Hi,
I am developeing small process chain for loading master data(Delta).
I have already done innitial load of master data in infoobject, now i am developing a process chain to load delta master data. My question is shall i need to use different infopackages than used for initial load OR same infopackages used for initial load can be used for delta load process chain of master data.
please reply.

Hi,
Best practice is to use different infopackages.
But the same InfoPackages can also be uesd in the Process Chain. No harm.
Anup.
Edited by: Anup ShankarBS on May 5, 2008 10:50 AM

Similar Messages

  • Process Chain Flow doubt

    Hi,
    There is a process chain of flow start>Infopackage>DTP>ActivateDSO_->InfoPackage1>DTP1>ActivateDSO1_
    Only doubt starts where it is underlined. why the infopackage1 has been linked after the Activate DSO eventhough no dependency for DSO1?
    Instead the infopackage1 can be linked after start variant of the same process chain, right?
    regards,
    Draj S

    hi,
    please checkout the below link it may help you
    http://help.sap.com/saphelp_nw70/helpdata/en/67/13843b74f7be0fe10000000a114084/content.htm
    DataFlow of Process Chains in different SAP BW-BI
    Steps for Process Chains in BI 7.0 for a Cube.
    1. Start
    2. Execute Infopackage
    3. Delete Indexes for Cube
    4.Execute DTP
    5. Create Indexes for Cube
    For DSO
    1. Start
    2. Execute Infopackage
    3. Execute DTP
    5. Activate DSO
    For an IO
    1. Start
    2.Execute infopackage
    3.Execute DTP
    4.Attribute Change Run
    Data to Cube thru a DSO
    1. Start
    2. Execute Infopackage ( loads till psa )
    3.Execute DTP ( to load DSO from PSA )
    4.Activate DSO
    5.Further Processing
    6.Delete Indexes for Cube
    7.Execute DTP ( to load Cube from DSO )
    8.Create Indexes for Cube
    Thakns,
    Neelam

  • Process chain running :doubt

    Hi,
    I had scheduled one process chain which is running now---
    now its in last step that is
    "deleting overlapping request in infocube----"
    i had checked this job : it is running with out any hassles--
    now after this only AND process is there to finish the chain---
    Now i want to schedule the process chain again for weekend!
    can i change the start varinat though the chain is still running??
    Raj

    Hi Raj,
    Its not a good practive to reshedule the chains which is running now..
    when u attempt to reschedule then the process will gets terminated from the point where its running .... I mean the present running job will be in active mode and it will gets finished.. but the process after the active process will gets disconnected as soon as u reschedule the chain..
    So better to wait for ur chain to finish and then proceed with the reschedule...
    Also before rescheduling try to deschedule the chain...
    Thanks
    Assigning points is the way to say thanks..
    If this resolves ur issue then close this thread by assigning points..

  • Process Chain: what does the variant do with "Delelte changelog"

    We have a process chain developed by a consulting firm that inside the process chain, there is a variant with the description of "Delelte changelog older than 3 months".  Double click this variant to open this variant interface, 1st column titled "Object" shows all rows are ODS picture icons, 2nd column titled "Object Type" shows all rows are "Change Log Table", 3rd column titled "Object Name" shows all rows starting with "8ZXXXXXXXXXX".  What kind of this variant function in Process Chain as "Delete changelog"?
    Thanks and we are looking forward to seeing your answer soon!

    Hi
    DSO contains 3 tables. New data table, change log table and active data table.
    New data table: When the data was loaded, first the data goes to new data table.
    change log table: When you activate the data in DSO, it goes to change log table and active data table. Change log table contains the changes happened like before image,after image.
    Active data: Reporting is done out of this table.
    Over a period of time the change log table grows in size and it needs to be periodically cleaned to reduce the size of the table.
    The variant used to delete the change log entries if it is older than 3 months automatically using the process type "delete change log" in process chains.
    Hope it helps.
    Regards
    Sadeesh

