Hi BI Experts, Good afternoon.
  Daily we are running the process chains in the night time. And the  first process chain starts at 22:30(master data loading).
  But from 5 days onwards, our process chains are running in the morning time around 10AM.
  We informed to our BASIS team but they could not do anything.
  What may be the problem.
  Can anyone tell me the solution?
Thanks in advance
  Anjali

May be your chain was in the wait at the scheduled time, as there were no adequate processes available at the app server to take up your job.
Check with your Basis ( and also your users ); about the optimal time to schedule the job and reschedule your jobs.
Ravi Thothadri

Similar Messages

  • [solved] To display Processes which are not running from constant process

    i have constant processes prostat1,prostat2,prostat3,prosta4,prostat6,prostat8,prostat9 (6 processes) runs to support the application
    Now my problem is
    i want to display the process which is not running (from the above 6 processes)
    Thanks in advance

    Try this
    echo "Constant processes not running"
    echo
    for PROC in prostat1 prostat2 prostat3 prostat4 prostat6 prostat8 prostat9
    do
            if [ ! "`ps -ef | grep $PROC | grep -v grep`" ]; then
                    echo $PROC
            fi
    doneBTW, those are 7....:-)

  • Scheduled process flows are not running automaticaly-OWB database clonning

    What I did:
    1.     Cloned the entire OWB repository database from live (bidb01.bh.xyz.com) server to new (green1.bh.xyz.com) server.
    ******     Source     New
    Physical Hostname     bidb01.bh.xyz.com     green1.bh.xyz.com
    DB Logical Hostname     xyzbidb      bidb-lh
    Service Name     BIPROD     BIPROD
    Listener Port     1521     1521
    Oracle Home of RDBMS     /app/oracle/home/product/10.2.0     /orabidb/oracle/product/10.2.0
    Oracle Home of OWB     /app/oracle/home/product/10.2.0/owb /orabidb/oracle/product/10.2.0/owb
    2.     Followed the Metalink Note 434272.1 (How To Update Warehouse Builder After A Database Cloning)
    Issue:
    Before doing the step-2, every time we put the new database up the normal process flows which run every day (10 AM, 1 AM , 2 AM , 2 PM, etc.) got executed on the production environment and hung the original processes that are being run on the production environment.
    After following the note 434272, scheduled process flows in production is working fine but in the new server it is not at all working.
    Could anyone please help me to fix this?
    Edited by: Padmanaban G on May 7, 2010 5:15 PM

    The issue was resolved by renaming the workflow. What is learned here is, we should not have same workflow name for two different workspace.

  • Process Chains is not running

    Hi All,
    I have created the Process Chains and Scheduled the Process chain on early morning 2.00AM. In STart variant, i have specified the time and date and saved the Process Chains. I have checked the Scheduled job in SM37 and found,BI_PROCESS_TRIGGER is scheduled. Today i have checked the Log view and found Chain has not executed.
    Can u pls help on this issue.
    Thanks,
    Jelina.

    Hi Jelina,
    In the scheduling options,check whethre you have selected direct scheduling or with meta chain. Make the desired one and also if you want it to repeat periodically, then Check the Periodic job checkbox and select the periodic vaules from the Period Values Tab.
    Hope this helps...

  • Process Chains are not shown in QAS?

    Hi all
    Version :  BI 7.0
    I transported the process chain from DEV to TEST system and my transports are successful. But when i logon to test system and double click on my process chain ... i dont view my chain.
    What could be the possible reason?
    Please help me out.

