Problem: Scheduling Process Orders.

Hi,
I have a problem in PPPI with scheduling in Master recipe and with the process order in CM25. Can you help me?
In Master Recipe:
I create a capacity category 0025 to display for a resource the setup formula and Processing formula in the Scheduling Tab (as the capacity category 0001 - I also tried to let the capacity category 0001 be used in application C - Master recipe and didn´t work).
In OP40, I created and assigned in applications to C Recipes
Afterwards, I ordered the views in OP13.
When im creating a resource, i prove the formula and i have no problem. But when I assigned it to the recipe and the recipe to the production version to make a process order, neither the master recipe or process order schedules the order.
When I create a resource with a capacity category 0008 (standard) the scheduling works just fine in the process order.
Scheduling in CM25:
Also when Im trying to schedule the order in CM25, I see two lines of the same order (i guess are the 2 phases 0010 and 0020), is there anyway to just see the second to avoid misunderstanding?
Thanks in advance!
AM

Dear,
For FIFO you can use the Characteristic  LOBM_LFDAT for FIFO if is LOBM_VFDAT then in plant storage data 1 view maintain the SELD then assign these Characteristic to class in CL02 then assign this calss to material master.
Then craete sort rule in CU70 withCharacteristic  LOBM_LFDAT or LOBM_VFDAT
then assign it to serch strategy in MBC1 or COB1 with selction criatoria.
In OPL8 assign this serch procedure.
Then create the order and check the result.
Regards,
R.Brahmankar

Similar Messages

  • Problem in process order creation.

    Dear Sir/ Madam
                             i am facing a problem while process order creation.
    the problem is:
    Error when calculating cost for order ATFEDEC11  "see log Log is deleted when saving
    Do you still want to save?"

    Hi,
    The log for production order preliminiary costing is not saved. Therefore, once the order is saved, there is no log available anymore (this is by the way a question of PP; none of the logs is saved).
    Hope that helps...
    Regards,
    Declan

  • I have Problem in Process Order ,

    Dear , I have Problem in Process Order ,
    See we have Numbe of process order , that status is REL CRCR DLV PRC CSER BCRQ BRRQ GMPS*
    Now i want to Mass TECO all order , but i can not TECO because status should be CRFI ,
    So
    1) how can i change staus all order at once to CRFi?
    2) Can i do the TECO in staus CRCR ?
    3) Any other solution
    REGARD
    SAP

    Hi,
            It is NOT possible to do the process order TECO with the status CRCR , this has to be changed to CRFI
    you can change the status to CRFI  from CRCR in the following way
    1) go to CO54 -T-code
    enter the plant & Date range
    enter the process message category PI_CRST ( sap std) or relevent category defined for you plant
    select the to be sent option
    2) here you will get list of process messages related to control recipes, click on the SEND (ctrlshiftF12)
    process message will be processed & Control recipe status will be cahnged to CRFI for CRCR
    Thanks,
    Rajaniaknth

  • Problem  with Process Order Scheduling..

    Dear Experts,
    i'm stucking with the scheduling of a process oreder.
    I've maintained all scheduling parameters into OPUZ except "selection ID" for detailed scheduling as it is grey & not allowing to fill any entry into it.
    I've also maintained production scheduler and other relevant settings into master recipe & resource regarding scheduling .
    Still i'm getting the error"Scheduling parameters for process orders have not been entered" message no CT609.
    Kindly help me out , where i'm wrong
    Thanx in advance...

