Problem in REM Backflush in Repetetive Mfg
Hi
i got the following error when i try to run the REM BACKFLUSH in repetitive process. (MFBF)
" Update control of movement type is incorrect (entry 131 _ _ _ F)
Message no. M7226
Diagnosis
The system could not find entry 131 _ _ _ F in any of the movement type control tables."
if any body having any idea kindly guide me
Thanks in advance
siva
Hi,
Good afternoon and greetings,
Please go through the following OSS Notes
Note 216633 - MB01: Error M7 226 for automatic PO
Please reward points if found useful
Thanking you,
With kindest regards
Ramesh Padmanabhan
Similar Messages
-
Background Job in COGI(REM Backflush error handling)
Hi Everyone.
I have one question.
Our company use REM Backflush .
And Our REM profile setting is next.
- Use GI Backflush at GR posting
- Don't use report point backflush
- Create cumulated and individual postprocessing record
In this circumstance, we use T-code COGI to process backflush error.
When I execute the COGI in online, There is no problem
<b>But, After I make a job for background in sm37, When I execute background gob for COGI, There is a problem. In real, Background gob is will executed. But COGI errors remain as before.</b>Hi,
Actually you should use
Transaction MF47
Program RMSERI11, for post process record.
For post processing , manually entry like storage location and Batch number(if batch management is enabled) is required , if the post process record is created according to this error.
And hence it is not possible to correct all the records by background job.
Thanks
Thamizh -
Missing parts in REM backflush
Hi Gurus....
While doing a REM backflush using MFBF, a problem occurs such that a few of the component materials which are part of a BOM header material are missing. Ideally any material which is a bulk material will not appear in that list. In this case the material is not a bulk material also. While posting the document as well as while reversing the document, the missing materials never appear in that list.Please advice on the same.Dear alapati naveen,
Please clear thse doubts,
1. Are you using a REM profile with reprocessing allowed?
2.If so means while doing assembly backflush,the system posts document for GR(131 movement for the
header material) and GI (261 movement for the BOM component's) for the material which has sufficient
stock to fulfill the requirement and the materials(component's) where there's a deficit of stock in that
storage location or plant goes to MF47(Reprocessing List).
3.In MB03 you can see the list of materials for which full posting has been made sucessfully,it might be
either GR or GI.
4.So you are saying partial GI has happened and so check in MF47 whether that one material other
than the bulk material lies here or not.
Check & revert back.
Regards
Mangalraj.S -
HI GURUS,
I have craeted production version (MOD1)and done product cost collecter ,also complete mfbf (rem -backflush).
My new requirement is,
i have changes bom item and in rate routing i have changes some opeartios and activity types which assigned to MOD1 prod.version.
Now i want do product cost collecter amd mfbf transition with MOD1 version with new changes,can i do .
is it possible....Dear Manoranjan,
In my understanding even if your product is a standard cost estimated material,whenever there is some change in the
BOM/Routing/Rate routing of this part,as explained our other forum friend use T Code MF30 to a preliminary cost estimate or else
goto KKF6N,after entering the part code,plant,select the production version,click on change mode and the cost calculator ikon and
then save the data.
This is a must to do activity once after there are some changes in BOM/routing.
Check and revert.
Regards
Mangalraj.S -
Activity used for confirmation- REM backflush
Hi friends,
I am working on a Z report for getting cost of extra activity posted (Activity backflush) in REM backflush MFBF. Details are available in AFRU but I am not getting table for actual 'Activity type' used for confirmation.
I need this data for each (confirmation number + counter) or Document log.
Please help.
Thanks & Regards,
SandeepHi R Brahmankar ,
Information available in S026, S227 & in MCRI & MCRJ is not wrt (Confir. number + counter) or Doc. logwise.
I couldn't use the FM. What are the input parameters for this FM?
Pl help.
Sandeep -
Dear All,
Can anyone please tell me me the table for MFBF-REM Backflush
Regards
PrashantHi,
What data you are looking for?
However below are the tables used in REM.
SAFK RS Header Master Data
S025 LIS -- Run Schedule Quantities
S026 LIS -- Material Usage
S028 LIS -- Reporting Point Statistics
CEZP Reporting Point Document Logs
CPZP Reporting Points - Periodic Totals
The list is not exhaustive. Let others also add.
