operation.
Is there a way to do that?
Thanks
Anne

Hi,
Inorder to get the print of any shop floor control papers you to configure the same in SPRO : Tcode : OPK8 against the user and Plant.
If you want to have your specific layout then you need to create a FORM and Assign the same here agianst the Ref Ord , Plant, List, Output devics, SAP Script Form.
You can even give the printer Specification here, which can be assigned to Plant., MRP COntroller and List combination
If you want to restrict at the transaction level it is possible to do here.
Hope this will help you.
regards
radhak mk

Similar Messages

  • My colors are not printing out right after I changed the cartridges/cleaned printheads

    I have an officejet pro 7780 all in one and the colors were starting to fade and I had a message my inks were low so I exchanged the old color cartriges with Hp cartridges, cleaned the printheads and ran all diagnostics and I still can' t get the colors to print correctly.  I hace veen trying to print an orange background and it keeps coming out pink.  I even uninstalled and reinstalled the printer and still the same, ecverything else works fine.

    The troubleshooting steps in this document may resolve your issue.
    Bob Headrick,  HP Expert
    I am not an employee of HP, I am a volunteer posting here on my own time.
    If your problem is solved please click the "Accept as Solution" button ------------V
    If my answer was helpful please click the "Thumbs Up" to say "Thank You"--V

  • Production order print out

    Hi friends,
    i would like to know the configuration setting required for shop floor paper print out like producton order, confirmation, time ticket etc. i have checked execute printing in opkp. in control key, print, print time ticket, print confirmation  are checked . in co04, and co04n i am not able to get the production order print out.
    in opk8 please tell the required confirmation in detail (step by step)
    regards'
    Arun

    Need to do the setting in OPK8
    first check the configutaion link below and then come bsck w/yr doubt
    http://help.sap.com/saphelp_40b/helpdata/en/3a/72369adc56d11195100060b03c6b76/frameset.htm

  • Confirmation Slip Print Out

    Hi Experts,
    Requirement is to have a print out at every confirmation (CO15 - For Order).  How do you print a confirmation slip? 
    I did some research in the forum but they all seem too technical for me, im sorry.  Can you please lead me right through it?  I just need to be able to print a simple print out of the confirmation with the Goods Movement information.
    Thanks in advance!

    Dear
    In OPK8
    Name of the list - LK02, LV02
    Spool parameters - User and plant = *
    Reference operation - Type
    All lists
    Refer this thread,
    Re: Production Order Print Out
    In OPK8 you need to do the setting for confirmation print LV02 Confirmation slip , print program - PSFCCONF, LK02 then you need to active control key for printing in OP00 then assign the control key and printer to work center that is assign to last operation in routing or in production order operation screen.
    Then you can take print in background through COHVOMPRINT, CO04N or OPKV.
    Just check those above and try
    Regards
    JH

  • Confirmation Print Out ?

    Hi SRM Gurus,
    We have SRM 5.0. We would like to take the print out of confirmation. Is it possible? Could you please list the steps to be done?
    Thanks in advance,
    Ramkumar

    Hi
    Have you seen this link -
    GR Printing in SRM
    Regards
    - Atul

  • Label print after TO confirmation

    Hi ,
    I have specific requirment and wonder if there is a standard way to trigger labels after TO is confirmed? Requirement is that we validate SH to from a custom table on staging. If SH matches then we print lable otherwise not.
    Thanks

    I think Yazmin is referring to partner function "SH" ship-to party Manish. If that's the case I believe its possible to print based on a select ship to customer numbers (NACE entries) but it really depends on what output type and other details,
    We need better details please Yazmin
    Where is this output coming from after TO confirmation? (TO, HU, Delivery, Shipment)?
    Is this a custom output type if not what output is it?
    Is the requirement to print or not based on an existing custom table or are you just mentioning custom table as a possible way to access a list of SH partners that you want to print the output for?
    Please provide as many details as possible to get the best answer to your query.
    Kind regards

