Process Chain starter in Production

I transported a process chain in to Prod but when I click on the start process, it doesnt show me anything. Everything else looks perfect. What is the problem?

Hi Fran,
Some time variants are not collected automatically in a request you have to manually collect them .
Hope this will help you
Suneel

Similar Messages

  • Process chains start after transporting

    Hello friends,
    since we've upgraded to NW7 we encounter the problem that process chains start automatically after transporting them from test system to productive system. This ist very unpleasant!
    Does anybody encounter this problem too? Ist there a system settig, which disables the automatic start of process chains after transporting?
    thnx in advance!

    Hi,
    Process chains execute when transport request imported  :Note 1233327 - Correction: Scheduling of immediate start for transport
    In order to stop Process Chains from being scheduled immediately upon import, insert the following into the RSADMIN table with ABAP program
    SAP_RSADMIN_MAINTAIN:
    Object = NO_TP_SCHEDULE_IMMEDIATE
    Value = X
    After this change is made to the RSADMIN table, you can import Process Chain transports where the Start process variant has it set to be scheduled immediately.
    This entry can be modified in the future by the same ABAP program and just changing the value of Object to space.
    rgds,

  • How to know the process chain start time & end time?

    HI all .
    how to know the process chain start time & end time at the table level as well as in RSPC level .
    regards,
    Srinivas

    Hello,
    there is a program "/ssa/bwt" which will help you to know the exact time when the process was started and ended.
    but the thing is you have to provide name of the process chain with the date at which it was executed.
    another option is - you can double click on start process and on the last process of the chain.
    here, you will get both the timings... Start time of the start process will be the start time of your PC and end time of the last process in the chain will be end time of your PC.
    Hope this will help you.

  • How to know the process chain start time and end time

    Hi Experts,
                   How to know the process chain start time  and end time .
    Thanks in advance
    Regards
    Gutti
    Edited by: guttireddy on Feb 23, 2012 11:30 PM

    Hi Reddy,
    You may find the run time of a PC using below steps.
    1. Call SE38 > /SSA/BWT > Execute  > Enter your PC , choose the date and time > Execute. Here Run-time of a PC is displayed. (or)
    2. Call RSPC1 > Enter your PC > Execute > Goto Log view > Right click on the start Variant > Displaying Messages > Note down the start time in Chain Tab. Now Right click on the last Process type of the PC > Displaying Messages > Note down the End time in Chain Tab. The Difference b/w start time and end time gives the Run-time of your PC.
    Hope this helps.
    Regards
    Sai

  • If Process Chain Fail in Production?

    Hi to all,
    Please can anyone tell me, if there is process chain running in production and any process type fail or process chain fail ?.
    Does we need to repair it, or repeat it or, restart it.
    How to identify what should be done and how to do it.
    I shall be thankful to you for this.
    Regards
    Pavneet Rana

    Hi
      Based on the error occur in process chain step, we have to monitor the error.
    If the error or red color occur when you schdule and check the log view,  then right click the error process step and select display messages, check the error clearly by using process monitor.
      based on the error you have to react.
    this links will helpful to you.
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/502b2998-1017-2d10-1c8a-a57a35d52bc8?QuickLink=index&overridelayout=true
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/00a1f389-ec7c-2c10-04bc-9d81b3084171?QuickLink=index&overridelayout=true
    Edited by: Srikanth.T on Jan 23, 2012 11:29 AM

  • Trigger Tcode in ECC as soon as process chain starts in BW

    Hi Experts,
    I need some help on how to trigger a transaction code in ECC as soon as the process chain starts in BW.
    I need to give some selections in the ECC like company code, period and year to fetch the report in ECC . I use it for reconciliation of data between ECC and BW.
    Pointers if any would be really helpful.
    A step  by step guide, presentation,doc would be really appreciated.
    Thanks

    Thanks for the reply ravi but what i am looking for just opposite of whats explained in the link.
    I am looking for the info on how  to execute/trigger a transaction code in ECC as soon as the process chain starts in BW ie BW to ECC
    the doc explains how to trigger a process chain in bw from ECC.
    Thanks

