Problem with goods movement during operation confirmation

Hello,
While doing the operation confirmation,the goods movement are not posted for the components attached to that operation i.e i am not getting the quantity of the components in the "goods movement" tab while confirming.
check points done: 1) Final confirmation tick is activated during ope. confirmation.
                             2) Backflushing is activated for material(componenets that areattached to that operation).
please let me know what is the reason for not getting the qty displayed in the "Goods Movement" tab
Thank you.
Regards
Santosh

hi
Normally if you activated the backflush for the material in the order,the material wont be displayed in the goods movement tab unless you activated the All materials in the parameters for confirmation in the intial screen of IW41
kindly check
regards
thyagarajan

Similar Messages

  • Problems with goods movements cancelling network confirmations

    Hello experts,
    I'm having some problems with goods movement when cancelling network confirmations.
    I assign a component for a operation in the project builder (CJ20N). Then when I execute a confirmation for that operation in CN25 everything works correctly, I can assign the time for the confirmation and SAP automatically carries the component assigned to the operation. Once I have done the confirmation the goods movements and the hours have a correct account assignment.
    The problem is that if I cancel this confirmation, the hours are correctly cancelled but the component is still there. If I try to cancel the goods movement with MIGO it is no possible because the system says that must be cancelled with the corresponding transaction (CN29) but, as I have said, the system does not cancel it.
    On the other hand, If the goods movement goes to COGI transaction and then I post-process the error, If later I cancel the confirmation, everything works correctly.
    Does anybody know why this could happen?
    Thanks and regards
    Laura

    Hi
    I think this question was raised earlier also. The best way is to allot a fixed time slot for your users so as to avoid clash. I suppose i explained that the master data of any material is stored at one place only and if you schedule a background job for this then all your good movement transaction will be in que and performed in orderly manner.
    If automatic posting is not possible then use the time slot method.
    Krishna

  • Goods movement during operation confirmation

    Hi Gurus
    Currently My system is backflushing all the components when i partially confirm the operation through Co11n T-code, which i dont want. I want the backflushing should happen only after the final confirmation of the operation.
    Is there any configuration change required to stop the backflushing only during partial confirmation.
    Thanks in advance,
    Quantum.

    Hi
    In SAP U can do backflush in 3 ways
    Indicator: Backflush
    Determines whether the backflush indicator is set in the production order. Here, a 3-level hierarchical logic is applied:
    1. In the routing, the backflush indicator is set in the component assignment.
    2. In the material master record, the backflush indicator has the characteristic "Always backflush".
    3. In the material master record, the backflush indicator has the characteristic "Work center decides",
    the indicator being set in the work center.
    If at all u dont want to Backflush at the time of Confirmation in CO11N, partial confirmation , dont set any backflush indicator in any level, u can go for Manual Goobs issue Using MB1A, So that u can confirm Goods issue , and final component u can confim By setting Auto goods recipt with the help of Control Key for the last operation in routing.
    i Hope this will help.
    madhu

  • Error in Goods Movement during order confirmation

    Hi,
    I am trying to confirm a production order through CO11n,but i am getting an error in Goods Movement .
    The following message is displayed in the log -  "* Posting only possible in /11 anperiods 2008d 2008/10 in company code A100*".  Can any one guide me what should i do to confirm the order without any error in Goods Movement,
    Thanks in advance.

    Hi,
    It is advisable to correct the Goods Movement Errors in COGI in the same period (before closing the period by MM in MMPV). You cannot correct the same if the period is closed.
    Only option is you need to open the closed period in consulatation with FI and MM team members
    OR
    Delete the Error movement records in COGI and post the Goods Issue for the production order in Tcode : MB1A with movt type 261 and go inside and mention the materials which you want to issue to the order.
    Hope this will help you.
    regards
    radhak mk

  • Error in goods movement during confirmation

    I get an error while doing the goods movement during confirmation stating that posting is not possible during that period.

    Hi,
    If it is MM Posting period problem then check in MMRV and MMPV ..
    In MMRV - u can allow posting to previous periods
    In MMPV -U can close and open periods i think
    If it is CO posting period problem then check in OB52 , Here to get posting period variant for your company code from OBY6 and input in OB52 and check for all accounts the periods , change the periods accordingly for the year..
    regards
    pushpa

  • Hi, I have problem with importing MOV files from SJCAM 4000. MOV files are in supported formats for Adobe Premiere Elements 11. But if I'm importing MOV file, only audio part is imported, video part is not imported. How can I solve this problem?