  • WBS Forecast dates disappears during scheduling after final confirmation

    Hi dear Experts.I faced a problem with WBS dates.
    The system overwrites forecast and basic dates on WBS after final confirmation of attached activities. And start to schedule wbs dates from dates of activities with no confirmation. Is there any way to solve this prolem?
    In other words i need my WBS to take into scheduling ALL the operations forecast date. Moreover how the system can overwrite the forecast dates wich were entered manually by user?
    Green - actual dates
    Yellow (orange) - forecast dates
    Bue - Basic dates
    Please help.

    Hi Kirill,
    Please check the control parameters for WBS Scheduling. Check if the scheduling method over here is WBS Determines Dates. If this is the case, irrespective of the scheduling that was carried out at the activity level, the system overwrites the basic and forecast dates present at the WBS level. May be in your case the scheduling method that had been used was "Network determines dates".
    . Please change this and let me know if this helps.
    Regards
    Varun

  • Printing delivery notes upon picking confirmation

    We wish to only print delivery notes once picking is confirmed and goods ready to go.  We can achieve this in VL02n via amendment to routine 35 in V/27 however generation of output does not appear to apply when picking is confirmed via transaction VL06C rather than in the delivery itself.  Any suggestions as to how to generate reliable printing of delivery notes upon confirmation that picking is complete?
    Thanks
    Birna Rowley

    Hi,
    In the definition of output scheme, set  a new conditional subroutine (define it with VOFM) as 035 (for instance 935), as this coding:
    form kobev_935.
    * Workarea KOMKBV2 is available
      if  komkbv2-kostk = 'C'.
        sy-subrc = 0.
      else.
        sy-subrc = 4.
      endif.
    endform.
    form kobed_935.
    endform.
    Check before with debugging that KOMKBV2-KOSTK has the desired value. After, define the output with VV21 and option inmediatly.
    I hope this helps you
    Regards,
    Eduardo

  • I paid my order right after the confirmation came in, but i don't get a confirmation that i paid, and i paid it about one and a half week ago, what can i do?

    I paid my order right after the confirmation came in, but i don't get a confirmation that i paid, and i paid it about one and a half week ago, what can i do?

    Download from Download CS5 products
    Install then enter your serial number.

  • Reverse Production Confirmation After Usage Decision (UD)

    Hi All ,
                 We are using Quality Inspection Type 04 ("Good Recipt production Inspection ") . We have Done some wrong Entry in Production Confirmation after that quality person also did Usage Decision for the inspection Lot. now we want to cancel this confirmation . will some one help me how we can reverse UD (Usasge Decision) and Cancel the production confirmation .
    Thanks In Advance .
    Regards

    Dear Jaideep,
    Check out this,
    Do you mean to say you want to cancel the document for which 321 movement has been made where the stock has been
    cleared from quality to un-restricted?
    This is not possible,unless if you have used SAP notes,
    Note 1108313 - Cancelling usage decision and lot
    Note 175842 - Inspection lot: Reversal of goods movements from UD.
    Otherwise cancel the confirmation and the error movement 102 will be going to COGI.
    Do 102 through MB31 against that order and delete the 102 error from COGI.
    Check and revert back.
    Regards
    Mangalraj.S

  • I can't log into Tumblr.I'm trying to creat a account there.It goes tosecond stage when asking year and confirmation.After thatstage it is not responding furthe

    I can't log into Tumblr.I'm trying to create a account there.It goes to second stage when asking year and confirmation.After that stage it is not responding further.And I am using win 32 bit with Mozilla 30 version.Please help me some one.bye