    Yes i did import to the right client. I can see my process chain name left side. But when i double click on it. It should show the process chain right side in the Planning view. But i dont my process chain there.
    I re-transported and checked but still having the same issue

  • Process flows are not running in OWB

    I have a process flow which has a main process and this main process calls 3 subprocesses and 1 externel process. This workflow was running fine and it suddenly stopped working and when I try to run it from WF monitor it is giving the following error.
    Activity CALWINDW_INC_LOAD_PF_WE
    Result Exception
    Error Name -20001
    Error Message ORA-20001: Task CALWINDW_INC_DELETE_PF does not exist. Please check that the ProcessFlow has been deployed successfully. ORA-01403: no data found
    Error Stack Wf_Engine_Util.Function_Call(WB_RT_WORKFLOW_UTIL.EXECUTE_TASK, CLWNPKG, 200509200915, 37461, RUN).
    I tried running it from OWB deployment manager but it didn't work.
    I have checked all the process flows and the mappings all are deployed and all the mappings are running sepreatly. I tried dropping and deploying the process flow again and it deployed successfully without any error. We have tried rebooting the server, creating new PF location and new process flows, but nothing worked out. Becuase of this issue we can't run the whole process. Any help will be appriciated please.

    May be your chain was in the wait at the scheduled time, as there were no adequate processes available at the app server to take up your job.
    Check with your Basis ( and also your users ); about the optimal time to schedule the job and reschedule your jobs.
    Ravi Thothadri

  • OID is up & running but "ldap"  process are not running

    Hi all,
    Oracle Internet Directory is up & running but LDAP processes ( Not Running ---- Process oidmon
    Not Running ---- Process oidldapd
    Not Running ---- Process oidrepld
    Not Running ---- Process odisrv) are not running.
    I am trying to configure SSO for reverse proxy server and ran the command ssocfg.sh https proxyServerName proxyServerPort
    and when i am trying to go for next step that is ldapmodify -D cn=orcladmin -w welcome1 -v -f setdasurl.ldif
    it is showing up cannot connect to LDAP server. and also when i am trying to acess SSO admin Server the redirection url is showing up with 404 page not found error.
    pls help me
    Thanks

    Do 'oidctl status' and check if the 'oidldapd' is up and running. If not, start 'oidmon' by executing the command 'oidmon start'.
    To start 'oidldapd', use 'oidctl' command.
    Eg: oidctl connect=<sid_name> server=oidldapd instance=<instance_num> start
    Sometimes, when you start 'oidmon', the 'oidldapd' process is also started. So, its a good idea to do 'oidctl status' after 'oidmon start'

  • Scheduled Brio/IR Jobs are not running as expected in EPM 11.1.2.2

    Hi All,
    We are observing some scheduled jobs are not running as expected,they are not running on the scheduled time.
    Given below are more details.
    We have 2 Jobs running at 6:00 AM daily based on single Recurring Time Event and it is observed that this jobs are not running on time(ex: 6:06 AM EST).
    I tried verifying Consolidate Job Status in workspace admin options and the v8_RecurtimeEvent table for any miss in the 'Next Run Time',
    but they were having the scheduled date/time of run.No clue from EPM Logs.
    Interesting observation is the same jobs are running after updating the schedule time a little bit further(ex: 6:06 AM to 6:07 AM),but again after some days
    the updated job(6:07 AM ) will stop running.
    Thanks,

    Put the IR job logs in TRACE:32 mode which will give more information in the logs . Refer this document link to put in TRACE mode :http://docs.oracle.com/cd/E17236_01/epm.1112/epm_install_troubleshooting_1112200.pdf
    Thanks,
    KK

  • How to Notify if Process Chain DOES NOT complete?

    How do I use Process Chains to notify me if the end process of a chain DOES NOT run by a certain time? Example: Chain starts at 6PM every night, always finishes by 7:30. If it doesn't complete by 8:00, I want to be notified. I can spawn an event on completion of the chain, but the 8PM job has to notify me ONLY IF this event is not active. How to do that?

