Process Flow Transistion dissapears

Hello!
Some of the created transitions are not created in the actual Process Flow. This is obvious when looking in the Process Monitor. When I redraw the one missing, deploy and execute the process flow again. I get more transitions but not all of them!
Does anyone know how to solve this issue?
Best regards,
Tina

Hi Tina,
it is an OWB bug. For more details and workarounds look at these threads
[owb process flow error handling|http://forums.oracle.com/forums/message.jspa?messageID=2138808#2138808]
[10GR2 - Process Flow executes in wrong order...|10GR2 - Process Flow executes in wrong order...
Also on Metalink is registered a lot of bugs for different releases (including 10.2.0.4 and 11.1.0.7, for example bug 7603716)
Regards,
Oleg

Similar Messages

  • Major problem - Process Flows hanging randomly - 11.2.0.1

    Hi,
    We are experiencing the following problem.
    Randomly process flows sit doing nothing.
    Have ran some days and totally fine. Process flows fine - each activity has all the necesassry outgoing activities.
    What causes this?
    If run again - fine.
    How do we resolve.
    We need to be able to kick off the process and leave it to run without having to check if it hanging al the time.
    Any help/advice would be great.
    Many Thanks

    Hi,
    I found out that wrong ordering of transitions may cause strange problems. In owb, check that the outgoing transistions of each operator are numbered sequenty (0,1,2, ...). Sometimes, some number appear twice, e.g. 0,1,1). This often happens after an existing transition was deleted.
    And make sure that the "else" transition (the one without any condition) always has the highest number.
    Regards,
    Carsten.

  • URGENT:error while deploying a process flow

    EMP_COUNT is a mapping which i have deployed .
    when i try to deploy a process flow i get the following error:
    OMB05602: An unknown Deployment error has occured for Object Type API8028: No signature is available for mapping EMP_COUNT because the generation language is undefined. Please set the generation language property of this mapping, or generate this mapping to set the generation language property to a default value..
    thnx in advance

    OMB+> OMBALTER MAPPING 'EMP_COUNT' SET PROPERTIES (GENERATION_LANGUAGE) VALUES ('PLSQL')
    Fast enough? ;-)
    Regards,
    Detlef

  • Cannot deploy process flow package specification from file

    Hi,
    we are using owb 11gr2 on linux. We successfully managed to deploy mappings and tables into a specification file, and then deploy from that file into the target database (RAC). But when we try to deploy a process flow package we run into an error:
    A process flow package can be deployed to a specification file. But a deployment from that specification file fails with the error: " OMB05623: Cannot deploy specification from file. Exception follows. nulll"
    ### SETUP
    set CONN_DESIGN "xxx"
    set CONN_TARGET_DESIGN "yyy"
    set CONN_TARGET_RT "xxx'"
    set DIR "D:\\tmp"
    set RELEASE "V0_2"
    set file "$DIR\\$RELEASE"
    set plan "FILE_DEPLOY_$RELEASE"
    ### Deployment via control center: works!
    OMBCONNECT $CONN_DESIGN
    OMBCONNECT CONTROL_CENTER $CONN_TARGET_RT
    OMBCC '/KLINGEL_DWH'
    OMBCREATE TRANSIENT DEPLOYMENT_ACTION_PLAN '$plan'
    OMBALTER DEPLOYMENT_ACTION_PLAN '$plan' ADD ACTION 'PF_TEST' SET PROPERTIES (OPERATION) VALUES ('REPLACE') SET REFERENCE PROCESS_FLOW_PACKAGE '/KLINGEL_DWH/WF_DWH/PF_TEST'
    OMBDEPLOY DEPLOYMENT_ACTION_PLAN '$plan'
    OMBDISCONNECT CONTROL_CENTER
    OMBCOMMIT
    OMBDISCONNECT
    ### Deployment via specificatin file: fails!
    OMBCONNECT $CONN_DESIGN
    OMBCONNECT CONTROL_CENTER $CONN_DESIGN
    OMBCC '/KLINGEL_DWH'
    OMBCREATE TRANSIENT DEPLOYMENT_ACTION_PLAN '$plan'
    OMBALTER DEPLOYMENT_ACTION_PLAN '$plan' ADD ACTION 'PF_TEST' SET PROPERTIES (OPERATION) VALUES ('REPLACE') SET REFERENCE PROCESS_FLOW_PACKAGE '/KLINGEL_DWH/WF_DWH/PF_TEST'
    OMBDEPLOY DEPLOYMENT_ACTION_PLAN '$plan' AS SPECIFICATION TO '$file.xml'
    OMBDROP DEPLOYMENT_ACTION_PLAN '$plan'
    OMBDISCONNECT CONTROL_CENTER
    OMBCOMMIT
    OMBDISCONNECT
    OMBCONNECT CONTROL_CENTER $CONN_TARGET_RT
    OMBDEPLOY SPECIFICATION FROM '$file.xml'
    ### OMB05623: Deployment von Spezifikation aus Datei nicht möglich. Exception folgt. null
    ###OMB05623: Cannot deploy specification from file. Exception follows. nullIf we use the operation DROP it works. But REPLACE and CREATE do not work.
    We get the error regardless whether the code is executed as an expert or on the command line at a windows client.
    Does anyone knows a workaround?
    Deployment via a specification file is a must due to license and architecture requirements.
    Thanks,
    Carsten.

