Problem in cs61 sales order bom

Dear sir
i created  sale order for  item 100  x matrial and item 200 y material ,sales order no 1234.for this sales
order i want to create sales order bom by cs61 . when i create this the system should allows item 100 for x matrial and item 200 for y material for same sales order . but if  i give  material y for item  100 and material x  for  .200also the system allowing to create the sales order bom.this will effict the bom .
so system should not allow to create the sales order bom when i give wrong material to item .
pl give me correct solution for above problem
regrds
Baswa

Baswa,
when you create sales order BOM through CS61 its all together new BOM specialy meant for that sales order - material combination.
To create it you can take referance of Material BOM , but there is no such functionality to restrict the componet changes or quantity changes.
The CS61 its self is meant for creating customer specific BOM , which can be all together different from Material BOM. as in many business its required that , we need to modify our existing BOM on customer request to incorporate that customer specific changes. For all other things standard BOM is there in system and its not affected by this new customer specific BOM.
If you need further help , discribe your need of creation of sales order BOM.
Hope it helps you.
Regards
Ritesh

Similar Messages

  • Find FM or BAPI to sales order routing (CA01) and sales order bom(CS61)

    Hi Experts,
    I just want to find a function module or bapi to create sales order routing.The related transaction is CA01.
    For the created routing, it's releated with sales order number and sales order item.
    And also need a FM or BAPI to create sales order bom.The related transaction is CS61.
    For the created BOM, it's releated with sales order number and sales order item.
    Watting for your response!!
    Thanks a lot,
    Frank

    Hi Experts,
    I just want to find a function module or bapi to create sales order routing.The related transaction is CA01.
    For the created routing, it's releated with sales order number and sales order item.
    And also need a FM or BAPI to create sales order bom.The related transaction is CS61.
    For the created BOM, it's releated with sales order number and sales order item.
    Watting for your response!!
    Thanks a lot,
    Frank

  • Plant change in Sales Order not possible due to Sales Order BOM

    Hi all,
    we are trying to change the Delivery Plant in a Sales Order after the creation of a Sales Order BOM, but it gives a V1773 message first, then a blocking error V1810. The same happens with a Production Order.
    How can we change the Delivery Plant after the creation of one of these objects?
    Our scenario:
    - Make To Order
    - Sales Order BOM created with transaction CS61
    - Sales Order Routing created with transaction CA01
    We need to create the Sales Order BOM on the Production Plant (which doesn't change), but we need to be able to change the Delivery Plant in any time.
    Should you have further questions, feel free to ask.
    Thanks in advance,
    Giuseppe

    Hello Caselli,
    For V1773, please check the solution provided by note 588884, which is a modification. With this note it turns possible to delete all multi-level sales order BOM using transaction CSKB, which may be useful.
    The behavior mentioned by you is the standard behavior of the system. The scenario works as designed, a plant change is only possible as long as there is no other document assigned to the sales order.
    Longtext of V1 810 says:
    The plant can no longer be changed in the following situations:
        2. There is a production order for the order item but it is not a static assembly order.
    Your scenario seems to be point 2 as mentioned above. You can check the requirement type (VBAP-BEDAE) and requirement class in OVZH and assembly type (MNTGA) in OVZG.
    If you change the plant for the items with existing production orders, it will cause the incorrect values in the COPA. An order item is assigned to plant A and the corresponding production order exits. This
    means that the costs are assigned to plant A (this is the place where the costs accrue). Order and production order will be balanced at plant A.
    If you now, after the process has already started, should allow to change the order to plant B the following examples of problems will come up:
    - The costs accrued in plant A (see production order)
    - The SD order is now assigned to plant B, this means billing will be with plant B
    This leads to the fact the costs are on plant A, plant B has a benefit. Plant A cannot settle the costs and plant B has unexpected earnings. Inconsistencies in all involved process steps, SD, CO, COPA are the results.
    If you want to change the plant in the sales order you'll have to perform these steps:
    = Delete the production order.
    = Change the plant of the sales order item from A to C.
      This should be possible unless there are other documents which are already assigned to this sales    order item. Save.
    = Create a new production order and assign it to the sales order item again.
    I hope I am able to help you with this information.
    Best Regards,
    Bhavin Joshi

  • How to compare sale order bom and production order bom.

    i would like to provide report with respect to comparation of sale order bom and production order bom, but i am not familiar with SD and PP, can anyone give me some clue? i only know sale order bom is created via 'CS61', afterwards run mrp to get production order, the process appears complicated, i needn't know the process detail, just want to know how to get sale order bom and relative production order bom. please guide me.