  • Process chain starter

    Dear All,
    We have transported a process chain, however, while trying to change the start condition of the process chain starter, it is not allowing us to change the start condition. How to resolve this issue ?
    Thanks,
    Sam

    Hi,
    Are you trying to change the scheduling of the process chain starter or are you trying to change the starter itself?
    If you are trying to change the scheduling then you can do it and it might ask for Transport request, you can simply save the same in transport for the first time.
    If you are trying to change the start process then you can follow the standard procedure as to bring the changes from D to Q and then to P.
    If the process is enabled for the Objest Changeability in the transport connector then you can be able to change the process chains in the target system as well after storing the same in the transport.
    Hope this helps.
    Murali

  • Process chain start variant repaired in production

    Hi
    I took up tasks from our previous Bi team
    I am told we have followed the regular process of DEV --  QA and PROD for all  process  chains
    I see a strange observation in Production for a particular process chain in its start variant
    It is shown to run as immediate in the start variant, in the detail view , but
    it runs scheduled at a certain time every day, I can see the scheduled jobs released
    I see that in production it is attached to a request in repaired status
    process chain works fine and triggers regularly
    I am unable to understand why it shows as immediate in the start variant and however runs on a regular schedule

    Hi
    1) why does the start variant of this META chain show up as immediate, when it is actually running scheduled ?
    are you able to see the chain in green color(scheduled state).
    when you right click on start process chain step and you have option to select display scheduled job?..if yes check the start condition by double click on job.
    2)Does the change directly in production, could have brought in this behavior?
    We can change the start condition of process chain, when right click on start variant and select display variant..here you can see last changed name
    3) If , I re transport the whole META chain from DEV-QA --PRD , will the start variant change or will it cause trouble considering the fact that the start variant was repaired in PROD directly.
    No need to transport again, if you know the start condition of process chain, edit the same in prod and save it.
    Regards,
    Venkatesh

  • Process chain issue in production server

    hAI
    I created the process chain to load the transaction data . Then i transported to Quality and Production server.
    1) When i try to open the my process chain in RSPC in Production System. Then im not getting the process chain . But im getting black just.                                                                               
    But when i press 'change' button in Production Server then it says that "changes are carried out in original system" and then im getting my process chain .
    2) When i try to schedule my process chain in production server then it asking for new transport request . Why it is like that . Once i transport the process chain from development server to production server. Then it shouldn't ask for new request.
    Pls help in these secarios. I need urgent help .
    kumar

    Hi Kumar,
    I don't know what the problem is but you can copy in PRODUCTION environment the process chain to a new one.
    Please follow the steps:
    1. Open the problematic process chain (display or change mode).
    2. In the command line write the word "copy" .
    3. A popup will appear, insert a new name for the new process chain and confirm.
    4. The new process chain is now opened but it is not active yet.
    5. Delete the "old" START event and insert a new one.
    6. Activate and schedule the chain.
    While activating the new chain, no transport request should appear in PRODUCTION.
    Hope it helps, Amir.

  • How to send a email as soon as the process chain starts

    hi,
    i feel i am doing the right thing . but i couldn't get the mail.
    i have created the process chain.
    and attached the message to the start of the chain.
    i had inserted the subject to the message and the recepient id is attached to the addresse.
    any thing else to be done.
    every thing is connected.no need to do the settings as we were getting mails for the other chains.
    please do reply in detail.
    regards,
    soumya

    Ensure proper settings done in SCOT.also see after going in SCOT -->CLICK on JOB then see whether any job is scheduled to run to send mails or not ?if yes after what time period it runs.see this.
    else check this link
    Creating messages in Process chains

  • Process chain start by dialog process

    Hy Expert, i have a serious problem.When i schedule a process chain , it start by dialog process. What i do for start process chain by background process?
    Thank's a lot.
    Andrea

    HI
    You could do the following:
    1) Create an event variant (i think it was SM63 or something like that)
    2) write a short abab program that raises an event (see example)
    *& Report  start chain
    REPORT  start chain.
    CALL FUNCTION 'RSSM_EVENT_RAISE'
      EXPORTING
        i_eventid                    = 'your created event'
        i_eventparm                  = 'your variant'
    * EXCEPTIONS
    *   BAD_EVENTID                  = 1
    *   EVENTID_DOES_NOT_EXIST       = 2
    *   EVENTID_MISSING              = 3
    *   RAISE_FAILED                 = 4
    *   OTHERS                       = 5
    IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
    ENDIF.
    3)  Scedule your chain by event and activate it (you need to make it periodical to run severeal times).
    4)   Scedule the program.
    Hope this helps.
    Regards,
    Minima

  • How can I realize a period process chain start: the 1st to 3rd day every?

