Procedure to carry forward Un-utilized commitment budget

Hi all,
what is the T.code & process to carry forward the "Un-utilized commitment budget" from one fiscal year to other fiscal year. ( since FR34 is in 4.6) please let me know new T.code & process in ECC6.0
Rgds,
Swathi.
Edited by: swathi fico on Dec 15, 2008 7:59 AM
Edited by: swathi fico on Dec 15, 2008 9:08 AM
Edited by: swathi fico on Dec 15, 2008 2:40 PM
Edited by: swathi fico on Dec 15, 2008 4:54 PM

Hi,
As per your request you want to know the transaction to carryforward COMMITMENT BUDGET.
Carryforward process with Former Budget
================================
If you are using Former Budget and you want to carryforward commitment budget, you should ONLY run the following steps:
Prepare Budget Carryforward (BPINDX05)
Carrying Forward Budget to the New Year (RFFMCF30).
Note that you can only carry forward commitment if the definitions made in the default settings for the year-end operations of Customizing for Funds Management Government allow this. For more information, see the IMG of Funds Management Government, section Enter Default Settings. Using program RFFMCFM1 Monitor Closing Operations, you can get an overview of the current Customizing settings.
The Commitment Carryforward must be executed before the budget carryover because the budget tied to the commitment is included in the calculation of the residual budget.
If you are using the function Revenues Increasing the Budget (distribution procedure), you must use the corresponding program to execute the budget increase. For more information, see Increasing the Budget in help.com.
Carryforward process with BCS
================================
You must define the parameters used for the commitment carryforward. Budget changes in the previous year and/or the following year depend on whether you use the statistics indicator for the commitment carryforward.
You should use transaction FMMPCOVR to run the carryforward process. Please check the documentation of this program (RFFMMP_COVR) via SE38. You will find not only information text but links in order to check all the needed customizing settings in order to run the carryforward process.
=================
You can find more information in help.sap.com in the menu:
Public Sector Management -> Funds Management -> Closing Operations -> Budget. There you have
2 submenus:
Budget Control System (BCS) and
Former Budgeting
I hope it helps you
Best Regards,
Vanessa.

Similar Messages

  • KOCO -( Budget Carryforward)  & KOCF ( commitment carry forward ) report

    Hi
    Can some one explain me how to be sure that some one has  successfully run two t-codes KOCO -( Budget Carryforward)  & KOCF ( commitment carry forward ). I want to make sure that Budget and Commitment carry forward has taken place.Is there any report which I can run.This situation is due to a  person left the organization suddenly and I am not sure he has run it.In any case if I run it again what will  happen ?
    Thanks in advance
    Satya

    Hi Abhinay,
    Thanks for the answer.
    When you say they have to perform year end activities like checking PO and PR, what actually they are doing? Do they just need to check whether those PO or PR are required (if not, close them) or they need to do something more? . As far as I know, no steps like checking PO and PR are required here. So I am wondering whether we have missed anything or not. Can you give me some details about that step?
    Also, if we are using only Total value for the budget, not annual value, I don't need to do the budget carry forward closing step. In this case, do I need to do the commitment carryforward step?
    Thanks,
    Ting

  • Actuals after Commitment and Budget Carry forwards

    We recently did a Commitment Carry Forward using CJCF from year 2009 to 2010 (but did not do budget  carry forward) and this added the Assigned amount by USD 100 in 2010 for the WBS Element.
    I have some doubts and my questions are :
    1) when I do the Goods Receipt in 2010 for the commitments carried forward, will the system check for 2009 budget or 2010 budget ?
    2) if it checks for 2009 budget and adds to the actuals in 2010, will it not be an incorrect business process ?
    3) what would have happened if the budget had also been carried forward from 2009 to 2010.
    Thanks for any response.