  • Not able to open existing process chains in BW development

    Hello Experts,
      I am not able to open my existing process chains in development, actually I would like to schedule the process chain but I couldnt do that becoz of above reason. While opneing I am getting pop-up message as " Choose a change request with target system/CONSOL/". I reported this issue to Basis but they told it is not an issue at all
    I need to resolve this asap.
    Thanks in advance,
    Andy

    Roger,
    For the time being you can create a transport, but indicate that it shouldn't be transported.
    Then you will be able to work with the process chain.
    Just be sure to delete the transport so it doesn't get moved to production on accident.
    Nick

  • Error handling in process chain-doubts

    Hi ,
    I have some doubts in error handling of process chains.
    1) I have  aprocess load infopackeage and subsequent process is update fromPSA.
    process load infopackage got failed  , so i loaded  the IP manually and repeated the next i.e process update from PSA .
    How to correct the process chain from now?
    2) I have  aprocess load infopackeage and subsequent process is Delete request in infocube .process load infopackage got failed  , so i loaded  the IP manually and repeated the next process i.e Delete request in infocube. Chain continued by deleting the right request . How this is possible ?
    Plz  help me  as this is urgent and daily i have to deal with this  issues. If any documents on error handling is greatly appreciated.
    My mail id is [email protected]
    Regards,
    Pavan

    Hi Pavan,
    Hope the following links will give u a clear idea about process chains and clear ur doubts.
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Errors in monitoring of process chains can be categorized into 4 different sections...
    Master data - Full Update
    Master data - Delta Update
    Transaction data - Full Update
    Transaction data - Delta Update.. in terms of loading of data which can be due to server shut down or system maintenance... errors due to incorrect entries in the OLTP system in which case you'll have to fix the errors in the PSA and manually load the data...
    Otherwise it can have errors on Attribute change run being locked by some other job... Aggregate Roll up failing because of attribute change run being run at the same time... Problem with hierarchies and save hierarchies...
    There can be problems with the data store activation if the ODS object contains any incorrect request sitting inside it... then, you need to delete the incorrect request and reload the data again...
    In case of Transaction Delta failure, you'll have to request for a repeat either manually in the infopackage or using the repeat option if available on right clicking the load event...
    For Master Data Delta failures, you need to do an Re-init by deleteing the previous initalization condition in the "initalization option for source systems" in the menu scheduler or reschedule the enitre chain... because, master data generally do not support repeat of last delta ...
    U can even look into these links:
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    For common data load errors check this link:
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    ****Assign Points if Helpful****
    Regards,
    Ravikanth.

  • Needs to delete one Master Data from main process chain in development syst

    Hi All,
    Can any one pls suggest how we can delete the master data load from main process chain in development system.
    In the main process chain nearly i am having 52 master data loads in that i required to delete one master data.
    Thnanks in Advance.
    karuna.

    Hi...
    1) go to RSPC1
    2) Give the technical name of the process chain
    3) in the top where we write tcode....there write COPY..and press enter...
    4) then remove the start process and the desired master data loads..
    5) create a new start process with a new variant..if you want to put ant condition you can put it there...
    6) then link the start process with the first process..
    7) activate your process chain...and schedule it as per your require...you can make it immediate run or can scedule it for a particular time...
    Or if you don't want to create anew process chain...then go to the design view of the PC and remove the desired load and again activate it...
    Hope this helps you...
    Regards,
    Debjani...
    Edited by: Debjani  Mukherjee on Sep 4, 2008 4:35 PM

  • Process chain doubt

    Hi All,
    In process chain in one process step which is delta load
    for master data infoobject failed due to error as idocs not updated to business warehouse an d avlble in ale inbox,now below the step there are amny steps connected ,if we do no manuall update by going to the monitor screen ,status -process manually .then we have to do manually other steps ,so to avoid that i repeated the step,it fetched 0 records saying there are new deltas on r-3 side,so how can i know that the delta updated is with correct delta records compared to r-3 side records.
    Thanks
    venkat

    Hello Venkat
    You performed repeat step and it fetched 0 records saying that there are No new deltas on R/3 side and you want to check if you have missed delta records.
    Few tips - Find out from RSMON , Generally everyday how many delat records are updated for that Info object .
    If you know the tables for master data on this Info object on R/3 side then check what are new entries and changed entries (created on yesterday & changed on yesterday ) and validate it with BW Master data table .
    Hope this helps
    Regards
    Pradip

  • How to Develop Meta Chain (Process Chains)

    Hi Experts
      How can i create a META CHAIN (Meta Process Chain)
      How can i insert a different process chain to into meta chain.
    In the process types i can't find any type with process chain
    Thanks

    Hi
    Thanks for the update.
    I can't able to find Process Type Local Process Chain
    Please update me in detail
    Thanks

  • HI doubt on Process chain...