    Many site issues can be caused by corrupt cookies or cache.
    * Clear the Cache
    '''[https://support.mozilla.org/en-US/kb/how-clear-firefox-cache?redirectlocale=en-US&redirectslug=clear-cache-delete-temporary-files-fix-issues How to clear the Firefox cache]''' {web link}
    and
    * Remove Cookies
    ''This will log you out of all sites you're logged in to. ''
    Press the '''<Alt>''' or '''<F10>''' key to bring up the tool bar.
    Followed by;
    Windows; '''Tools > Options'''
    Linux; '''Edit > Preferences'''
    Mac; ''application name'' '''> Preferences'''
    Then '''Privacy.'''
    Under '''History''', select Firefox will '''Use Custom Settings'''.
    There is a button on the right side called '''Show Cookies'''.
    If there is still a problem,
    '''''[https://support.mozilla.org/en-US/kb/troubleshoot-firefox-issues-using-safe-mode Start Firefox in Safe Mode]''''' {web link}
    While you are in safe mode;
    Press the '''<Alt>''' or '''<F10>''' key to bring up the tool bar.
    Followed by;
    Windows; '''Tools > Options'''
    Linux; '''Edit > Preferences'''
    Mac; ''application name'' '''> Preferences'''
    Then '''Advanced > General.'''
    Look for and turn off '''Use Hardware Acceleration'''.
    Poke around safe web sites and see if there is still a problem. Then restart.

  • Confirmation of activity types in CO11N

    Dear Experts,
    I have a small issue, while confirmation of production order in CO11N the activity type for the actual quantity is confirming but our requirement is that if we are confirming the half quantity means partial quantity, activity should also be confirmed for the half quantity.
    Thanks & Regards,
    Alok Tiwari

    Dear Bhupendra Singh,
    First of all thank you very much for your reply.
    I am trying to do the way you said but it is not happening.
    My requirement is if the production order quantity is 10 each and planned activity is 10 min for labor and if i want to confirm partially 5 each then the activity to confirm for labor should automatically propose me 5 min.
    Regards,
    Alok Tiwari

  • Production order status was not changed to 'CNF' after final confirmation.

    Hi guru.
    I experienced very special case that production order status was not changed to CNF after final confirmation.
    I did final confirmation and canceled confirmation. (CNF -> REL)
    And I did final confirmation again because of fixing activity quantity.
    the strange thing is that production order status wasn't changed from REL to CNF.
    I did  confirmation again with 0 activity, thereby  I solved this problem
    BUT i don't know why this case happened.
    Please, explain the reason.
    Thanks.

    Hi,
    As per my observation, their is not any change in the status of the order REL with confirmation CNF, instead of this, it has change from CRTD & then to TECO.
       Sequence of the status of the order as below
    1) CRTD MANC NMAT SETC
    2) REL  NMAT SETC - Changes from CRTD to REL after releasing of the order
    3) REL  CNF  PRC  CSER ERTR OPGN SETC -  After confirmation, it updated after the order REL status.
    Rgd,
    Chetan

  • Po print out after making changes in po

    hi experts,
    we r facing a problem ,after making a po when we edit it for additon of some more materials  and take the print out ,only item that were there in po intially are coming , it is not printing all the items that are that are added i po, but po print out is coming ok ,it is showing alll the items,can anybody help why it is coming like this .<b>points will be awarded surely</b>

    Hi
    In Message determination for PO, you have an output type (eg.,NEU) for printing the changed PO.
    This has to be created(if not maintained) and maintained in <b>"Fine tuned message control"</b> in SPRO and it should be <b>ticked</b> in the last column.
    Try this and it should work.
    Pls Revert and Reward.
    Regards
    Vijay

  • Office Pro 8000: Can't Print/Out of Ink Error even after installing new cartridge.