Regards,
Rohit. -
Component quantity control in PP-REM backflush
Hi all,
We are fancing the following scenario: a FERT material X is "produced" just packing toegheter 4 units of other FERTs materials X1..X4, without restriction of quantities from each material Xn in the pack. That means a unit of X can be made from 1 unit X1, 1 unit X2, 1 unit X3 and unit X4; and another unit of X can be made of 3 units X2 and 1 unit X4. The only restriction is a unit of X must contain 4 units of Xn.
Is there a way to control this packing scenario through REM backflush? I've created BoM, routings and production version for material X, but i can't find where to control components quantities as descrived.
Thanks in advance for ideas o guidelines in this issue...
mr.Dear Manuel,
1.I'm not sure how this can be addressed through packing materials,but assume you have created 2 different BOM one
containing 1x1,1x2,1x3,1x4 and the other one containing 3x2 and 1x4.
2.Create 2 different production versions one assigned with alternative BOM 01 and the second production version containing
second alternative BOM 02.
3.Create REM profile allowing to backflush using preleminary cost estimate using T code OSP2 and error correction mandatory.
4.Create 2 different product cost collectors for each production version.
5.While backflushing the system picks the BOm components as per the production version and allow to confirm the product.
Check and revert
Regards
S Mangalraj -
Incorrect routing in REM Backflush
Hi Experts,
While doing REM Backflush, after clicking "Actual activities", system is showing previously deleted operations and not showing the added newly added operations, hence these activities are coming in Actual cost.
Where as in preliminary cost estimation, consider the operation correctly .
REM profile is defined with " Post Activities - Using data from prelim. costing f. product Cost collector "
Thanks.
KiranDear Himakar,
A rate routing is a routing for repetitive manufacturing. It enables you to easily reproduce the lean
production process.In the rate routing, the production rate per operation is defined (production time
according to a base quantity). *Set-up time is not usually defined, since no changes to setup are
planned.*
So its not required to mention any value for set up time ,so that its not considered for costing and the
other processes.
http://help.sap.com/erp2005ehp_04/helpdata/EN/60/c6c50f146347e1933b4c15144ec31b/frameset.htm_
Check these links,
Re: Very Strange: SET UP time is not calculated Automatically Even for sta
Re: Set up time not coming while confirming in MFBF
Regards
Mangalraj.S -
Default Valuation type in REM backflush.
Hi,
In the configuration for split valuation (OMWC), for valuation category H (HALB), a batch HM has been defined as - Default: valuation type "in-house production" (DVT InhPr).
This means, for inhouse manufacture, system proposes this valuation type as default.
When, I create a production order for a material with this valuation type, system proposes valuation type HM for the given plant.
Where as, while doing REM backflushing for a material with this valuation type, system does not propose valuataion type automatically.
Why is it so?
Is there any other setting?
Is there any note for this?
Thank You,
-Madhavi.Hi,
Apply following BADI
Goods Movements in Backflushing (Repetitive Manufacturing) BAdI RM_BFLUSH_GOODSMVT
Regards,
Sanjay -
Dispatching problem in REM Planning Table
Hi,
I have encountered a problem in REM planning Table, from REM planning table when i m accessing Bar char planning table and try to dispatch the planned order it is not dispatching the order. I have checked the scenario is previously it was working fine but now it is not working with same settings can u guide me tht which settings affect the planning table dispatch. neither it was showing the capacity requirements, i have maintained the rate formulas is work centre and formula was working fine, i doubt it relate to SPRO settings kinldy give me hints where i can check n wht standard settings i have to make for planning table..Plz give some suggestion on this....
-
Dear pp guru!
I have faced one problem.how to activate reporting point backflush in rem profile.for a particular operation for example
EX: I have 10 operations.I want activate reporting point backflush for 5th operation.plz explain
Thanks
mnkHi Mnk Vekat.
To activate Reporting point, u have set optional or mandtoty reporting point at Rem profile and same should be assigned for Mrp view of materail.
For reporting point Opertaion u have set milestone control key indicator 1 (= milestone confirmation) at 5 th operation. All pervious opreations should have without milestone confirmation control key
Regards
pradeep -
REM Backflush Materials With Serial Number
Hi all,
We decideed to trace some materials with serial number. I have created serial number profile and assigned to the materials. But in REM confirmation SAP does not support backflushing materials with serial numbers. Cause of product cost collector i can not consume the material manually within inventory management.