    Hi,
    Check Tcode:CS14 to SD/PP BOM's
    Chidambaram

  • Sales order BOM is not reflecting in sales order

    Hi Guys,
    I have created a sales order in which all the items of the sales BOM (ex:A-a1,a2,a3).have been exploded.My strategy is make to order and i am dealing with valuated stock.
    Now i have created sales order BOM for that particular sales order thro cs61.I have made some changes in the item level (ex:A-a1,a4,a5) in the order BOM i want these changes to be reflected in my sales order is there any way to do so...
    RAMASWAMY

    Dear,
    You have to configure BOM explosion in VOV7 - item category settings - BOM area and you can specify whether it is a single level or multi level explosion etc., Depending on the configuration made here, the BOM explosion takes place in the order.
    Regards,
    R.Brahmankar

  • Reg: sales order BOM

    hi friends,
    can anyone explain me what is SALES ORDER BOM.
    Where it is applicable.

    Dear
    Sales Order BOM are used in Make to Order .If you want to assemble the products and depending upon the assemblies you want to price.   For eg. if the customer asks for a certain combinationa of Material A, B and C respectively, then you create a Material Master record Material D with item category group as LUMF.  While the Materials A, B and C are created with standared item category groups NORM only. 
    Then create a sales BOM using Tcode CS01 and enter the following details: 
    Material : Material D 
    Plant : Plant in which you created the material. 
    BOM Usage : 5 (Sales and Distribution) 
    then give the Materials A, B, and C and give their respective quantities. 
    Before you have to create pricing condition records for Materials A, B, and C. 
    Then configure the item categories ( T - code : VOV4). 
    When processing the sales order, just give the Material D and the system will pick up the corresponding assemblies for that material and populate in the order. 
    The item category for the header item will be TAP and the item cateory for the items will be TAN.
    In this cas the Material D is called as the higher level Item , and all the assemblies are called as the sub items.  Here the subitems are relevant for pricing and delivery where as the header item is not relevant for neither pricing nor delivery. It just acts as a text item.
    However , you can create Sales Order BOM by using Tcode : CS61 .Specify Sales Order, Item , Material, BOM Usage 5 in CS61 and create the same. Activate SO/WBS BOM active under BOM explosion in OMIW or OPPQ
    Regards
    JH

  • Sales Order BOM changes flow to Production

    Hi...
    I am lookign for help  in below scenario.
    We are useing the Slaes Order Boms for our Engineered to Order Material Production.
    But it s aconstant problem that if later on Sales Order BOM is changed some time later its not getting auto
    matically transfered to Production Order change BOM and its literrally a manual process to pass the communication
    from sales to production order and then do the changes in Production Order.which carries a risk always..
    Can some one propose the solution to automate this process..thanks

    Hi,
    It is not possible in STD SAP. Once the planned order is converted in to production order, the link between the production order & the master data will be removed. Then any changes in the master will not reflected in the production order.
    You need to think for some developments.
    Regards,
    V. Suresh

  • BOM Usage and Sales order BOM

    Can some one bring our the difference between BOM usage in the creation of a material bom and a Sales order BOM - To be more specific, when you are creating a BOM using the tcode cs01, I get a field called BOM usage where I can select it as 5 and define it as relevant to Sales and Distribution. I can also create a BOM which is Sales order specific using CS61 tcode. what is the difference between the two? When will the bom created using CS61 explode and when will the other one explode?
    Thanks for your reply in advance....