    When I tried to use my printer a few days ago, I received a "Can't Print: Out of Ink" error message concerning the magenta cartridge.  I had used the printer a few days before that, and had not received a low ink warning.  It seemed suspicious to me that I would have received an empty cartridge error message without first receiving a low cartridge warning.  The yellow and cyan cartridges read 70% full - all 3 were original cartridges.
    I purchased a new 940XL magenta cartridge and installed it per instructions.  Now I am getting a message that the new 940XL cartridge is empty.  I can shake the old 940 cartridge and hear liquid inside.  Obviously, the new cartridge is also full.  I've tried cycling power, reinstalling the software, etc, with no change in status.  If I swap back and forth between the old 940 and new 940XL cartridge, they are properly identified by type on my screen as the 940 or 940XL.  Due to the way the problem has presented itself, I don't believe it is a cartridge issue.
    Of course, problem first arouse on May 8th, and my warrantee expired April 26th.  Any suggestions?
    This question was solved.
    View Solution.

    I've solved my own problem, which was clearly a factory assembly defect.  I looked inside my printer with a flashlight in the area where the ink cartridges are installed, and found magenta ink sprayed inside the printer.  I disassembled the printer, and found that the magenta line had been damaged during assembly.  There are four ink tubes which exit from behind the ink cartridges, then make a U turn back toward the front of the printer.  Just after the U turn, they make another bend up-wards.  It is at this point that I found the damaged magenta line, directly above a screw on the right-hand side of the ink cartridge housing.  The lines are in a very narrow passage, and are held in place by several keepers molded out of plastic.  It appears that the lines were put in place in the keepers, then the screw inserted from above.  As I said, it is a very tight passage, and it would be very easy to damage the ink line at that point if the lines weren't carefully held back to insert the screw during assembly.
    To solve the problem, I removed approximately 1/4 inch of damaged magenta ink line.  I carefully cut the line with a sharp razor, to prevent collapsing the line or causing burrs to the tubing.  I then placed about 3/4" of self-sealing heat shrink tubing over one end of the ink line.  Next I spliced the line with a small piece of stiff plastic tubing from the handle of a cotton swab, which was a perfect, snug fit over the ink line.  Being careful not to collapse the ink tube or cause further damage, I gently twisted the ink line back and forth until the ends were butted up inside the cotton swab splice.  I then positioned the heat-shrink tubing over the splice, and shrunk it with a hair dryer.  The heat-shrink tubing I used has hot-melt glue applied to the inside, which further aided in making a leak-proof splice.  Again, there is not a lot of room, so the splice had to be kept small.
    I reassembled the printer, reinstalled the ink cartridges, and powered up the printer.  After the normal, long start-up delay, I printed several full-color test sheets, and all was fine.  The magenta cartridge that I had installed previously now shows that it is full, and the remaining cartridges also read the levels that they had prior to disassembly.

Maybe you are looking for

  • Max No. of Drives in a Raid0 stripe ?

    Hi, I suspect I know the answer already (which is no..) but can i increase my raid from a 2 drive stripe Raid0 to a 4 drive stripe Raid0 on my K7T266-Pro2 onboard raid controller ?? Looking at the Rocket Raid PCI cards you can have up to 4 on a strip

  • SharePoint Online : how to disable properties promotion / demotion?

    Hi,  I working on a solution hosted in SharePoint Online. I need to disable the promotion / demotion feature.  I know it's possible to do it using powershell in an on premise installation, like : $web = Get-SPWeb http://xxxx/sites/xxx $web.ParserEnab

  • Oracle ses Admin password not working

    Hi, The ip address of my machine has changed. So, the admin and search pages were not opening up since they have old ip address. So I went to the files and changed all the occurences of old ip with new one. I was not able to change it in .dbf and .lo

  • Pre-defined program in ECC 6.0

    Hi Experts,   I have a issue that can resolve by u guys,     Please provide the pre-defined program in ECC 6.0 that can stored the program code and all the includes in a program for the given path. Advance Thanks. u r answer will be given points.

  • Soft-Proofing issue

    I'm having hard time understanding soft-proofing even if I watched the video softproofing video. I turned S-P on for a bright and vivid image, create a virtual copy, set target colorspace to sRGB. It tells me that some colors are too saturated so I s