    In budget tolerence limit setting if you have maintained budget check ++ means for all trancastion the system will check for budget against posting values whenever you execute any transaction system will compare the values against available budget of posting year.
    in you case at the time po coiitments are created in 2009 and checked for available budget for 2009 now you are posting GR / service entry in year 2010 at this time your PO commitments are going to transfer to actuals but as posting is happening in 2010 system will check for the budget availability for year 2010.
    so for any annual budget project at the end of year you have to carryforward commitments and buget to next year.
    regards,

  • Using Schedule Manager (FMDM) to manage budget carry forward for commitment

    Greetings,
    Using ECC 5.0,  we have a business requirement to carry forward (FMJ2) some open commitments with budget and some open commitments without budget to the new fiscal year. We have attempted to use Schedule Manager (FMDM)  to change the settings on open commitments (purchase requisitions and purchase orders). While the Schedule Manager reflects the change in the budget carry forward status, the application of the FMJ2 does not work as expected.  Alternatively, we have changed the configuration settings and then transported changes to production environment. 
    I would appreciate guidance on how to troubleshoot operation of Schedule Manager so budget carrry forward status can be managed with this tool.
    Regards,
    Rod Anderson

    Thanks, Ming.
    My security team has confirmed that the FMDM is currently set up as a display only transaction.  I now know where to take the issue from here.
    Regards
    Rod Anderson

  • Commitment Carry Forward in the year end closing!

    Hi All,
    We have a lot of open PRs and POs against Internal orders and WBS at the year end and we also have the budget control activated. Now we are going to do the year end closing. My question is:
    1. Who should do the commitment carry forward, supply chain or FI team?
    2. If supply chain will do the PR or PO carry forward, will FI team also need to run the commitment carry forward (KOCF or CJCF) from FI side at the same time or not necessary?
    Thanks,
    Ting

    Hi Abhinay,
    Thanks for the answer.
    When you say they have to perform year end activities like checking PO and PR, what actually they are doing? Do they just need to check whether those PO or PR are required (if not, close them) or they need to do something more? . As far as I know, no steps like checking PO and PR are required here. So I am wondering whether we have missed anything or not. Can you give me some details about that step?
    Also, if we are using only Total value for the budget, not annual value, I don't need to do the budget carry forward closing step. In this case, do I need to do the commitment carryforward step?
    Thanks,
    Ting

  • FMJ2 - Carry forward with budget Line

    Hello,
    I have done a carry forward FMJ2 and everything works perfectly. However the client let me know that they also want the budget line associated to the commitments to be carry forwarded.
    When I try that, the system gives me error FMAVC005.
    In "Define basic stting for carry forward" I have "Carry forward with document chain".
    In "Enter default settings" I have flaged "Carry forward budget for commitement allowed" and also the other 2 (Commitemnt and residual).
    Any idea about this topic.
    Please let me know.
    Regards,

    Hello,
    Avalability control is activated and I ma working with BCS Budget.
    In 2013 I have introduce my budget FMBB (Budget line). Then I have created a reserve agaisnt this budget line.
    When I try to do the carry forward the budget line is not carry forward and so the reserve in 2014 is trying to consume a budget line that do not exist.
    Please find a document with the images of the customizng and the 4th one with the result of the budget in 2014 but without the availability control (I get a negative ammount).
    Regards,
    Daniel

  • Budget carry forward problem

    Guys,
    When i try to carry forward my budget for internal orders in KOCO i am getting this error. I am trying to carry forward budget of 2008. We are testing are year end steps. How does the system determine which fiscal year is closed? i have closed the fiscal year in asset accounting and was able to open year 2009.
    Why can i not carry forward budget to 2009.
    Update run only possible for closed financial years
    Message no. BP595
    Diagnosis
    You have tried to close the current fiscal year or a future fiscal year in a production run.
    Since the process cannot be reversed, you may only close a fiscal year which has elapsed.
    System Response
    Processing automatically takes place in test mode.
    Procedure
    Start the transaction again for a fiscal year which has elapsed.

    Some closing steps you can not do in the Future.
    In some case to test the fical year closing you have to change the CPU date from the server.
    An other option is to test it from 2007 to 2008
    There are some work arrouds you can found then on SAP notes, I think you can't to close the fiscal year for asset accounting to in the future
    Paul

  • Budget carry forward- giong up in the fund center hierarchy

    Hi,
    We are about to close year 2008 in the FM. We work with the former budget, and we don't have budget structure.
    When carry forward the commitment u2013 the receiver is the same as the sender.
    But, when I carry forward budget for commitment, the receiver is the upper fund center in the hierarchy.
    The budget is not where the commitments are.
    What can I do?
    best regards,
    Edit.