    Hi,All
    I want to set a start in a process chain as the following:
    a period value: the 1st to 3rd day every month
    How can I realize it ? Thanks.
    Best Regards
    Jiande Ding

    Hi Jiande Ding 
    create original chain as a Meta chain.
    create the another process chain with immedaite in start varaint..
    and put abap step in that PC after process chain..
    put this below code in that abap program.
    DATA: wwdate like sy-datum,
              WWDAY(2).
    wwday = sy-datum+6(2).
    IF WWDAY EQ '01' OR WWDAY EQ '03'.
       CALL FUNCTION 'RSPC_API_CHAIN_START'
      EXPORTING
        I_CHAIN             = <ur meta chain tech.name>
    ENDIF.
    Edited by: shanthi bhaskar on May 5, 2009 4:44 PM

  • Process Chain - Start Variant

    Hi Guys.
      I have a process chain and a start variant, but then when I transported. It seems not be transported the variant. CAn you please help me with this?
    Regards,
    Iván.

    check in forum, you will find lot of threads...
    1. Goto RSA1 --> Transport Connection.
    2. select objects by Object Types.
    3. You can see "Process Chain"
    4. double click on it. inthat select your process chain. go with transfer selection.
    5. Your process chain will transferred to right hand side. check the Grouping options on the right side tool bar. go with "Necessary Objects" under Grouping.
    6. you can see all the list od variants in that. go with transport icon on right side tool bar. you need to make sure all process variants collected in this.
    Nagesh Ganisetti.

  • Changes to process chain in the Production?

    Hi,
    I have process chain which is running hourly from 4 AM to 7 PM.We have made emial alert in the process chain at each event level.Now I have change some text in the email alert.As we dont tranfer the infopackage we have created the process chain i production itself.
    Please clarify my doubt:
    1.I will go ahead and change the text in email alert and again I will save it.
    2.Do I need to save and activate the process chain as a whole.
    3.Also do I need to schedule it again as it is running allredy succssfulyy.(in production)

    Hi Vasu,
        As you said this process chain has a hourly run between 4.00 am to 7.00 pm. Since for every run of this chain there will be a job scheduled, so if you wanna make any changes to your mail alert message and want those changes to be applicable from the next hour run, then you have to make this changes well prior this next run ( in between the current & next hour run). Before making those changes please do de-activate the chain, make the required changes & again Activate the chain. I hope this should solve your problem.
    Regards,
    Syed.

  • Process chain (RSPC) modifcation in Quality and production system

    Hi,
    In our landscape quality and production system is set as non modifiable. But we want to modify the process chain (RSPC) in Quality and production system.
    As per the thread Need input: do process chain/InfoPackages changeable on PROD in your compa?  in RSA1 -> Transport connection we made   RSPC ( Process Chain) ,  RSPT (process chain starter) and RSPV (process variants) are changeable.
    With this setting we are able to create/ edit new process chain in Quality and Production system. But we canu2019t edit the transported Process chain. i.e. process chain transported from Dev to Quality system.
    We donu2019t want to open Business Information Warehouse: Customer Namespace (/BIC/ ) in Quality and production system (Se06). Please let me know is there any other settings needs to be.
    We are on BI 7.0
    Regards
    Preethish

    Hi ,
    In RSA1 -> Transport Connection --> Object Changeability
    Object has 3 state
    Not Changable
    Changable Original
    Every thing changable
    What is the difference b/w Changable Original and Every thing changable
    Thanks..
    Preethish

Maybe you are looking for