    Well you can make the ABAP process type send message
    RSPC>from main menu Settings>Maintain process types
    change mode -->select process type "ABAP" and change "possible events" to "Process ends successful or Incorrect" save it.
    come out of process chain and goto the process chain maintenance again.
    In regards to your question of 18 steps ,as i said you only need this ABAP process type once at the END of the Process chain to SET the flag status = X.
    Another Process chain runs at 8.00 with only one process type ABAP process type to check the status in table if empty or X and send message accordingly,
    Fyip - table  RSPROCESSLOG and FM - RSPC_PROCESS_FINISH also available at your disposal to get some leads.
    You can wait until some one has better solution and implemented it before,i just put my thoughts in to it,its not imperative for you.
    I leave the thoughts with you.
    Hope it Helps
    Chetan
    @CP..

  • Process chain is not triggering through event after BW Upgrade

    Many of our process chains are event based.
    After BW upgrade 7.0  to BW 7.31 we tried to trigger the event through  SM64 Tcode. But the process chains are not getting triggered.
    Could anyone please guide me what might be the issue.

    Hi Bharan,
    Can you please check once the start variant of process chain which are based on event.I think it should trigger after event is triggred.
    Regards,
    Ganesh Bothe

  • Process Chains are running from 3 days

    Hi BW experts,
    Daily our process chains run in the night time.
    But Friday's jobs are still running. So i stopped all process chains on saturday.
    Friday's jobs did not finish till now. Still these are running. These are in active.
    Some process chains are stopped at CREATE INDEXES.
    Some process chains are stopped at ODS Activation.
    These are in yellow status.
    Please can anyone tell me the solution for this. I have to start our process chains today night.
    How can i rectify this problem? Can we stop the yellow status jobs
    Thanks & Regards
    Anjali

    Hi 
    check the loads in the process monitor whether it has completed or not??
    Some times it will show yellow if it gets completed also.Otherwise check for the source systems from where u r getting data.There may be a problem with that.
    Cheers
    Sunil Reddy LCP

  • Golden gate extract and replicate process are not running.

    All,
    I am trying replicate data between two oracle databases using golden gate.
    I am trying this scenario in a single machine(two databases and golden gate are on same windows machine)
    1. I have two databases PROD, UAT both are running on 11.2 oracle home.
    2. Created the ggate user both the databases, and enabled supplemental logging.
    3. Ran the following scripts in both databases.
    SQL> @marker_setup.sql
    SQL> @ddl_setup.sql
    SQL> @role_setup.sql
    SQL> grant GGS_GGSUSER_ROLE to ggate;
    SQL> @ddl_enable.sql
    4. Connected the source database (PROD) in ggsci prompt
    GGSCI (home-c07402bbc5) 79> add extract ext1, tranlog, begin now
    add exttrail C:\app\Bhanu\Goldengate\lt, extract ext1
    edit params ext1
    EXTRACT ext1
    USERID ggate@PROD, PASSWORD 123456
    RMTHOST home-c07402bbc5, MGRPORT 7840
    rmttrail C:\app\Bhanu\Goldengate\lt
    ddl include mapped objname bhanu.* // bhanu is a schema in PROD database.
    TABLE bhanu.*;
    5. Connected the target database(UAT) in ggsci prompt
    add checkpointtable ggate.checkpoint
    edit params ./GLOBALS
    GGSCHEMA ggate
    CHECKPOINTTABLE ggate.checkpoint
    add replicat rep1, exttrail C:\app\Bhanu\Goldengate\Mt,checkpointtable ggate.checkpoint
    edit params rep1
    replicat rep1
    ASSUMETARGETDEFS
    userid ggate@UAT, password 123456
    discardfile C:\app\Bhanu\Goldengate\rep1_discard.txt, append, megabytes 10
    map bhanu.*, target kiran.*;
    After that started the extract, replicat using
    start extract ext1, start replicate rep1
    Now the status.
    GGSCI (home-c07402bbc5) 103> info all
    Program Status Group Lag Time Since Chkpt
    MANAGER RUNNING
    EXTRACT STOPPED EXT1 00:00:00 00:11:43
    REPLICAT STOPPED REP1 00:00:00 00:21:16
    Can you please help me what is wrong in my setup and why extract and replicate process are not running.
    Edited by: user12178861 on Nov 19, 2011 11:22 AM

