Hello all,
we have a print problem with purchasing scheduling agreements:
when I go to ME38 to the scheduling agreement release docu and print out the latest release which has a zero amount for scheduled quantity, I'll get the error message
no print relevant changes to document xxxx exist.
ME140
I know there are already some threads about this topic in the forums but I was not able to find a helpful answer yet.
Thanks
Anne

hi
please check the message which are already available status is "Green". if its green you have to create another message and you have to print it again..

Similar Messages

  • Scheduling Agreement Release Comparison

    Hi Experts
    does Scheduling agreement release comparison works for JIT delivery schedule (Doc Type LP) in SNC?
    if yes then how it works and how it is different than forecast delivery schedule release comparison (Doc Type LPA)
    Thanks

    Hi Indira,
           The are two ways to address your business case :
    1. The simple way is to forward the work item to the concerned person (by selecting the user from user list) for releasing the work item.
    2. In the second option, we need to modify the workflow. A conditional work item (Accept/Reject) needs to be inserted immdtly after the SA workitem to accept or reject the user decision. Based on the decision, the workitem will either show him the SAP user list to redirect the same for releasing or it should go to the concerned user automatically (in static agent assignment). In case of acceptance, it will go to next step bypassing the rejection loop.
    In case of any further queries, please revert.
    Regards,
    Ashish J. K.

  • Scheduling agreement update with Info record

    Hi,
    My company is working with scheduling agreement both with external vendors and Inter company purchasing. SA is created for a long term (in years) but the price negotiation takes place for a shot duration (One year or less). The requirement is that whenever the Purchase Info record is updated (by department X), it should automatically update the relevant SA (created/updated by department Y). Any delivery schedule created after new effective PIR price, should have the new price and if there is no price in PIR for that date it should throw an error...
    Thanks is advance
    Manu

    Hi..
    Can anyone tell me the user exit that I can use to update price in related scheduling agreements when any purchase info record is changed...
    and another to check purchase info record at the time of delivery schedule creation to see if any valid purchase info record exists ..
    M

  • Scheduling Agreement Release Strategy Issue

    Hi,
    We have a typical problem in Scheduling Agreement Release Strategy.
    Once the SA is released for the first time it should restart the release strategy again if there is a change in Quantity or Value or Purchasing group. The release strategy is getting restart for some of the release strategies and not for others. I compared the characteristics, class for both the release strategies and I am not seeing any difference.
    Can anyone please help me in this regard.
    Thanks in advance.
    Regards
    Ram

    release strategy can be rerigger in case where qty or price change and the changes is over the percentage you defined for Release indicator
    goto release indicator config and in SPRO for release strategy and check the Value change %
    maintian 0.1 here
    so any change above 0.1 will retrigger
    and maintian value 4 in chgable field.

  • Issue with Scheduling agreements created with reference to Contract

    We create scheduling agreements only with reference to contracts. A contract may have multiple Scheduling agreements linked to it. Now the problem is that when a scheduling agreement is being modified, it is creating a lock to all the other scheduling agreements which refers to the same contract. So till the time the user is out of change mode in Scheduling agreement, no other user is able to perform any transactions pertaining to other scheduling agreements (referring to the same Contract)
    Is there anyway that we can address this?? Please suggest.

    The record locks are needed to avoid data inconsistencies. If 2 users would be able to have the same document open in update mode, then how can you decide which entry will be used  for a table update? And what would you tell the other person? (Oh sorry, another user was quicker, please start all over again)
    In some high frequent transactions SAP has developed some options like late locks for good movements, but more often you have to take organization measures like educating the users, and maybe reducing the number of items in a document and creating more documents instead.
    If it is a real big headache then you have to talk to SAP, have to explain the situation, and hope that they either have already a solution or even realize that it is not needed to lock all and can create a solution per OSS note.

  • Delete/Stop Scheduling Agreement Release (Purchasing)

    Hi,
    I have a question concerning releases of a purchasing scheduling agreement in SAP APO. Basically very simple - how can I delete them or at least stop them? I did not find any transaction or report to do so (only for SD scheduling agreement releases). I know that there is a functionality of "dynamic stopping" of release done by the system but how can I do it manually? If there is no such function (which I could not really believe) what would be the business scenario to stop such a release (releases are created by APO, but I manually want to delete them). There has to be such functionality...
    Many thanks in advance
    Christian

    Hi Christian,
    Pl check this document..
    if it helps that would be great for me..
    http://help.sap.com/saphelp_SCM700_ehp01/helpdata/en/22/ec9d3b0ec10670e10000000a114084/frameset.htm
    Thanks,
    Bala.