    Hi
    while using the material in each dept. the usage differs so for that sap provided this function. for sales bom is used only sales and also that material already exist in the plant. and mm bom the material has to procure from the some third party that all functionality will control throgh the maitaning bom usage.
    further your explanation i give below info.
    Text
    BOM Usage
    Definition
    This key defines the area (such as engineering/design or production) where a BOM can be used.
    Use
    By setting various indicators, you can define the maximum configuration of the item status and define whether an item must be or cannot be processed in a particular area (such as production).
    Examples
    A material is used in the areas production and costing in a company. For each area, you maintain a separate BOM with different items:
    Production BOM:
    This BOM contains items that are relevant to production. These items are copied to the planned order. Dependent requirements are generated for them, and they are copied to the production order.
    Costing BOM:
    This BOM contains items that are relevant to determining the material costs of a product.
    When you calculate production costs using a quantity structure, the system automatically determines the BOM and all the BOM items that are relevant to costing, in order to calculate manufacturing costs.
    pls find the config table which will give u clear picture about bom usage.
    STLAN     PMPFE     PMPKO     PMPKA     PMPRV     PMPVS     PMPIN     PMPER     ANTXT
    1     +     .     .     -     -     -     .     Production
    2     .     +     .     -     -     -     .     Engineering/Design
    3     .     .     .     .     -     -     .     Universal
    4     -     -     .     -     -     +     .     Plant Maintenance
    5     .     .     +     +     -     -     .     Sales and Distribution
    6     .     .     +     .     -     -     .     Costing
    7     .     -     .     .     -     -     -     Empties
    8     -     .     -     -     -     -     -     Stability Study
    M     .     .     .     .     -     .     .     External Munitions Display
    Z     +     .     +     +     -     -     .     Rebranding Sales BOM (1:1)
    Thanks
    Regards
    Hari Shankar

  • Sale order bom

    dear sir,
       can you tell be how to create sale order bom(master bom) from the beginning. please give detailed process right from creating sale order. my requirement is to have a single bom which can be changer according to customers requirement
    tahnking you
    arun kumar .r.v

    Hi,
    We need to maintain Material master records for the BOM Item and for the components also.
    The <b>item category group</b> of the BOM items should be <b>‘ERLA or LUMF’</b> and the item category is ‘NORM’.
    To Creating BOM item: Tcode - CS01 
    Specify the data for the following fields.
    Material: Specify the material for which components are to be maintained.
    Plant: Specify the plant of BOM item.
    BOM usage: Specify the application in which BOM is maintained (5 for SD).
    Alternative BOM: Specifies the sequence of a BOM within a group of BOMs.
    (L = stock item                  N = Non-stock item)
    In the overview screen specify the components which makes the main item and the corresponding quantities and save it.
    Note: During sales document processing if we enter the BOM item the system automatically determines corresponding components.
    I   *For the BOM to be exploded in the sales document the following customizing  setting is required.
    A) If the item category group is ERLA the item category of the BOM is TAQ, in the definition of which we have to specify the value A (Explode single level BOM) in the structure scope.
    B) If the item category group is LUMF the item category of the BOM item is TAP in the definition of which we have to specify the value A in the field structure scope.
    II   If the item category group is LUMF the system shows price for the components but not for the BOM item. For this the following customizing setting is required.
    A)     The item category of the BOM item is TAP which is not relevant for pricing, so the BOM item is not Priced.
    B)     The item category of the components is TAN which is relevant for pricin! g, so the components are priced
    III        If the item category group is ERLA the system shows price for the BOM item but not for components. For this following customizing setting is required.
    A)   The item category of BOM item is TAQ, which is relevant for pricing, so the BOM is priced.
    B)    The item category of components is TAE which is not relevant for pricing, so the components are not priced.
    While creating sales document to get the list of alternative BOMs in the definition item category of BOM item we have to check the field “Manual Alternative”
    Rewards if this helps you,
    cheers,
    RC

  • Sale order bom can be used in to process order or not

    To change the BOM for particular order items the sale order BOM can be created , to copy the sale order BOM into production order CO08 can be used , whether the process order can be created with ref to sale order any option is available is SAP

    Hi,
    There is no such transaction for process order with respect to Sale order.If planned order is created with respect to sale order after MRP,that can be converted to process order thorugh COR8 transaction.
    try to explore COR8 transaction

  • Configurable Material as BOM component in SALES Order BOM

    Hi Gurus
    I have following
    1. Material ABC is a configurable material (variant)
    2. BOM of this ABC has further configurable materials
    Is it possible to maintain requried charasterstic of the compoents which are configurble at the time of SALES ORDER BOM CREATION.
    If yes, how. please explain.
    Thanks in advance
    sunil