    Its woked fine for me for OWB 10.2.0.4 .... some steps are missing from code like
    when you are connecting again it should be
    OMBDISCONNECT
    OMBCONNECT CONTROL_CENTER $CONN_TARGET_RT
    OMBDISCONNECT
    OMBCC '/KLINGEL_DWH'
    OMBCONNECT CONTROL_CENTER $CONN_TARGET_RTI think you can try the same on different system .
    Cheers
    Nawneet

  • A/R process flow with notice of readiness for shipment

    Hi,
    I'm trying to implement the following A/R process flow:
    - sales order
    - xx% A/R down payment invoice
    - notice of readiness for shipment
    - incoming payment
    - delivery
    - A/R invoice (xx% down payment to be deducted here)
    What's the best way to implement it?
    Thanks
    Fabio

    Hi,
    no, it's something different. It is because we want to be paid before shipping anything.
    In more detail:
    - we request a certain amount of down payment after the order and before starting production
    - we request final payment before we deliver goods
    Thanks
    Fabio

  • MM - PO process flow chart

    MM Gurus , Can any one help me to provide me with the MM  PO and Change PO process flow diagram .Pl send me the diagram or links to my email ID
    Thanks in advance .Will give you points
    James
    [email protected]

    Dear James,
    Process Flow:
    1)Determination of Requirements: Through MRP, purchase requisitions
    2)Source Determination: helps you identify potential sources of supply, creating requests for quotation (RFQs
    3) Vendor Selection and Comparison of Quotations: The system is capable of simulating pricing scenarios
    4) Purchase Order Processing: information from the requisition and the quotation to help you create a purchase order. scheduling agreements and contracts are also supported.
    5) Purchase Order Follow-Up: The system checks the reminder periods you have specified. up-to-date status of all purchase requisitions, quotations, and purchase orders.
    6) Goods Receiving and Inventory Management: Goods Receiving personnel can confirm the receipt of goods simply by entering the Po number
    7) Invoice Verification: The system supports the checking and matching of invoices, and clearing invoices for payment.
    Flow Chart for PO & MM process :
    RFQ (ME 41) --> Maintain Quotation ( ME 47) -> Price comparision ( ME 49)>
    -->Create PR ( ME 51 N) --> Create PO ( ME 21N) --->
    > Good Receipt  wrt PO( MIGO)> Invoice Verification wrt PO ( MIRO)
    I hope this will suffice your need & if satisfied please reward points,
    Vivek

  • Demo on SAP Transportation Management Overview + End to End Process Flow by Navin Nadpurohit-SAP TM Consultant - Krypt Inc-a Leading SAP Supply Chain Company

    Hello All,
    Attached is the link explaining SAP Transportation Management Overview and a system demonstration of End to End Process Flow.
    Link:
    TM Overview + End to End Process Flow - YouTube
    Thanks and best regards,
    Navin

    Very Good Demo Navin

  • RPE-01008: Recovery of this request is in progress in process flows.