    Hi,
    The budget of year 2008 was entered at the subordinate FC.
    If there is budget in year 2009 at the subordinate FC, the budget carry forward is right (the sender and the receiver are the same).
    Only if there is no budget on the subordinate FC, the budget runs upwards the hierarchy.
    Thanks,
    Edit.

  • Budget carry forward

    Dear Experts,
    I have doubt regarding the budget carry forward.
    I'm using PS with Investment Management.
    Now I need to carry forward the budget from 2008-09 to 2009-10 fiscal year.
    I have the following transactions:
    IM:
    IM27 - Open New Approval Year
    IM27_CLOSE - Closing Old Approval Year
    IMCAOV - Budget Carry forward
    PS:
    CJCO - Budget Carry forward
    CJCF - Commitment Carry forward
    Can any one please tell me what is the hierarchy for the above transactions?
    Do I need to carry CJCO, CJCF and then IM27, IM_CLOSE & IMCAOV? or first I need to carry out for IM and then do for PS?
    What is the flow? Please advise me on the above.
    Thanks in Advice,
    Regards,
    Praveen.

    hi
    Do the following steps:
    PS:
    CJCO - Budget Carry forward
    CJCF - Commitment Carry forward
    IM:
    IM27 - Open New Approval Year
    IM27_CLOSE - Closing Old Approval Year
    IMCAOV - Budget Carry forward

  • Order or WBS budget carry forward!

    Hi all,
    Normally if we budget the order or WBS by year, we will need to run budget carry forward at the year end closing. But if we just use the overall budget and not use the budget by year at all, do we still need to run the budget carry forward at the year end closing?
    And also will there be any problem if we budget the order or WBS only by overall and we use the IM to allocate the budget later?
    Thanks,
    Ting

    Hi,
    If you use overall budget, no carry-over procedure is required.
    Regards,
    Eli

  • Funds Management-Budget Carry Forward

    Hi,
    I was doing testing for open item commitment carry forward along with Budget (FMJ2). In the selection screen, there is a drop down for Availability Control,  When I  Select Check and execute..
    1) I get errror message.. Budget "Annual Budget Exceeded by ......" . This message shld not appear as budget from CY is to be transffered to New Year.
    2) Then I executed FMJ2 again but this time I in Availability Control.. I selected Update without check.. this time there was no error and I could post it. But here the problem is when i see the report for Year 2009 (new year)FMRP_RW_BUDCON - Budget Control System (BCS) -> Budget -> Overview of Budget Consumption , Consumable bugdet  is 0, Current bugdet has value carried forward, available budget is in negative.
    I have release strategy for budget, but not for budget type carried forward.
    What could be the problem...How shld I solve this???
    Thanks & Regards,
    Jyoti

    Hi ELi,
    I have checked the table BUVALTPRO, automatic release is checked for carry forward process.
    Why I m not using release for this:
    1) IN FMJ2, I would like to choose Availaibility control as check, if I do this i'll get error message as release is done after I do carry forward.
    2) Budget is already released for open items in old year, so it would not make sense to release it again.
    3) Now, I have activated consistency check for Negative budget, so when I execute FMJ2, it does not allow me post even if I choose update wihout check and I get the message : "The current budget for budget type CFWD is negative"
    Does it has anything to do with
    IMG/PSM/FM Govt/Closing Operations/Closing operation for BCS/Set Up Automatic Budget Postings After Fiscal Year Change -
    what's d use of this?
    Thanks & Regards,
    Jyoti

  • Budget balance carry forward to new year fiscal year

    Hi,
    Currently, our setting for Funds Management Master
    Data is year-dependant. Now, our user request for a budget carry
    forward from one year to another year. So, we are trying to the fix the
    configuration.
    My question is, can we do the budget balance carry forward if the master data is year-dependant. If can, how to do that?
    For your information, our system is SAP R3 version 4.7C and using the BCS.
    Appreciate your advise on this matter.
    Thanks and regards