  • Schedule Agreement release report

    All,
    Is there any report to have the Schedule agreement releases to be generated online or in background?
    Kindly advice.
    Thanks

    Hi,
    Pls go to ME3N, choose dynamic selection on the top
    Release group
    Release Strategy
    Release indicator
    Release status
    Subject to release
    and execute, you get the report accordingly.
    Reward points
    Thx
    Raju

  • How ro delete/cancel procurement Scheduling Agreement Release in APO system

    Hi,
    Can you please tell me the ways to delete procurement schedule agreement release in APO system.
    I have gone through the thread "How to delete the old schedule line release? and found two transactions but it seems both the transactions like /sapapo/cmds_del  & sappao/cmds_sc02 are used for sales scheduling agreement release deletion.
    The system is not allowing me to delete the same in APO system as these are APO scheduling agreements.
    Please help me on the same.Thanks in advance.Revert back if any further clarification is required.
    regards,
    kaushik

    Hi,
    Thanks for your reply again.
    The /SAPAPO/DELETE_PP_ORDER program does not select the release schedule lines though it selects the Scheduling Agreement Schedule Line (Not released) for deletion.
    The transaction /SAPAPO/PWBSRC2 for Deleting External Procurement Relationship but as long as the released schedule line exists , it is not possible to delete the scheduling agreements.
    I have gone through the help.sap.com site and I was not able to found anything about deletion or cancel/closing of Scheduling Agreement Release.
    Still waiting for the solution.
    regards,
    kaushik

  • Deactivate Scheduling Agreement Release Profile

    Hi,
    We have configured scheduling agreement release profile for JIT and forecast delivery schedules.
    For some reasons we do not want to use the release profile, we do not wont schedule line release using ME84.
    Can any one pls suggest how to deactivate the release and also if any other settings has to be unchecked.
    Pls do the needful.
    Regards,
    Neha

    Hi Prashanth,
    Changing the setting from 2 to 1 in source list will not be relevant as schedule lines has to be generated while MRP run.
    I understand that if the material is checked for JIT in material master and when the Doc type is LPA then the scheduling agreement automatimatically goes for release. Correct me if I am wrong.
    Should the config setting for creation profile to be deleted from SPRO settings.
    Pls lemme know.
    Regards,
    Neha

  • Schedulling agreement release output issue/.........

    Hi All,
    This issue is related to scheduling agreement release. I've mentained condition record for doc type/ purch. org/ vendor through transaction MN10 for this.
    Now i am maitaining Delivery schedule for this, but system is not fetching the output type automatically here. Nor its is allowing me to put it manualluy as the whole field is greyed out.
    Can anybody help in resolving this issue?
    Thanks in advance.

    >
    aakansha kumar wrote:
    > Hi All,
    >
    > This issue is related to scheduling agreement release. I've mentained condition record for doc type/ purch. org/ vendor through transaction MN10 for this.
    >
    > Now i am maitaining Delivery schedule for this, but system is not fetching the output type automatically here. Nor its is allowing me to put it manualluy as the whole field is greyed out.
    >
    > Can anybody help in resolving this issue?
    >
    > Thanks in advance.
    Check if your output type is present in the output type determination in the following path:
    Materials Management -> Purchasing -> Messages -> Output Control -> Message Determination Schemas ->  Define Message Schema for Scheduling Agreement Release/Expediter
    Also check the analysis tab while you check the SA release, it will give you clearer idea about the problem.
    Regards,
    Aroop

  • Scheduling agreement release in APO

    Hey Gurus,
    We are planning and releasing scheduling agreements in APO through the product view.  The problem that we are having is that we can't see these released schedule lines in MD04 after the schedule lines are released in APO.  Is there somethign with the CIF that needs to be set up for this?  We already have integration models set up for PIR's and SchAgreements already.
    Also, we checked the /SAPAPO/CCR reconciliation report and didn't see anythign stuck in there   Do you guys have any suggestions for us?
    Sincerely,
    Kris

    Hi Kris,
    Please check the the distribution definition has been maintained for each location
    SPRO:
    Integration with SAP Components
    Integration via APO Core Interface (CIF)
    Basic Settings for Creating the System Landscape
    Basic Settings for Data Transfer
    Publication
    Maintain Distribution Definition
    Publication type: "confirmaiton for scheduling agreement"
    Regards
    Julien