    Thanks for your quick reply.
    I have done few changes but extract, replicate process not running.
    couple of points I would like to share with you regarding my setup.
    1. I am using single golden date instance to replicate the data between PROD and UAT databases.
    2. GGSCI (home-c07402bbc5) 1> dblogin userid ggate@PROD,PASSWORD 123456
    Successfully logged into database.
    GGSCI (home-c07402bbc5) 2> info all
    Program Status Group Lag Time Since Chkpt
    MANAGER RUNNING
    EXTRACT STOPPED EXT1 00:00:00 01:23:29
    REPLICAT STOPPED REP1 00:00:00 01:33:02
    GGSCI (home-c07402bbc5) 3> VIEW REPORT EXT1
    ERROR: REPORT file EXT1 does not exist.
    GGSCI (home-c07402bbc5) 4> start er *
    Sending START request to MANAGER ...
    EXTRACT EXT1 starting
    Sending START request to MANAGER ...
    REPLICAT REP1 starting
    GGSCI (home-c07402bbc5) 5> VIEW REPORT EXT1
    ERROR: REPORT file EXT1 does not exist.
    GGSCI (home-c07402bbc5) 6> info all
    Program Status Group Lag Time Since Chkpt
    MANAGER RUNNING
    EXTRACT STOPPED EXT1 00:00:00 01:24:10
    REPLICAT STOPPED REP1 00:00:00 01:33:44
    Target :
    GGSCI (home-c07402bbc5) 1> dblogin ggate@UAT,PASSWORD 123456
    ERROR: Unrecognized parameter (GGATE@UAT), expected USERID.
    GGSCI (home-c07402bbc5) 2> dblogin userid ggate@UAT,PASSWORD 123456
    Successfully logged into database.
    GGSCI (home-c07402bbc5) 5> add replicat rep1, exttrail C:\app\Bhanu\Goldengate/lt,checkpointtable ggate.checkpoint
    ERROR: REPLICAT REP1 already exists.
    GGSCI (home-c07402bbc5) 6> delete replicat rep1
    Deleted REPLICAT REP1.
    GGSCI (home-c07402bbc5) 7> add replicat rep1, exttrail C:\app\Bhanu\Goldengate/lt,checkpointtable ggate.checkpoint
    REPLICAT added.
    GGSCI (home-c07402bbc5) 8> edit params rep1
    GGSCI (home-c07402bbc5) 9> start er *
    Sending START request to MANAGER ...
    EXTRACT EXT1 starting
    Sending START request to MANAGER ...
    REPLICAT REP1 starting
    GGSCI (home-c07402bbc5) 10> info all
    Program Status Group Lag Time Since Chkpt
    MANAGER RUNNING
    EXTRACT STOPPED EXT1 00:00:00 01:29:46
    REPLICAT STOPPED REP1 00:00:00 00:00:48
    3. Is mandatory that I need two golden gate instances running each side ?
    Thanks for spending your time on this problem.

  • HOW TO STOP THE PROCESS CHAIN WHICH IS RUNNING IN THE PRODUCTION?

    HI ALL,
    CAN ANYONE TELL ME HOW TO STOP THE PROCESS CHAIN WHICH IS RUNNING DAILY AT 5.00 PM. I NEED TO STOP THE PROCESS CHAIN FOR COUPLE OF DAYS AND THEN RESTART IT AGAIN.
    cAN ANYONE TELL ME THE PROCEDURE TO STOP THE ENTIRE PROCESS CHAIN RUNNING IN THE PRODUCTION.
    THANKS
    HARITHA