    Hi Sap folks...
           Could any one tell me about the different issues we get when running process chains, especially on data loads. i want to know issues which comes like Collar 70, 90 and so many.
    Points will be rewarded to all the active members.
    Regards
    Sujan

    nice interview question for BW Support role.
    Plese refer to http://help.sap.com/saphelp_nw04/helpdata/en/8f/c08b3baaa59649e10000000a11402f/content.htm
    It will answer all your questions.
    I seriously think that we should have seperate subforum dedicated to 'BW Interview questions'
    rgds
    Pradip

  • Doubt on Process Chain

    Hi BW Experts,
    Due to some problems , we have stopped all process chains on 20/09/2007.
    We have MM process chain.
    Just now i see the Delta Infopackage of MM. In PROCESSING TAB only PSA is checked. 
    Update Subsequently in Data Targets in not CHECKED.
    We have not changed anything in Processing Tab.
    But before 20/09/2007, we have the data in Infocube.
    How it is possible.
    This Process Chain looks:
    START--> DELETE INDEX>LOAD DATA (INFOPACKAGE)>CREATE INDEX>COLLAPSE-->DB STATISTICS.
    Please can anyone tell me the solution.
    Regards,
    Anjali

    Hi Anjali,
    First of all, what exactly you wanted to ask? Whether how the setting changed? or How to correct the setting?
    Regards,
    Habeeb

  • RE: Process chain doubt

    Hi Guru's
    I am loading 4 flatfile data loads(4 info packages) to the same ODS. my question is while creating, a single process chain with the 4 infopackages should i create 4 ODS0 DATA ACTIVATION or a single ODSO DATA ACTIVATION is ok?
    Can anyone help me?
    Thanks In Advance
    Regards
    VS Rao

    Rao -
    if we have indexes in infocube they improves the performance (execution time) of  report on that infocube,but it take much time to load data into infocube when infocube have indexes.to avoid this we always delete the indexes before loading data into infocube after the data load is done then we create those indexes again (deleting indexes improves data load perofmance in infocube). we can do whole cycle in process chain.
    Edited by: anesh babu boddapati on Jan 11, 2008 7:08 PM

  • Process chains doubt

    Hi all,
    How can we schedule and monitor the process chains.How can we know that the process chains are executed correctly and where can we get the error messages for the failed processes?
    Also when i drag the attribute change run process after an execute infopackage process,inside the change run process there are different object types namely for infoobject,hierarchy and again execute inforpackage.some of the system suggested attribute change run process has the object type as execute infopackage.when should I use infoobject and when should i use execute infopackage for attribute change run process.Also when save hierarchy process is used,execute infopackage comes as default object type.should i have to change that to hierarchy object type.
    Any suggestions is appreciated.
    thanks.

    Hi,
    As mentioned by Jkyle you can easily Schedule and Monitor the Process Chain.
    Also, for the failed process or for the successful process, you can define Messages. This Messages will automatically come in your Inbox with the Status.
    Most of the people use this method for monitoring the Process Chain. You can do this by using the Context Menu of Process Type and say Create Message.
    You can remove the InfoPackage by saying Remove Process.
    Alternative is use Program RSDDS_AGGREGATES_MAINTAIN for Attibute Change Run define Variant for your InfoObject and Include the Process ABAP Process in your Process Chain.
    Hope this helps.Please reward the points if the solution helps you and also let us know if you have any further clarifications.
    Regards,
    -Ashish