    Hi, I have problem with importing MOV files from SJCAM 4000. MOV files are in supported formats for Adobe Premiere Elements 11. But if I'm importing MOV file, only audio part is imported, video part is not imported. How can I solve this problem?

    haben
    From looking at the specifications of your camera (SJCam 4000), we know already what video compression your camera is using. It is H.264.
    A H.264.mov file should be supported by Premiere Elements 11. On what computer operating system is your Premiere Elements 11 running?
    Do you have the latest version of QuickTime installed on your computer? And, are you running QuickTime and Premiere Elements 11 from a
    User Account with administrative privileges? Please go to Premiere Elements 11 Publish+Share/Computer/QuickTime to confirm that you find
    presets there for the QuickTime choice there.
    What are the properties of these H.264.mov files - is it 1080p30 (1920 x 1080p30)  or something else? Do you know if this camera is recording with a variable or
    a constant frame rate?
    Please review and consider and then we will decide what next.
    Thank you.
    ATR

  • Does anyone have problems with iTunes movie rentals freezing in the middle of the movie?

    Does anyone have problems with iTunes movie rentals freezing in the middle of the movie, requiring a force quit, which causes your rental to disappear? This has happened multiple times to me recently. Last time Apple didn't refund my money after reporting the problem. I have been using iTunes for many years but am about to give up.

    Correction: I was refunded for the previous movie freeze.

  • HT203200 Is there a problem with redeeming movies from itunes?  I purchased some movies with digital copies.  But I can not download, due to Code redemption being temporary unavailable for the past 2 days.

    Is there a problem with redeeming movies from itunes.  I purchased some movies with digital copies.  But i can not download movies, due to code redemption being temporary unavailable.

    Hi there Cedric!
    I have an article here for you that I believe will help you out with this issue by reporting it to iTunes. That article can be found right here:
    How to report an issue with your iTunes Store, App Store, Mac App Store, or iBookstore purchase
    http://support.apple.com/kb/HT1933
    Thanks for being a part of the Apple Support Communities!
    Regards,
    Braden

  • Dismantling / Installation with Goods Movement

    Hi,
        I have a doubt in Dismantling / Installation with goods movement. How it works? What are the prerequisites are there?
    Please guide me.
    Regards,
    Maheswaran.

    Dear,
    The below SAP links should be helpful
    [Refurbishment Process|http://help.sap.com/saphelp_47x200/helpdata/en/5b/ae3bf14b8611d182ba0000e829fbfe/frameset.htm]
    [Dismantling and Installation with Goods Movement.|http://help.sap.com/saphelp_47x200/helpdata/en/a2/599e8e2a9d11d68d760000e8284931/content.htm]
    Regards
    Alfred

  • Goods movement in QC confirmation for inprocess operation

    Dear Friends,
    I am doing inprocess inspection for routing operations. After results recording, I get the window where I am entering yield.
    If I go to confirmation tab, I can enter the activities and qualntity. But ther I am not getting goods movement tab.
    I want assign batch no. to material in the goods movement tab.
    How can I get it?
    Please help me.
    Waiting for reply!
    Thanks!
    Kiran

    No Inputs?????

  • Good Movement at the confirmation of an operation

    Dear All,
    I tried to make good movement when I maked an confirmation for an operation.
    I configured whit TC: OPK4 automatic good movement and whit TC: OP67 I choosed option automatic good movement for control key.
    However, when I maked an confirmation (TC: CO1F), the system didn't propose the material from BOM, for issues, or the finished good to get in stock.
    And an additional question: if I have many operations on the routing and each of them have the same control key (PP01, for example) the system cannot accept any automatic good movement.
    What can I do in this case?
    Thank you very much for the answers.
    Regards,
    Marian

    Hi,
    You are trying progress confirmation right...
    As per my knowledge for production order confirmation you could findth egoods movement...
    in CO15 or CO11N...
    For th e second question if u have N number of operations then you could confirm operation wise in CO11n and for first operation goods issue and for the final operation goods recipet will happen
    Regards,
    sravanthi
    Edited by: Sravanthi683 on May 21, 2009 10:34 AM