    Hi,
    First and foremost let me advice you to be very careful while doing this.
    For Rescheduling
    RSPC> chain > Goto > Planning view and
    click on Execution tab > select > Remove from Schedule and then in Maintain variant of start process reschedule for the day you require it to run.
    For terminating active chain
    You can start from SM37, find the process WID/PID then go to SM50 or SM51 and kill it. Once its done come back to RSMO and check the request, it should be red but again manually force to red and save by clicking on the total status button in the status tab. This shuld ensure that the process is killed properly.
    The next step will be to go to targets that you were loading and remove the red requests from those targets.
    Note: For source system loads you may have to check if the request is running in the source system and kill if needed and pull it again.
    But for BW datamart delta loads u may have reset the datamarts in case u are going to pull the delta again.
    Re: Kill a Job
    Re: Killing a process chain.
    Regards,
    JituK

  • Processing Instructions are not allowed in SOAP documents

    Hi, there. I am trying to integrate WS-Security into our server using the api-sample in JWSDP 1.6 as it is the one that fits into our current architecture in place.
    I have the following code:
    DOMSource domSource = new DOMSource( indoc );
    SOAPPart soapPart = msg.getSOAPPart();
    soapPart.setContent( domSource );
    ProcessingContext context = new ProcessingContext();
    context.setSOAPMessage( msg );
    where indoc is an org.w3c.dom.Document object.
    The last line throws an exception that is ultimately caused by:
    java.lang.UnsupportedOperationException: Processing Instructions are not allowed in SOAP documents
    at com.sun.xml.messaging.saaj.soap.SOAPDocumentImpl.createProcessingInstruction(SOAPDocumentImpl.java:109)
    (Please find the complete (partially edited) stack trace at the end of this message.)
    The exception is thrown even when the following very simple (unsigned) SOAP message is submitted:
    <?xml version="1.0" encoding="utf-8"?><soap:Envelope xmlns:soap="http://schemas.xmlsoap.org/soap/envelope/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema"><soap:Body><requestMessage xmlns="urn:schemas-company-com:transaction-data-1.17"><merchantID>ever03</merchantID><ccAuthService run="true"/></requestMessage></soap:Body></soap:Envelope>
    As you can see, the only processing instruction is the XML processing instruction, which I don't believe is disallowed in SOAP documents, right? So, I'm not sure why it's complaining about processing instructions. I'm guessing during the transformation into whatever form ProcessingContext wants the document to be in, certain processing instructions are erroneously being inserted.
    I would appreciate any inputs. Below is the stack trace, partially edited to show only the relevant lines.
    Thanks,
    Ever
    com.sun.xml.wss.XWSSecurityException: com.sun.xml.messaging.saaj.SOAPExceptionImpl: Unable to create envelope from given source:
    at com.sun.xml.wss.SecurableSoapMessage.getEnvelope(SecurableSoapMessage.java:109)
    at com.sun.xml.wss.SecurableSoapMessage.init(SecurableSoapMessage.java:89)
    at com.sun.xml.wss.SecurableSoapMessage.setSOAPMessage(SecurableSoapMessage.java:400)
    at com.sun.xml.wss.ProcessingContext.setSOAPMessage(ProcessingContext.java:199)
    Caused by: com.sun.xml.messaging.saaj.SOAPExceptionImpl: Unable to create envelope from given source:
    at com.sun.xml.messaging.saaj.soap.EnvelopeFactory.createEnvelope(EnvelopeFactory.java:111)
    at com.sun.xml.messaging.saaj.soap.ver1_1.SOAPPart1_1Impl.createEnvelopeFromSource(SOAPPart1_1Impl.java:39)
    at com.sun.xml.messaging.saaj.soap.SOAPPartImpl.getEnvelope(SOAPPartImpl.java:98)
    at com.sun.xml.wss.SecurableSoapMessage.getEnvelope(SecurableSoapMessage.java:107)
    ... 32 more
    Caused by: javax.xml.transform.TransformerException: java.lang.UnsupportedOperationException: Processing Instructions are not allowed in SOAP documents
    at com.sun.org.apache.xalan.internal.xsltc.trax.TransformerImpl.transform(TransformerImpl.java:647)
    at com.sun.org.apache.xalan.internal.xsltc.trax.TransformerImpl.transform(TransformerImpl.java:279)
    at com.sun.xml.messaging.saaj.soap.EnvelopeFactory.createEnvelope(EnvelopeFactory.java:97)
    ... 35 more
    Caused by: java.lang.UnsupportedOperationException: Processing Instructions are not allowed in SOAP documents
    at com.sun.xml.messaging.saaj.soap.SOAPDocumentImpl.createProcessingInstruction(SOAPDocumentImpl.java:109)
    at com.sun.xml.messaging.saaj.soap.SOAPPartImpl.createProcessingInstruction(SOAPPartImpl.java:368)
    at com.sun.org.apache.xalan.internal.xsltc.trax.SAX2DOM.processingInstruction(SAX2DOM.java:177)
    at com.sun.org.apache.xml.internal.serializer.ToXMLSAXHandler.processingInstruction(ToXMLSAXHandler.java:583)
    at com.sun.org.apache.xalan.internal.xsltc.trax.DOM2TO.parse(DOM2TO.java:224)
    at com.sun.org.apache.xalan.internal.xsltc.trax.DOM2TO.parse(DOM2TO.java:121)
    at com.sun.org.apache.xalan.internal.xsltc.trax.DOM2TO.parse(DOM2TO.java:85)
    at com.sun.org.apache.xalan.internal.xsltc.trax.TransformerImpl.transformIdentity(TransformerImpl.java:592)
    at com.sun.org.apache.xalan.internal.xsltc.trax.TransformerImpl.transform(TransformerImpl.java:638)
    ... 37 more

