Process Chain and Info Package Transportation?
Hello All
Case 1
How to transport a Process chain and a Info Package Individually?(<b>first time from DEV to QA</b>)
Case 2
I have 9(<b>IP1 to IP9</b>)infopackages and 3(<b>P1 to P3</b>) Process chains and in each Process chain I have 3 Info packages like IP1,IP2,IP3 in P1 and so on.,
Now is it necessary to transport Infopackages and Process chains individually or is it enough to transport Process chains only(If v transport Process chains will the Infopackages will also transport)then how to assign a request to each one?
What I mean is,all <b>Infopackages are in $TMP(Package</b>),and Process chain is also <b>$TMP</b>,Now is it necessary to change the package for Infopackages as well as Process chain and Tranport only PC,Iam confused here,can anyone help me out?
Many thanks
balaji
Hi Balaji,
If you have created new infopackages then you have to transport them. It is not necssary to transport the info-packages if you have them in the process chain but have not changed them.
Also you cannot transport any BW object with $ tmp package. Assign a package and then transport the objects.
The best way to transport the process chain is from the RSPC screen. Click the transport button there and collect all the objects and transport them.
Bye
Dinesh
Similar Messages
-
Error while transporting PCs and Info packages frm dev to qa
Hello Guyz
First of all, I am new to this forum. Heard a lot about it, and I hope I can learn a lot by the exchange of information in this forum. I ve already gone through so many threads, and have gained a lot of insight in BW.
I have an issue, where I am transporting process chains and info packages from dev to qa. But the transports have thrown errors, saying that the 'Source System XXXCLNTXXX does not exist and info package has been deleted'.
My question: How can I transport these objects in such a way that the loads which were going from ECCDEV to BWDEV, now go from ECCQA to BWQA? Are there any settings in SE09 or SE10 or somewhere in BW where I can do this?
Thanks in advance.
Atul.Hi Atul........
There is no such settings........check this.......
How to transport BW object
Anyways.....I think there is some problem in the Client name.......Just check the Source system name in RSA1...........if it has been changed somehow........then run transaction BDLS and change the source system assignment........
Regards,
Debjani...... -
Data transfer processes and info packages in new client
Hi,
We have created new client from the development client.
The Info cubes and update rules are available in new client, bu the data transfer processes and info packages are not moved to the new client.
What is the actual sequence of steps to be followed when new client created from development client. Have I missed some sequence or steps. What are the sequence of steps to be followed when created a new client.
Kindly suggest to resolve this issue.
thanks and regards
MurugesanHi,
I have never seen clients created on the BI system. As such all the objects in the BI system are client independent as well as the data stored in the tables does not have the mandt field. Hence you cannot distinguish different clients in the BI system. Also if you notice all the request in BI are workbench request and not customizing requests.
I do not think this is a viable solution. Maybe you can contact SAP.
http://help.sap.com/saphelp_nw70/helpdata/en/b7/8a9a3aaf894871e10000000a114084/frameset.htm
http://help.sap.com/saphelp_nw70/helpdata/en/a9/bb963a570b4b5de10000000a114084/frameset.htm
Regards,
Vikram -
Process Chain Triggered automatically when transported to test system
Hi All,
We modified several process chain and transported the process chain to Test system.
Few Process chain triggered automatically as the varient was set to immediate in development system.
Now we want to move the process chain to production. Do we need
1. new transport request with the variant to future date and discard the transport request which created issues
2. New transport request with the variant to future date and transport the new along with the old transport to production system
3. Change the start date in Test system and transport the same request to production
Kindly advice me on the action to be taken.>
> Hi All,
>
> We modified several process chain and transported the process chain to Test system.
> Few Process chain triggered automatically as the varient was set to immediate in development system.
> Now we want to move the process chain to production. Do we need
>
> 1. new transport request with the variant to future date and discard the transport request which created issues
> 2. New transport request with the variant to future date and transport the new along with the old transport to production system
> 3. Change the start date in Test system and transport the same request to production
>
> Kindly advice me on the action to be taken.
Regarding 2: When the old transport is imported into production the start will be set to immediately and the process chain will execute. You should not use this option.
Regarding 3: Changing in Test system will not affect the content of the transport, it will still be the same as released from Dev.
We have avoided this annoying problem with process chains being executed when transports are imported by creating a "parent" process chain that simply triggers the process chain in question. This "parent" chain should not be transported. You then set the start option for the original process chain to "start by API/Event" then you can transport the original process chain whenever you want without any risk of the process chain being executed.