    Dear Dennis,
    Ensure the scheduling parameters in OPUZ for the order type,plant combination and for all (* )scheduler you have maintainied
    the scheduling type,the check box for scheduling and generate capacity requirements under detailed scheduling is set.
    Check and revert back.
    Regards
    Mangalraj.S

  • Problem during Process Order creation

    Hi,
    I have problem while creating Process Order.
    I have maintained all the basic data required to create the process order.
    When I Release the order, I am able to create the control recipe also, but PI sheet is not generated along with it. System gives the message "No PI maintained in customising for CRD for which control recipe is to be generated "
    If I maintain the same, then system is unable to create the control recipe.
    What may be the problem here? What i can do to rectify this situation?
    Pavan

    Hi Pavan,
    1. Maintain PI in SPRO of process management
    2. Assign this PI to one of phse in master recipe
    3. Plz check wheather ur created Control receipe destination or not.
    4. if not then maitain the same in Spro.
    5.Check the ordre type dependent parameter i.e COR4 from SPRO
    see the Control recipe gerated in REL phse else maintai the asme in production scheduling profile.
    if possible plz send the sctren shot fir the same to
    [email protected]
    Regards
    Siddhesh

  • Problem creating process order with ref of sale order

    Dear all,
    Kindly give solution for this scenerio..............................
    I am creating Process Order with ref of sale order manually in cor1. In the COR1 screen copy from field i gave my ref sale order, so that particualr order and batch is assigned to that order only.
    My problem was suppose if sale order is created for 10 tonns, but my batch size and resource capacity is 2 tonns only. so first time i change my batch quantity 2 tonns instead of 10 tonns and created my order and confirmed.
    if i go to second time the same process i am doing creating process order with ref of same sale order but it comes again 10 tonns instead of 8 tonns. why it comes like this already i confirmed 2 tonns in this sale order?
    my requirement is if any process order is created with ref of any sale order and again if i am creating any process order with ref of same sale order left quantity only system should show.
    for this what i have to do kindly help to this
    regards,
    s.sakthivel

    Dear KK,
    Pls check whether ZKIN, ZKQT, ZKOR have all the properties similar to IN, QT, OR respectively. If they are different, please ensure that you know the reason why they are different. This check has to be done at tcode VOV8
    Some fields like sales document category, Transaction group, screen seq group, Doc pricing procedure need to be similar to the parent document unless you know why you have changed them.
    Once this check is done, check the copy controls in VTAA. Before that try creating these documents separately without reference. This shoudl work fine only after which you need to check copy control. If this is not working fine, then there is some problem with the document type settings in VOV8. Testing this is possible only if Reference mandatory field is left empty. Make sure that is properly configured.
    Once this is done, check copy controls in VTAA. You can just copy the copycontrol between IN and QT and QT and OR and create for ZKIN to ZKQT and ZKQT to ZKOR.
    Once this is done, check whether your item category settings are properly done , also the schedule line settings. The tcodes are VOV7, VOV6, VOV4, VOV5 etc.
    Now check whether your material master and customer master are consistent with the item category settings(Item category group).
    Now create the transaction. It shoudl work fine.
    Reward if this helps.

  • Problem in Process Order - Urgent

    hi i have a problem in COR2.
    After creating the process order i TECO Technically complete the same,
    and when i save the process order the system just hangs.
    When i debugged the code i found that issue is inside the functional module CO_ZV_ORDER_POST - Create/change end routine order.
    It does not do the commit work properly. this is in PRD so please help me to resolve this
    I checked for other system and the process order gets saved.
    What should i do
    please help

    Please check the OSS note - 1041204 - Controlling COMMIT WORK in production order BAPIs
    Hope this helps you.

  • Problem in Process Order

    Hi!
    While creating Process Order, storage location is getting filled by default in Material list. The Issue storage location has been kept blank in MRP 2 view of material master.
    Can you advice where can be the problem.
    Thanks in advance.
    Regards
    Dinesh

    You will find in the Production version
    MM02- MRP4 production version--details
    Proposed issue storage location for components
    The proposed issue storage location is used in Repetitive Manufacturing for components for which no issue storage location has been maintained in the BOM. The goods issue of the components are then posted from this issue storage location.
    Dependencies
    If you want the system to use this proposed issue storage location in MRP and in the Repetitive Manufacturing backflush for withdrawing the components, you must make the necessary settings in Customizing for either MRP or for Repetitive Manufacturing. Here, you must define the storage location determination strategy, Only assembly per MRP group by entering the indicator 2 in the ISLoc field.
    You use this procedure when all components lie in one storage location together close to the production line where they are required.
    Regards
    Ratan