  • Scheduling Agreement Release

    Hi All
    Scheduling agreement is created & released. Release indicator is 6, after the release again some line items are blocked & some line items are deleted without affecting any characteristic of release strategy
    ( No Change in value , Document type , Purchase group on which release strategy is based)
    Wheteher release strategy will be reset in this condition form release to unrelease
    Please suggest
    Thanks in advance
    Regards
    Rajesh

    Hi,
    If no user exit is activated in support for your release strategy, then any change which results in no revision of your original value will not cause any release strategy reset.
    Cheers,
    HT

  • Scheduling agreement created with reference to contract-Issue

    Hi all,
               I had posted a query as how to update net price in the contract/scheduling agreement if the condition price is updated through inbound Idocs.I got the correct answer  as you need to run the report RM06ENP0/RM06ENP1 as per note 685117.
    But now I am having a different issue;the scenario is like: A scheduling agreement is created with reference to contract.So the SA is linked to contract now.I am now going to change the condition price of SA through Inbound Idoc.After the updation ,the condition price gets changed in all cases.
    In one server,I found that the net price gets updated and the link btn contract and SA is broken without running the report RM06ENP1(Ideal situation,this is what I want).In other server ,I found the net price is not getting updated,ie the link is not broken even after running the report RM06ENP1.
    Can anybody tell me why the second situation is happening?

    Hi,
    i have done ur scenario. According to ur scenario, quantity contract is created for 100 units may be kg, pc etc.. Then scheduling agreement is created with reference to that contract but for 200 units may be kg, pc etc.. Scheduling agreement is created without getting any error or warning message.
    In the Next step, i.e. maintain delivery schedule( Tcode: ME38). U get the ERROR message as Scheduling agreement document number xxxxx is does not exist after entering scheduling agreement number in the initial screen of ME38.
    if this information is useful for u, reward me according to ur usage.
    bye
    Narasimha Rao Gunda

  • Schedule agreement releases

    How I will come to know the Schedule Agreement is released or not in ME84? LPA is agreement type.
    ME84 I have executed and next screen green light is coming.
    But while going to ME33L and seeing Release number ,its 0.
    Please explain how I can do this?
    Thanks

    Hi PS,
    You need to output the last relase. Once you process it's output successfully, it would be considered. Otherwise not.
    Any release which is not transmitted, is not considered as valid for use in SA.
    Sanjeev
    Edited by: Sanjeev Shrivastava on Mar 24, 2008 6:50 AM

  • Schedule Agreement release to SUS

    Hello Experts,
    We are implementing MM-SUS. I am new to SUS. Please let me know step by step configuration required to send Schedule lines created (ME38) for Schedule agreement (ME31L) to send to SUS.
    I have run the transaction ME84. But it returns with Error code 26. No data for given selection.
    Thanks in advacne.
    Aakash.

    HI Ravi,
    I didnt get you.
    What to check in XI and what status  you want to know of ECC.
    We have ECC 6.0. All mappings done in XI.
    my problme is when i run transaction ME84, it is not creating any Idoc for DELINS.
    Can you tell me how to get it done?

Maybe you are looking for

  • How can i get my pictures and music from my ipod to my itunes library after having to get a new computer where none of my file exist

    please help i dont know how to do this and i dont want to loose my pictures or music that is on my ipod and not my computer i had to restore my windows and i lost everything but its still on my ipod touch 8 gb

  • N97 crack in screen

    Gday, A most interesting thing happened on the weekend. I left my 5 month old, in as new condition N97 in the car on the weekend whilst in central Victoria during the heat of the day and when I returned I found it with a tiny crack in the screen maki

  • 1Z0-560 Unified Business Process Management Suite Implementation Specialist

    Hi I am a BPM 11g/10gr3 developer based in Mumbai,India and wanted to know the pattern of the exam so that I could prepare accordingly. Is the exam 1Z0-560 a multiple choice question exam similar to the BPM Boot camp assesment exam? Regards, Ritu Sin

  • Rebate VK344 - VK445

    Hi experts, During the transaction VBO3, i try to create a manual rebate payment. I have the following message : "Manual payment is not allowed fot this agreement type" (VK344). So, I try to define a manual payment in VB(2 but I have the message u201

  • Using external monitor with macbook pro?