    Dear Sunil,
    Please refer to the following link:
    http://sap-img.com/sap-sd/sales-bom-implementation.htm
    I will suggest you to visit  http://sap-img.com/sap-sd.htm. It will give you the overview of SAP SD module.
    Moreover there is a separate section of FAQs with answers which will help you in great deal.
    Do let me know in case of any queries.
    Hope this helps you.
    Do award points if you found them useful.
    Regards,
    Rakesh

  • BOM changes reflecting in sales order BOM of delievery completed materials.

    Hello gurus
    i am explaining my requrement. My scenario is like this.
    1.creating sales order
    2.reating sales order BOM
    Next production peole will create production order and will do confirmation of order and Goods reciept.
    3. after this sales people will do delivery of the materail.
    For example yesterday i have delivered one material X.
    Today if i change the super BOM of the material X, these changes are reflecting in the sales order BOM of yesterday delivery done material X also. My client want to restrict thise changes. Pl help me how to resolve this ?
    regards
    srao

    Hi Brahmankar
      we checked for User exits we didnt find. Can u help me out on this regard.
    Can we lock the sales order BOM ? means if we do any changes to super BOM assly level also, these should not reflect to sales order BOM . pl guide me
    regards
    srao

  • Creating material bom with reference to Sales order bom.

    How to create material bom by coping Sales order bom.?

    Mayur,
    Just go to T code: CS01 use BOm  usage 1 & then select the copy from icon in the menu bar.
    On the popup screen enter material no, plat , bom usage =5 (sales bom).
    System will then allow you to select items from Sales bom. Select the items you need copied to Material BOM. Then save.
    Hope this helps.
    Thanks,
    Ram

  • Query related to selection of BOM (Production BOM or Sales Order BOM)

    Hello All
            Am having a scenario wherein the FG is having 5 components out of these 5, two are subassembly and 3 are raw materials, 3 of these components are customer specific i.e. 1 suby assly and 2 raw materials are customer order specific, now what i wanna know is that how shall i decide the BOM, will it be a Sales Order BOM or normal Production BOM. If i go for a Sales Order BOM, can any body tell me the processing of Sales order BOM. For the above FG the packing materials are also cutomer specific and that too is included in BOM. Any help in this regard shall be highly appreciated.
    Regards,
    J K Tharwani

    Thanks for your reply.
          I would like to know am using strategy 52 for this FG, so that i can have option to procure order specific components after sales order arrival, and components which are not specific to the order can be procured before sales order arrival. Where am confused is if am planning with FG1 i.e. am entering PIR for FG1 and am procuring order independent  components before sales order arrival and suppose if the sales order arrives for FG2 for which components i have procured before sales order arrival is same but the remaining components which are order specific are different from that of FG1, then how the MRP shall behave. How the requirement for the FG2 shall be met. Kindly throw some light on this scenario.
    Expecting a positive and prompt response.
    Regards,
    J K Tharwani

  • Function Module for Sale  order BOM

    Hi
    What is the function module to retrieve sale order BOM ?
    thanks in advance
    krishna

    Hi, Your thread has been moved to SD Forum.

Maybe you are looking for

  • I can't update my macbook pro from lion 10.7 to mavericks

    I can't update my macbook pro late 2011 from lion 10.7.5 to mavericks, what I do?

  • IS SENDER IDOC ADAPTER NECESSARY?

    Hi, I read somewhere that to send IDOC from one R/3 system,we need not to create any sender IDOC communication channel,bcoz while creating it we dont specify any technical details. Is it true? Why dont we need any sender IDOC channel?

  • My laptop wont open pdf file

    when I come to open my pdf online it wont open at all.

  • Query builder doens't start

    Hi I am using SQL Deleveloper 3.1.07. If I want to create a view, clicking on the "Query" button inside the general tab of the view properties window doesn't bring up the query builder. Ther's noting in the log window, only silence. Can anybody help

  • Help on writing a query

    Hi,         I was given a task of changing the existing query the COPA. I want to aggregate the last three months data into a single month.     Any suggestions for doing so. Thanks,