  • Goods Movement Qty While Confirming the Order

    Hi Friends,
    While confirming the order The end user Will go to the goods movement screen and enter the actual consumed Qty (When all BOM components Are marked with automatic Back flush) For the components with 261 movement type and will enter the storage location and batch no if required .
    Now my requirement is the user should not have the access (it should be in gray) to the BOM Components qty to change
    OR
    He should not be able to change beyond the qty As per scrape % Given in Material Master or BOM.
    The Reason for this is
    Even When there is a shortage for BOM components in SL location, he is reducing/Adjusting  the required quantities as per the existing Qty ( If there is no stock then making it to ZERO also)  and confirming the order.
    Pl suggest me is there any user Exit for this or can I do it thru Standard SPRO settings.
    hari

    Hi,
    You  can make screen variant SHD0 for CO11N and hide it.
    In t code SHD0, give the transaction variant name ( say ZCO11N )of ur std CO11n.
    CO11N screen will appear, when u will save the variant, u will getgood movement tab , it will hide now.
    Activate the transaction variant.
    Regards,
    R.Brahmankar

  • Problems with image movement

    Hello everybody:
    First of all let me tell you that I am not a DVD wise person. I am starting to use iDVD and hope to soon be able to use DVD Studio Pro. The problem that I have is that I created a presentation in Motion using only photographies. The project was done using the Full HD(HDV1080p 30) format and saved as a quicktime file. When the file is played it looks great with smooth movements, but when transferred to iDVD the pictures still look good but the effects and movements are not smooth anymore, they stutter at times... This is the first time that I have this problem, maybe because I tried to do the project in full HD format? Or maybe is a problem of the speed of the data transfer? I know iDVD has a menu that allows to burn a DVD with Pro quality but I am still getting the same result.
    Also please...could someone recommend me some webpage o text regarding dvd recording for beginners?
    Thanks a lot for you help...

    Hi
    One thing
    iDVD - Can't do HD - not any version of it
    DVD Studio pro - most probably
    Roxio Toast™ - at least with Blue-Ray component to Blue-Ray burner/disks (DVD too but very short eg 20-30 minutes)
    Tutorials
    Some of them on internet
    iDVD 5
    www.kenstone.net/fcphomepage/idvd_5stone.html
    iLife6
    www.apple.com/ilife/tutorials/
    iMovie HD 6
    manuals.info.apple.com/en/iMovieHD_6_GettingStarted.pdf
    iLife08 and Mac OS X.5
    www.apple.com/ilife/tutorials
    iMovie08 and Mac OS X.5
    www.apple.com/ilife/tutorials/#imovie
    iDVD08 and Mac OS X.5
    www.apple.com/ilife/tutorials/#idvd
    Karsten Schluter
    karsten.schluter.googlepages.com/im08tricks
    Podcasts Apple
    - Find Out How - Document Apple
    - Find Out How - Mac OS X Apple
    - Find Out How - Movies Apple
    - Find Out How - Music Apple
    - Find Out How - Photos Apple
    - Find Out How - Web
    Books
    David Pogue's books
    • iMovie HD the Missing Manual
    • iMovie 6 & iDVD The Missing Manual
    • iMovie’08 & iDVD The Missing Manual
    • iMovie’09 & iDVD The Missing Manual
    Yours Bengt W

  • Segregate the scrap as an operation wise during operation confirmation

    Hello PP Gurus,
               One  FERT item's BOM contains 4 HALB items in which 3 are mentioned as an negative qty, ( it may be reusable scrap using in production again), and having 5 operation sequence. The problem is while confirming first operation itself the whole scarp value is generated for those 3 HALB items which are mentioned as an negative value. I want to segregate the scarp value for each and every operation or at least any of operation by qty wise or percentage wise. Is it possible to maintain it in system? and also is it possible to control by order type wise?
    Is there any setting to do meet this requirement?
    No manual material issue , during confirmation material are issued/generated by using back flush.
    Thanks

    Hello Mr.Devendra,
                Thanks for your reply. I want to do an settings for component allocation by operation wise while during the production operation confirmation. Is there any option or SAP User exit and enhancements?
    For example, a FERT 'A' having as an sub assembly 'B','C','D' and having 5 operations(10,20,30,40,50)in Routing. In these 'B' mentioned as an positive qty and the remaining 'C','D' are mentioned as an negative qty. while doing confirmation components are allocated for first operation(10) itself. i want to allocate the component for operation wise. In my case, while confirming operation 20 only part of 'B','C','D' will be allocated and the same for segregate to operation 30,40. How can we handle this situation is there any option?
    Thanks