  • Problem with process order resource selection condition

    I face a problem while trying to release process order as i am getting an error as "Resource XXXX assigned to operation 20 does not meet resource selection condition".What may be the reason for this.how to check and rectify...
    Please help.

    hi,
    I think you have been using a work center in place of resouce.
    Actually
    Resource catagory = 0008 is assign to Application C (Recipe) & only use in Recipe Creation.
    Work Center catagory = 0005 is assign to Application N & R( Routine & Refernce operation set) & only use in Routine Creation.
    Parminder

  • Problem with process order settlement

    Hi,
    I'm having a problem while doing settlment for process orders. I have two types of process orders AJWV and AJW0; AJWV works for center 2000 and AJW0 works for center 1000. When I calculate variances both work good. The problem comes when I try to settle them. For AJWV orders there are three finance documents generated, FI document, Controlling document and Profit Center document. But for AJW0 it's just generated Controlling document and Profit Center document.
    Both order types have the same settlement profile assinged
    The settlement rule for both orders is to Cost Center, full settlement 100%
    Both orders are produced for Sales order with valuated stock
    I already checked the account assigment for the materials corresponding to each order, and both account determination are ok.
    What can be the problem so the AJW0 is not posting to FI variances?
    Thanks

    Hi,
    Yes for AJWV the FI entry was generated.

  • Problem in Process order confirmation ( while doing batch splitting)

    Hi All
    In our Industry we have sceneraio
    we create Internal order and assign internal order to sales order
    Once MRP run take place
    Planned order created and converted to process order
    Process order released
    once we try to do confirmation of process order
    example suppose process order header matl qty : 8
    and in final confirmation while Goods receipt(101) of Fert
    we do batch splitting (example 4 batch : each qty : 2)
    but some time system not allows to do Goods receipt (movement type101)
    system gives "Error confirm order not allowed"
    please need urgent help
    Thanks in advance
    Sunil Singh

    Hi Sunil,
    During your first confirmation you must have activated "Final confirmation" Indicator, probably this is blocking from further confirmation.
    Please check whether current system status of the order contains "CNF" if so, please cancel the previous confirmation and then redo confirmation with "partial" button active. Final confirmation should be activated only when it is the last confirmation for the order.
    Hope this will resolve the problem, reward your points....
    Regards,
    Prasobh

  • User Status change problem in Process Order

    Hi,
    We are in process of upgrading our system from 4.6C to ECC 6.0. I have a problem with User status change for process Orders.
    In 4.6C we are using the profile x with settings:
    10     ZNEW     Created process order     10     90     1     1     ZSTA
    20     ZLCK     Locked process order     20     90     1     1     ZREV
    30     ZOPN     Reopened process order     20     90     1     1     ZOPN
    40     ZMST     MES order started     20     90     1     1     ZMST
    50     ZMCL     MES order closed     20     90     1     1     ZMCL
    90     ZTEC     Technically completed      20     90     1     1     ZTEC
    In ECC 6.0 we also use the same profile settings as above.
    The problem is in ECC 6.0 when I do a goods receipt the User status changes to ZTEC . The process followed is ..Create process order, Release Order, Goods issue, Phase partuial confirmations, Goods receipt and then Finla confirmations of phases. Now in 4.6C if i do the above process the User status remains at ZMST and it only changes to ZTEC when i technically complete the order but in ECC 6.0 when I do a goods recipt from above steps the User status changes to ZTEC. THis should not happen.
    Any pointers will be very helpful.