    Hi,
    I am calling shell script as an userdefined activity in a process flows.
    All the process flows were working fine.
    Today, all the process flows wherever the shell script is called ended up with an error showing " RPE-01008: Recovery of this request is in progress".
    Could any one please explain, what might be reason?
    Thanks in advance.
    Thank you,
    Regards,
    Gowtham Sen.

    Hi,
    we have exactly the same problem here.
    Does anybody have a solution?
    regards
    Lutz

  • To check whether a process flow is valid or not

    Hi,
    I want to check whether a OWB process flow is valid or not inside a PL/SQL block. Can anyone let me know about any repository table or view where I can check the process flow status.
    Regards,
    Poulose

    Use display schedule job option from the context menu of the start variant of the process chain.
    When u chick this.. u will get the available job on this start process.. There u can see whether the process chain in schedule mode or not?
    If u can see multiple schedule then u can delete the older ones which are not needed and then u can maintain only one schedule job.
    If u click twice.. then there are chances that u might end up with the 2 schedule job with the same time frame.. .. so check the same with the steps mentioned..... if u find two jobs then u need to delete one.. if not there might be chance that ur PC might get trigger twice.. and one trigger will gets failed. and the other one will gets executed..
    Thanks
    I hope this is clear to u..
    Assign points if this helps

  • Process flow of excise duty from procurement to sales accounting entry with amount.

    Dear Expert ,
    Kindly any one help the process flow of excise duty calculation from procurement to sales accounting entry with amount.  for example.- if material amount is Rs. 10,0000 and excise duty is 8% , edu ecss 2 % , and sec ecss 1%. I want know the accounting entry on- MIGO, J1IEX, MIRO, F-43  AND , PGI, BILLING DOCUMENT, J1IJ , TR6 CHALLAN, J2IUN.
    Regards
    Akshaya

    Hi,
    In case of
    A. Procurement : there are two types of procurement viz. Local and Import
    LOCAL
    1. MIGO
    Inventory A/c Dr
    To GR?IR
    2. J1IEX
    CENVAT Receivable (Basic) A/c - Dr
    CENVATReceivable (Ecess) A/c - Dr
    CENVAT Receivable (S & H) A/c - Dr
    To CENVAT Clearing
    3. MIRO
    CENVAT Clearing A/c - Dr
    To Vendor A/chrough
    4. F-43
    No excise entry through SAP direct posting but through manual posting in case using TAXINN procedure.
    5. TR6 Challan
    PLA Payment  (Basic) A/c - Dr
    PLA Payment (Ecess) A/c - Dr
    PLA Payment (S & H) A/c - Dr
    To PLA on Hold A/c
    IMPORT
    1. MIRO
    ECS+SECS on Cus+CVD A/c Dr (consists of ECS on custm+cvd and S & H on custm+cvd)
    CVD Clearing A/c Dr (consists of Additional Duty CVD and CVD)
    Customs Clearing A/c Dr (consists of Basic Customs)
    To Customs Vendor
    2.  MIGO
    Inventory A/c - Dr
    To GR/IR A/c
    To Customs Clearing (consists of Basic Customs)
    To ECS+SECS on Cus+CVD (consists of ECS on custm+cvd and S & H on custm+cvd)
    3. J1IEX
    CENVAT Receivable (Basic) A/c - Dr
    CENVATReceivable (Ecess) A/c - Dr
    CENVAT Receivable (S & H) A/c - Dr
    To CVD Clearing
    4. F-43
    No excise entry through SAP direct posting but through manual posting in case using TAXINN procedure.
    5. TR6 Challan
    PLA Payment  (Basic) A/c - Dr
    PLA Payment (Ecess) A/c - Dr
    PLA Payment (S & H) A/c - Dr
    To PLA on Hold A/c
    Sales
    1. PGI
    COGS A/c Dr
    To Inventory
    2. Billing Document
    Excise
    ED Suspense A/c Dr
    To Liability for BED
    To Liability for ECS
    To Liability for S & H
    Customer
    Customer A/c Dr
    To ED Suspense A/c
    To Revenue
    To VAT / CST
    Hope your doubts are clear.
    Regards,
    Tejas

  • Training and Event management.Process Flow..