Regards,
Lars -
Process chains and event collectors
Hi All,
I need help in Process chains and event collectors.I joined in new project and this client using process chains and event collectors and they ask me to work on these areas.I didnt work on this as of now So please send any docs on this area and explain the procedure and technology methods behind this concept.I would really appreciate If someone can send me the full documentation on this concept as I couldnt find any any docs on this.
Thanks,
RasHi Ras,
Process chains are a sequence of processes to be performed. The are put together in a chain with the necessary dependancies (process A needs to finish before B can start) and conditions (if A and B are successful then C else send an email), and then scheduled. They usually revolve around processes related to data loading: Load, activate, roll up, compress etc.
Please take a look at this links/threads for more info:
http://help.sap.com/saphelp_nw04/helpdata/en/8f/c08b3baaa59649e10000000a11402f/content.htm
process chains
process chains
Process chains
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
Process Chains
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
Re: Ho to make a variable mandatory or optional?
There are lot of threads available in the SDN....go through them.....hope it really helps you in getting understand what are process chains and Events included in that.
Assign points if it helps you.
Regards,
Sreedhar -
Hello all,
We are currently having a problem with submitting process chains. When the chain runs it does not display any of steps in the process chain and where they are running from the job we submit (RSI_START_BW_CHAIN) So what we see is that the PC has been submited and completes in say 17seconds...however everything is still running on the system...for example our CIF PC runs for 3hrs but alls we are able to see is that the job executed from CPS with no problem. I've been digging around trying to find clear documenation about PC and CPS with little luck. Am I approaching the job submission incorrectly? We are on 7.0.3.Hello,
You should be using the RSI_RUN_BW_CHAIN job to start process chains. Maybe you can try that first. For the rest things should be straight forward. Depending on the BW backend systems you might encounter some issues, with BW 7 the synchronization has changed and you would be better of using one of the latest 7.0.4 versions (SP6 has just been released).
Regards Gerben -
Hi SAP Gurus,
I have installed an SAP PO system and am running the Config Wizard from NWA. The functional unit I have selected from NWA is - "Process Integration and Orchestration Package". This functional unit has in turn selected few more functional units like AEX, SLD. The issue that I am facing is that the wizard does not appear for my inputs and it shows that the selected wizards are running. Please see attachment "config_wizard_running.jpeg"
I read some forums and found a thread where in it was mentioned how to stop the config wizard and restart it. http://scn.sap.com/thread/1422958
Even after restarting my server, the functional units are still showing as running in NWA --> Configuration --> Scenarios --> Configuration Wizard --> Functional Unit Configuration UI. Please see attachment "Config_wizard_stuck.jpeg"
I restarted the application as suggested in the post so that I could run Config Wizard again. But its now allowing me to start it as the status is Running.
Please suggest.
Regards,
AmitHi Dimitri,
Thanks a lot. I have resetted the functional units. This time the wizard comes up ok.
Regards,
Amit -
Hi Experts,
I am facing problem in process chain execution in the AND node. The error is
This AND process is not waiting for event RSPROCESS, parameter 4941U4Q6QKIR8RFKMAZWYP5JB
I checked the log in ST22 but there is nothing , also no error msg in display msg or maintain variant.
is there any solution?Hi Soniya.....
The problem is due to the successor process is not activated, again try to
activate the process chain and schedule it.........
As a work around.........if instance and variant is already generated........then continue the process chain using the program : RSPC_PROCESS_FINISH.......
otherwise copy the rest of the chain and execute............To do this open the chain using RSPC1>> in the top where we write tcode.........there write COPY.........Give a name to the new chain.....remove all the processes till AND process...........then create a new Start process..........make the start condition as immediate..........and schedule the chain...
Hope this helps......
Regards,
Debjani....... -
How to create process chains,and how to use process like and or xor
Hi,
How to create process chains,and how to use process like and or xor.
can any one please give me a example in each.
Thanks,
cheta.Hi Cheta,
Here is step by step procedure to create process chains
Process chain is nothing but executing a process ..(or) loading the data any process we can do in background.. that means.. automatically we can execute our process based on Time or any event..
Creating Process Chains
Prerequisites
If you want to include a load process in the process chain, you need to have already created an InfoPackage.
You cannot load flat file data from a client workstation in the background. For this reason, you have stored your data on an application server.