How can i consume the materials with serial number in repetative manufacturing ?
Regards,
techmaster,Hello
Please check note SAP note 100621.
This note states that repetitive manufacturing does not allow to use serial numbers on the components.
BR
Caetano -
HR data in REM backflush posting
Hello,
I am working in REM scenario and have this REM back flush situation -
During Activity back flush the actual timings needs to be posted against the individual activity.
Is it possible to post these activities against personnel ID which are maintained through HR mini master in REM through MFBF ?
(In discrete we can post the actual hrs against individual personnel ID in CO11n)
I will really appreciate any inputs and suggestions.
Thank you in advance.HI
Check the REM profile assigned to your material and also when you Backflushed the QTY then do post with correction system will explode the BOM and then fetch the qty required then you can edit them there and then save it. you wont be able to see the header material on the next screen but you can see the document generated in MB51or MIGO
Check and revert
Regards
Anupam Sharma -
Dear Friends,
While doing the REM-Assembly backflush, system is not showing the header material (131 movement) in the component screen of confirmation. Actually I want to post the GR into different storage locations. Now system is taking the storage location from the initial screen and posting the 131 movement. Hence I am not able to split the quantity into 2 different storage locations in the component screen. Please let me know, is there any way to show the 131 movement in the REM component screen.
If you need any further clarification, please let me know. Thanks in advance.
Regards,
KNHI
Check the REM profile assigned to your material and also when you Backflushed the QTY then do post with correction system will explode the BOM and then fetch the qty required then you can edit them there and then save it. you wont be able to see the header material on the next screen but you can see the document generated in MB51or MIGO
Check and revert
Regards
Anupam Sharma -
Hello!!
I have a question on how the scrap is posted in MFBF transaction.
If we make 1000 units of a finished goods and 100 of them are scrap. In the MFBF transaction we can do the backflush for 1000 units first, this will leave 1000 units of finished good inventory and also system goods issues the finished goods BOM components. Then when i go in to record scrap for 100 units, system is only goods issuing on the BOM components and it is not reducing the finished good inventory by 100. How to handle this? We want to see 900 units in the finished good inventory.
Bottom line is, business wants to know both the gross units and the scrap for the finished goods.
Also, there is only one scrap movement 551 defined in the MFBF transaction, is there a way to have multiple scrap movements. We wanted to track multiple scraps with different movements depending on when it occurs during the production cycle.
Thank you in advance...Hello,
You can maintain operation scrap, component scrap or assembly scrap and capture the extra goods movement. But this will increase consumption of materials where scrap is maintained. And you get report in terms of the total value (amount) but not in quantity.
What you can do is maintain scrap as one more material in BOM of FG with negative quantity. as by product.
When you backflush, system will list all materials being consumed along with scrap quantity calcuated with reff. to BOM quantity and total FG production qunatity. If you feel that scrap generated is different then you can change the quantity also here. You can define different store location to recieve the scrap quantity.
For Scrap movement type is 551 which is used in REM Profile.
Hope the information is useful
regards
Maybe you are looking for
-
CS6 problem. When I open the Mask panel, it takes up the entire screen width and the Looks controls disappear, Also, there is a new panel below the Mask panel that seems to have no purpose that I can find. The documentation says "Mask and Look panels
-
Get JSF objects in a Filter Class
Hi! I have a problem with my JSF application. As the most of the web applications I have a login at the begining and I place a Listener - Filter classes for catching the session timeout to returning the user to the login page. All this works OK. The
-
My iPhone 4 won't sync to iTunes 10.4 on MAC OS X 10.6.8! HELP!
When I connect my iPhone to my Mac, iPhoto runs but iTunes does not pick up the device. What is the problem? Do I have to reinstall itunes?? if so, how do i do that??
-
Lookout limitation​s and selection of the computer system for lookout
This is regarding the limitation of the lookout i.e. upto how much IO lookout is reccomended to use. or it is on the basis of the l4p or lks file size basis. Do you have some criteria for the selection of the computer system for lookout on the basis
-
[SOLVED] Authenticate with the current user instead of root on GNOME