  • Report on process chains using SEM-BPS

    We are looking to develop a tool to:
    1. Monitor data loads at the process chain level
    2. Within in the same tool, enter error resolution /
       action steps for all failed loads
    3. Report out % of successful or failed loads, using the data captured by the tool.
    We have studied the BW Tables rspcchain, rspcchainattr, rspclogchain, rspcprocesslog, rspclogs, rseventchain and
    rspcchaint.
    We are considering the following options:
    1. Develop an ABAP report and allowing the process chain monitor to manually enter the error resolutions (Perhaps in a Z-Table)
    2. Create an InfoCube in BW using the above tables and then write a query, but we can not allow the user to enter error resolutions in the query.
    3. Create a transactional infocube in SEM-BPS using the above tables and use the input functionality of tansactional infocube to facilitate the error resolution report entry.
    Can anyone suggest any alternate solution, or has anyone encountered similar requirement on project?
    One more doubt to check: is there any way to create an infoobject with CHAR type to enter data with 1000 or more characters? Or is there any other alternative solution to it? The doubt is to take care of the text entry for the error resolution.
    Milind Vad

    Just some thoughts:
    Have you considered using document service in BW or even KM (Portal) technology rather than CHAR 1000+ fields? This would give you more flexibility also on the type of document.
    For loading there are monitors available (based on tables like RSMONMESS). If you are interested in loads only (and not other process types), maybe using information from the BW load monitor could be beneficial (like RSMONMESS) rather than the process chain stuff.
    Maybe it's even worth having an InfoObjekt with a resolution code that links to a document describing the resolution with a key and whenever there is a new solution available create a new key with a new document. That would be most beneficial for reporting (like how many times has this problem / resolution occurred and the like).
    Regards, Klaus

  • Transporting Process Chain

    Hi All,
    I have an existing process chain scheduled on daily basis in the prod environment. I want to change the process chain by adding some data load steps.
    My question is, if I move the modified PC from dev to production. will the process chain be removed from daily schedule? I mean do I need to reschedule the process chain? or this change will not affect the process chain schedule?
    Experts Pls advise.
    Note: Pls do not get confused with my other post regarding process chain, that is related to meta chain.
    Regards,
    Anand

    Hi Anand,
      I also had such scenario in my project where i had to add some more data loading and index creation & deletion steps in my process chain. I did created a copy chain in development system and made modifications to the old chain & saved a copy of that chain in devlopement. Performed testing of the chain in Accpetance & Quality & then moved to production. You can also follow the same path so as to make sure that in case if you face issues faced if any, with the newly developed chain, then your old one is inctact and bussiness is not affected due to the issues in the newly created chain.
    Once your new chain is succesfull you can move it to production and schedule the new chain and remove the old chain from schedule. This will ensure that the bussiness is not impcated due to this change.
    Also one more thing to be remembered is that before you transport a chain to production make sure that you Metachain chain and the other Local Chains in the Metachain should have their start variant set to a future date or select the variant to "Run using Metachain or API" else as soon as the chain is moved to production it starts running automatically.
    Hope this info clears you doubts.
    Thanks

Maybe you are looking for

  • Vendor Stock On A Particular Date

    Hi, How can we see the Vendor Stock on a Particular Date. For example, today is 04.08.2007, and actually we want to see the Stock of a Vendor as on 31.03.2007. Regards.

  • Match Code Objects and ID's

    Hi,     Can you explain what is Match code objects and ID Regards, Bharath Mohan B

  • How to use clockwordmode on st15i to install custom ROm like CM10 JB?

    I have rooted my phone alreasy and its on stock ROM & kernel. Now I want to use CM10 JB for ny device for that I should have to use clockword but it doesn't support my device. While the threadd for installing the JB is telling that I have to install

  • Zoom and pan a UITableView

    Consider my entire tableview the view I want to zoom and pan. I put an outer view around the table view but could not get both zoom and pan to work. I can get zoom to work but it always leaves me on the top left with no panning abilities. I can get z

  • How to set proxy to javamail?

    Hi friends: I want to receieve email using javamail. I use code: Properties prop=new Properties();        prop.put("mail.pop3.host",host);        prop.put("mail.smtp.auth","true");//        Session session=Session.getDefaultInstance(prop);        ses