Creating Process Chains
You have the option of creating a process chain in the process chain maintenance screen directly or by using a maintenance dialog for a process:
Creating a Process Chain Directly in the Process Chain Maintenance Screen
You are in the BW Administrator Workbench.
1. Click on the Process Chain Maintenance icon in the AWB toolbar.
The Process Chain Selection dialog window appears.
2. Choose Create.
3. Enter the technical name and a description of the chain, and confirm your entry.
The Add Start Process dialog window appears.
4. Create a variant for a start process.
1. a. On the Maintain Start Process screen, choose whether you want to schedule the chain directly or whether you want to start it using a metachain.
2. b. If you choose to schedule the chain directly, enter the start date value for the chain under Change Selections and save your entries.
The Maintain Start Process screen appears again.
3. c. Save your entries, return to the previous screen and confirm your entries in the Add Start Process dialog window.
You are taken to the Plan View of the process chain maintenance screen.
In the left-hand area of the screen, a navigation area is displayed. In the right-hand area of the screen, the process chain is displayed.
5. Use the drag-and-drop function to add the relevant processes into your process chain.
You use the Process Types function to select the processes. This sorts the process types according to different categories. You can also call up InfoPackages and processes for the data target from the separate InfoSources and Data Targets navigation trees.
Hope this helps
Regards
Karthik -
URGENT:Process Chains And events Related
Hi All,
I have created a new process chain which is a normal ODS Process Chain.For that I started with the start Process and then created event in sm62 to trigger the start of process chain.Similarly,I have at the end of the process chain ,I have added 2 ABAP Programs ,one to mark the successful completion of process chain and another to mark the Error or Unsuccessful completion.For these programs,I maintaines Processvariants and here, we have utility Programs.So used the relevant utility program and created a program variant and Events ,One for successful completion of process chain and another to mark the Error or Unsuccessful completion.
But ,Now ,I find that when I trigger the eventin sm64,I find that the process chain is not being run.Is that any problem with the events I created.This is the first i am involved with creation of events in SM62.Can anyone help me in this regard.
Can anyone,tell me thatdo we need to do anything else apart from Creating events .Imean like assigning jobs and then Programs in the Step of that Job.
Please Kindly help me in this regard.It is very very urgent for me.Thank you.Points will be assigned.
Regards,
SamirHi,
I have tried in the same way you have said .I have maintained as after event and activated and scheduled.after that i triggered the event insm64.But still,I am not able to see the Load in RSMO.
I have just checked out in sm37.And found that some jobs have failed.I think this might be the reason for the Process chain to not run.
I am just pasting the error msg and solution.
Job BI_PROCESS_ABAP, waiting for event RSPROCESS 489W6WH6I7OHV7BL3N9909F7F, has no predecessor
Message no. RSPC003
Diagnosis
Although job BI_PROCESS_ABAP has been started by event RSPROCESS 489W6WH6I7OHV7BL3N9909F7F and is recognized in the process chain, the current run for this process has no job preceding it.
This is why the system was unable to determine a log ID, and the chain is broken.
System response
The job has been terminated.
Procedure
With the exception of the start process, each process must have a process that precedes it.
Then Another error for the another cancelled job is
Job BI_PROCESS_OR, waiting for event RSPROCESS 489WC2QYBC4AJSYILQ10TWABF, has no predecessor
Message no. RSPC003
Diagnosis
Although job BI_PROCESS_OR has been started by event RSPROCESS 489WC2QYBC4AJSYILQ10TWABF and is recognized in the process chain, the current run for this process has no job preceding it.
This is why the system was unable to determine a log ID, and the chain is broken.
System response
The job has been terminated.
Procedure
With the exception of the start process, each process must have a process that precedes it.
Please kindly help me if you understand the problem.
Thanks,
Samir -
What are Info objects and Info package
Hey guys
can anybody tell me What are Info objects and Info package
thanx
saifhi Saif,
or you can directly using RSD1 to create infoobject characteristic.
help.sap.com may help you
http://help.sap.com/saphelp_nw04s/helpdata/en/fc/1251421705be30e10000000a155106/frameset.htm
http://help.sap.com/saphelp_nw04s/helpdata/en/23/054e3ce0f9fe3fe10000000a114084/frameset.htm
http://help.sap.com/saphelp_nw04s/helpdata/en/80/1a637fe07211d2acb80000e829fbfe/frameset.htm
http://help.sap.com/saphelp_nw04s/helpdata/en/80/1a63b3e07211d2acb80000e829fbfe/frameset.htm
also
sap bw cookbook by Jude Lobo
http://www.sapgenie.com/sapgenie/docs/MySAP%20BW%20Cookbook%20Vol%201.pdf
http://www.sapgenie.com/sapgenie/docs/MySAP%20BW%20Cookbook%20Vol%202.pdf
hope this helps. -
How to find deleted process chain and query
Hi All
Some body has deleted one process chain and one query from development system
how can i know who has deleted these?
is there any table where deleted process chain and queries will maintain????