    Hi,
    The log for production order preliminiary costing is not saved. Therefore, once the order is saved, there is no log available anymore (this is by the way a question of PP; none of the logs is saved).
    Hope that helps...
    Regards,
    Declan

  • Sched.start date not allowing on week-ends for fwd scheduling process order

    Hello Experts,
    For a process order & scheduling typr forward/in time if I take sat or sunday as a start date then if I click on schedule, system changes it to previous workin day (friday). But however if i select backward/in time scheduling type & put week ends as finish day then system does not change this date.
    How can I make system to allow schedule start date on week ends also for forward/in time scheduling type. in a factory calendor sat & sunday are holidays. while for work center, calender sat & sunday are marked as working days.
    Thanks for advance,
    Vijay.

    Hi
    it depends upon client requirement.you must have defined the holiday calender as well.if you select the public holidays in your factory calender.then system will allow you to do your daily transctions on public holidays as well and vice versa.so better go with all options selected .and plz check at your end
    plz revert back if it works
    Regards
    Anupam Sharma

  • Scheduling Process Order

    Hi
    Iam using collective  process order with one subordinate order.
    All Phases are having relationship. First phase 0011 has predecessor 0888
    When i reschedule header order individually then schedule dates and basic dates of header order changes in increasing order with each rescheduling of header order individually.  Iam using floats before and after production.
    This happens while rescheduling  header order individually and does not happen with subordinate order.
    But when i add dummy  start operation and phase  without any resource then system does not change  schedule dates and basic dates of header order changes in increasing order after rescheduling header order individually. 
    Is this standard behavior or Bug?
    Please could you check in your system and let me know reason.

    Hi Mayuresh,
    Please check your Master recipe activity hours, the system calculates the scheduling dates based on it and OMDW transaction-for rescheduling horizon,tolerance value forward/for displacement.
    Best Regards,
    Sriramm

  • Batch determination Problem in process orders

    Dear Friends,
    i am getting problem of BD for components in process order that the FIFO sequence is not
    showing.
    !. I have made settings like Strategy Plant/order type
    2. Charecteristic in the class and sort rule LOBM_VFDAT
    3.  Class assigned to materials.
    4.  raw materials batches have maintained Ex.date, date of produced(at the time of GR by 561)
    5. Order type i have assined search Proc.
    in the order strategy info showing sort rule correctly in theprocess order, But the sequence it showing
    is neither with GRn date or not with Exp date.
    kindly guess what might be the problem...
    Regards
    Robert

    Dear,
    For FIFO you can use the Characteristic  LOBM_LFDAT for FIFO if is LOBM_VFDAT then in plant storage data 1 view maintain the SELD then assign these Characteristic to class in CL02 then assign this calss to material master.
    Then craete sort rule in CU70 withCharacteristic  LOBM_LFDAT or LOBM_VFDAT
    then assign it to serch strategy in MBC1 or COB1 with selction criatoria.
    In OPL8 assign this serch procedure.
    Then create the order and check the result.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • BAPI not able to connect with Livecache

    Hello All,    I am using "BAPI_PIRSRVAPS_GETLIST" .    But not get pegging detail. When I debug it is not able to connect with livecache.    How to use BAPI FM in Program, How to connect with livecache ?    Anybody has sample ABAP program for this ?

  • Windows 8.1 WDS Installation cannot continue because a required driver could not be installed.

    When i try to deploy a custom Windows 8.1 Pro Image Via WDS I get the above error. I have enabled Client side logging and checked WDS logs and install logs on the failed installation (Shift+F10). I don't think the issue is a matter of the drivers tha

  • The Infromation on the web shifts to my right .

    When I open my Mozilla Firefox my search bars shift to the right of my screen. Also all my infromation is to large to fit my screen the complete rigt side is inable to be seen. I've tried to reinstall it and it continues to do the same thing .

  • Calling CATT through report program

    hai folks!       well i am facing some problem while working with CATT. i am making use of the transaction VT02N. my problem is i am passing some records to CATT by using   excel sheet.here some records are processed succesfully   and some are not.no

  • Aperture and Sync

    I have read some of the posts but they don't seem to work. I just bought a 16 G iPad and am trying to sync my photos. For example, I have some pics called Twins. ( my new twin girls). There are 300 pics of them. When I sync, only three show up on the