    Hi,
    copy cost center planning:
    kp97  - copy plan to plan
    kp98  - copy  actual to plan
    Internal order copying
    ko14 - copy plan to plan
    ko15- copy actual to plan
    all the best
    prasad

  • Down payment Carried Forward: Negative budget

    Hello,
    I have a downpayment of 8 euros in year X related to a PO. I carry forwarded the PO to year X+1.
    In year X+1 I have received an invoice of 7 and so the system automatically:
    Invoice 7
    Invoice -8
    Downpayment -8
    Payment 8
    That means that the budget is negative in year X+1. Any solution for that? If I check "Activate the conversion of bank clearing" in the settings of the Payment Transfer it would be the same?
    Please let us know.
    Regards

    Hi Mar,
    I had seen this SAP note before posting thread.
    I have some doubts in regard to implementing above note which are as follows:
    1. In update profile Down payment request & Down payment is marked for statistical update then why it is impacting funds
    2. SAP Note says that it is a modification & SAP will withdraw support after implementation of note. What are the changes take place once note is implemented:
          a. Whether I would not be able to make down payment against purchase order line item?
          b. If i can not make payment then this note is of no use as i want to track down payment against purchase order.
          c. If i can make the down payment against purchase order, will it not impact purchase order history?
                                                                                    OR
          d. this change will only impact fund management & down payment document will not impact fund management
    Thanks

  • Wrongly carried forward budget (KOCO) want to return.

    Hi,
    I have by mistake carry forward the budget for a internal order to wrong year, like; a order created in 2008 and i wanted to carry forward the budget to 2009 but done to 2010.
    We need to have the budget corrected to the value. I have tried with entering several transactions like budget adjustment KO22, KO24 and KO26, but the budget is still not correct. Currently the internal order is closed, but the budget needs to be corrected for it to be able to get used in the future properly.
    Please suggest if I can correct the budget which is wrongly carried forward to wrong year?
    Regards,

    Any Input?

  • Budget Carry forward report

    Hi,
    i am working for one of the client where they have carried forward the budget for some of the internal orders and for the rest of the internal orders budget is yet to be carried forward.
    is there any report whereby i can find out for which internal orders budget has been carried forward to the next year & for which internal order budget carry forward is still pending
    Regards
    Jyotsna

    Hi Jyotsna
    I dont there is any such report... Ideal way would be to run KOCO... Create a Variant and execute for all the Orders(A to ZZZZZ or 1 to 99999999)... Those orders where Budget is already carried forward, will automatically get exlcluded
    br, Ajay M

Maybe you are looking for

  • Is it possible to send group emails without having to select each email address individually?

    Does anyone know how to set up a group so that you can send an email to multiple emails addresses with one click? I often send to the same 5 people and feel there's got to be a way to avoid typing in all of their names/email addresses each time. I ca

  • Dynamic excel filename Receiver Mail adapter

    Hi all, May i know what is the way to dynamically set the file name of attachment in receiver mail adapter. Can we do using DynamicConfiguraion??? If yes how? Thanks In Advance, H.L.Babu

  • Array of JPanel and Array of JTextField?

    Hi, I try to create array of jpanel and inizialize it in "for" , but when run it give me this error message: "Exception in thread "main" java.lang.NullPointerException" at the row: "panInsCantante.add(panInsNCC);" why? (ps. i tried in another code to

  • JPA and table names

    Hello, are there any possibilities to use the same table names in different SAP JPA EJB? For example, the first project has entity with a name History and the table name is TMP_HISTORY. The second one has also the entity History with a table name TMP

  • TABLES USED IN PURCHASE ORDER CREATION

    Hi all, I want to know the tables used in purchase order creation header line. Those which are refereed by structure mepo_topline especially... mepo_topline-superfield MEPO_TOPLINE-ebeln etc..... Looking forward to hear from you all. regards, VKC