Thanks & Regards,
Krishna
Edited by: krishnamurthy g on Sep 1, 2008 5:33 PMHi,
Usually its totally in tractable to find a deleted chain :
But you can try out with the following options:
1> T-code SLG2 .
2> T-code SLG1 - find out who was logged on to the system on that particular client at that time.
3> Try out the following tables in se16 :
RSPCLOGS --- Application Logs for the Process Chains
RSPCLOGCHAIN --- Cross-Table Log ID / Chain ID
RSPCCOMMANDLOG --- System Command Execution Logs (Process Chains) .
Hope it will be expedite.
Thax & Regards.
Vaibhave Sharma -
Authorization objects for Process chain and Data source in BW 3.x
Hi,
Can any one tell me the authorization objects regaring process chain and Data source in BW 3.x versions. I guess we have auth objects for both of them in BW 3.5 that is S_RS_PC AND S_RS_DS .
Can any one help me solving this issue
Thanks
BharatHi bharat
I dont thin these objects are part of 3.0
check from SU03 weather these objects are present in 3.o box
In 7.0 they exist:
http://help.sap.com/saphelp_bw33/helpdata/en/8b/134c3b5710486be10000000a11402f/frameset.htm
TO see weather these objects exist:
Go to Tools -> Administration ->User maintenance ->Information System -> Authorization objects -> Authorization objects by Complex Selection Criteria -> By Object Class. For the object class, enter either RS (for Business Information Warehouse objects)
OR
S_BCE_68001413 (Tcode for this rep)
Thanks,
Raj -
Authorization objects for Process chain and Data sources in BW 3.x version
Hi,
Can any one tell me the authorization objects regaring process chain and Data source in BW 3.x versions. I guess we have auth objects for both of them in BW 3.5 that is S_RS_PC AND S_RS_DS .
Can any one help me solving this issue
Thanks
Bharatits the same thread again
/community [original link is broken]
Thanks,
Raj -
Difference between process chain and event collector
what is the difference between process chain and event collector and also plz explain about metachain.In what scenarios they are used.
Many Thanks,hi,
have a look at these help docs
Process Chain:
http://help.sap.com/saphelp_nw04/helpdata/en/8f/c08b3baaa59649e10000000a11402f/content.htm
Event Collector:
http://help.sap.com/saphelp_bw30b/helpdata/en/c1/6c0538c7cb583ae10000009b38f8cf/content.htm
http://help.sap.com/saphelp_nw04/helpdata/en/6e/192756029db54192427cf6853c77a7/content.htm
Creating an event colector:
http://help.sap.com/saphelp_bw30b/helpdata/en/45/253d3873130057e10000009b38f842/content.htm
regards
sham'm
Maybe you are looking for
-
Slow performance in iPhoto - library is huge
Hello, I have a huge number of pix in iPhoto (approx 11k) that I have accumulated of my kids over the last three years. The library is about 9.4 GB. When I open iPhoto, it imports all the pictures every time. I really cannot have any other applicatio
-
User, Role, Profile Synchronization Job Fails
Hi Gurus, When I am scheduling a job the User, Role, and Profile Sync. job fails giving an error "Cannot assign a java.lang.String object of length 53 to host variable 5 which has JDBC type VARCHAR(40)." This happens when the synchronization happens
-
ME57 report modification.....
Below i clearly mentioned the detials pls anyone tell the solution asap... 1. Copy the existing program (ME57) RM06BZ00 in a new program ZRM06BZ00. 2. Create a Role table, this would essentially be to enable us to find the role of a buyer based on ei
-
Site Content Creation Problem in Web Page Composer
Hi, I am trying to create the Site Content / Cross Site Content based on the standard Web Forms and after saving the content, it is throwing the error and from then i am not able to access the Site Content of any web site or Cross Site Content Folder
-
Hi, one a new installed standalone cFolders 4.5 system I have added a new user (central user administration) on the ABAP AS (via SAP logon) with a initial password. I forced to enter a new password with the following parameters in RZ10: login/passwor