    Hi, Experts,
    Can any body give me some notes on  Training and event management and process flow also like integration between ECC-6.0 to Non SAP
    1.Training request
    2.Appraisal documents for performance feedback
    3.Tracking Feedback processes
    Pls help me in configuring these services.
    With Regards,
    San Rao.

    Hi san rao,
    as per your reply you using the new appraisal template and also you have released the template now simply run the BSP application HAP_DOCUMENT and access the appraisal documents  
    attach these BSP applications in your portal system.
    following pages of the above application will  be help full
    documents_todo
    documents_received_open2
    documents_where_participated
    Regards,
    Umesh Chaudhari.

  • When a process flow activity takes a long time to run.

    Hello,
    I have a process flow activity that sometimes takes a long time to run so that the process flow never ends. Is it possible that I can set the activity so that during a certain time that this has not been executed automatically flow process to continue?
    I'm Using Oracle Warehouse Builder 11g on Windows Server 2003 R1.
    Greetings and thanks.

    What I've done in the past is just use a small polling procedure (PL/SQL) and a conditional transition in the process flow, depending on what the proc returns (Continue or Fail) then the flow of control in the Process is changed.
    I think the key also is to not have too much paralellism going on too, that way it's easy to streamline the PF and remove slow moving processes to a more linear path (stopping bottle necks on your logical AND).
    Edited by: NSNO on Apr 29, 2010 2:31 PM

  • How can I pass parameters from one process flow to another process flow?

    How can I pass parameters from one process flow to another process flow (sub process) in warehouse builder? let me know the steps I have to do in warehouse builder.
    Thanks in advance,
    Kishan

    Hi Kishan,
    Please post this question to the Warehouse Builder forum:
    Warehouse Builder
    Thanks, Mark

  • Can I change a process flow at run time??

    Hello everybody,
    I work in Oracle BPMS 11.1.1.5. I need to change a process flow at run time due to changes in the business logic, I mean add, delete and modify tasks, navigation flow, etc. I know business rules can be modified using Oracle BPM Composer, but I couldn't find the way to modify the process flow. I have seen other BPMS, like BizAgi, for ex. that can do that. Do Oracle BPMS have that functionality? Please I need it a lot!!!!
    Regards and thanks in advance,
    isabelbernely

    Hi
    As JonPetter mentioned, you can get this and preferably get only from Support. I hope you have some license if you going to prod with this. Use that and if possible talk to your sales guy and create a support account. Then request the feature pack. The thing is, if we put it in some public shared location, it is the violation of using the oracle product. Unless someone takes risks they may upload but still its not advisable.
    Sorry
    Ravi Jegga

  • Experts VS Process Flows on OWB 10g Release 2 (Paris)

    I was looking at the the new features list for OWB 10g Release 2 (Paris), and I notices the new feature called Experts. Does anyone have any insight into when an Expert would be used instead of a Process Flow? It doesn't look like Process Flows are going away, so I was trying to get a grasp of the use for Experts.
    From Here:
    http://www.oracle.com/technology/products/warehouse/htdocs/owb10gr2%20new%20features.htm
    Experts. Experts are solutions that enable advanced users to design solutions that simplify routine or complex tasks that end users perform in Warehouse Builder. You can design these solutions in the Expert Editor which resembles the Process Flow Editor and shares many of the same commands and navigational tools.

    Hi,
    Just to start with the Experts capabilities, they can be used for designing schema objects.......I tried with an expert for sampling the source files, creating External Tables on top of it....validating and deploying..........itz very interesting to work with.........I am unable to see the practical use of this for end users.....
    where as we all know, the PF can only be for executing the deployed objects.....
    Mahesh

Maybe you are looking for