    Me again... I just realized my second post sounded like I had figured out the problem. No, I still have the problem. I just added the one line that I forgot to include in my original post.
    I would sincerely appreciate any help.
    Ever

  • Process chians r not running as per the scheduled time.

    Hi sriends,
    Unable to run the process chains(back ground).
    Every day our process chains r runing properly but all of sudden they are not triggering on the specified time and there is no error msg.
    pls give me some idea to resolve this....
    Thanks in advance,
    Reddy.

    Hi Ram,
    You need to go and check the released Job of your Process Chain.  Go to Planning View of your Process Chain, then right click on your start variant and check for "Display all Jobs".
    Then it will show the list of all finished and released Job. Check whether the finished Jobs are having any delay. If there is any delay then it is related to your system performance. If not double click on the released JOb and check the schduling details.
    Hope it helps!!!
    Cheers,
    Neelesh Jain.

Maybe you are looking for

  • Error / Failed to create file in the network

    I'm using and enjoying the Oracle Data Integrator and created two packages for extraction and loading. But trying to create the file in the directory on the network get an error. I checked the permissions, but without success. Can anyone help me? Tha

  • ITunes store - shopping in an other country?!

    Hello, I have an account for Switzerland, now I found a song in the US shop from. How can I shop in the US shop? It always tells me I don't have the rights for the US shop and sends me to the Swiss shop. But there the song does not exists. The same h

  • Itunes 10.7 freezing/will not open

    Hello Everyone, I recently purchased a new mac mini.  I've set up the computer, transferred files, and updated my software.  Everything seems to be working great, with the exception of itunes.  When I attempt to open itunes one of two things happens

  • Why is all my memory getting used all the time?

    Hey My mac is recently very slow. I have posted a tread about this: https://discussions.apple.com/message/23923203#23923203 I have now found out that my memory useage is very high. I do sometimes use 3.99 out of 4. Most of the time it is around 2,5-3

  • Kind of easy date question

    guys, I need a little help. I have a banned_from field and banned_to field in my database, both fields can be null or just one of the fields can be filled in (i.e. just the banned_from or just the banned_to date. OR obviously both fields can be fille