  • Problem with P45 Platinum during POST

    Good day! 
    I have MSI P45 Platinum mainboard and from to time to time it freezes during POST with AMI bios POST code - 423C. This happens right after the message that "4096MB OK" and before the detection of SATA/IDE drives.  When this happens, the only way to make the system run is to turn off the power (pressing Ctrl-Alt-Del of Reset would result in the same error)  - after that the POST procedure finishes correctly and I don't experience any problems afterwards (system is rock-solid after POST completion).
    So my question is - can anyone explain me what does this post code mean (D-Leds are not much of a help)? Is this a mobo problem or may be there is some kind of incompatibility with my hardware. I should mention also that I've tried all versions of Bios both official and beta without any success.
    This problem does not trouble me that much (doesn't happen often), but still I would like to understand what may cause it.
    P.S. My system config - iC2D E8300/MSI P45 Platinum/4x1Gb DDR2-800 Geil Black Dragon (5-5-5-15)/MSI Radeon 4870 1Gb OC edition/HDD 250 Gb WD + 120Gb Seagate/SB Audigy 4/DVD-RW Asus 1814/PSU TT Toughpower 700w (w0105)
    Thanx in advance and please excuse my poor English   

    Thank you for the reply! 
    Quote from: Jack the Newbie on 16-December-08, 06:39:42
    What is your current BIOS Version?
    I've recently flashed the latest beta bios version - 1,5 beta 6... but it produces the same error as did the latest official bios v1.4 
    Quote from: Jack the Newbie
    Does the same problem occur with only one memory module installed?
    I don't know actually. But thanks for pointing this out  - I will test the system with one (and then with two) module(s). I've tested the modules with the memtest86+ software (the latest version, which supports P45 chipset) several times and it showed no errors. So the modules are OK and they worked without any problems with my previous mb (Gigabyte P35-DS3).
    Quote from: Jack the Newbie
    What do the POST-Status LEDs of the board tell you, when the system freezes at the described stage?
    Well, I guess I don't fully understand what does the combination of LEDs tell during the freeze. I'll try to describe the combination -
    LED12 - OFF           LED13 - GREEN
    LED8 - RED             LED7 - OFF
    LED14 - OFF           LED10 - GREEN
    LED15 - RED           LED11 - OFF
    In mobo's manual this diagnostic LEDs are grouped in 4 groups and the description of the group that most closely resembles my case is - "Testing base and Extended memory etc." But I'm not sure that I'm identifying the problem correctly, because of the LEDs that are OFF.
    Quote from: Jack the Newbie
    Are you experiencing any freeze and/or stability problems appart from the described problem?
    No, as I said in my initial post, once it get past this stage everything is running smoothly - OS boots and all software, including the most demanding games or tests, are running OK.

Maybe you are looking for

  • Error and Blue screen with pc suite

    Hello Recently I am having a problem wid nokia pc suites. After putting the notebook on sleep or hibernation, when i resume windows, i get an error message  saying rundll32 has stopped working. details of the error is as follow -  Problem signature:

  • How do I complete online .pdf form and then print?

    Sometimes, I can enter data on an online .pdf form and sometimes, I cannot.  I need to complete forms and then print them rather than print a blank form to complete by handwriting.  Window XP and Vista on my computers.  I have installed some Adobe an

  • Java.io.FilePermission + Flex :(

    Hi Guys, i have a very strange problem and hope that u can help me. J I am developing an Air-App using a Coldfusion (Hoster is hostek.com) Backend. The Application has a User-Login which works correctly. After the login the app calls the server to ge

  • Data Load Best Practice.

    Hi, I needed to know what is the best way to load the data from a source. Is the SQL load the best way or using data files better? What are the inherent advantages and disadvantages of the two processes? Thanks for any help.

  • How to disable iCloud on iPhone??

    How do I disable iCloud on my iPhone? Mindlessly clicked through the iOS5 setup. Deleted my account already. Should that be enough? Really don't wanna use this feature. Help please. Thanks!