Hi Gurus,
Can you please tell me the process of Sub Assets in AUC and in normal assets as well?
How to capitalize it, retire it, what to do if any sub assets is gone for repairing?
Please revert asap.
Thank You

Hi,
A sub asset is one ore more subs on an main asset.
When you use investment orders/projects I think you can't use sub-assets.
When you have sub-assets for AUC in asset accounting it is possible.
Sub assets you are use to make a group of assets that belongs to one object.
In the fieldstatus you can set up the copy rules from the main asset to the sub-asset and what you can change.
In the sub asset you can have different depreciation rules, cost center,.. from the main asset.
Like the boulding (main asset) depreciation is 40 years. In year 5 you do an investment then you say 35 years
You have to retire the main and sub assets separate
How and if to use sub assets is based on your requeirements, first the requirements and then to found a solution and not the way arround otherwise you have still 100 options

Similar Messages

  • Settlement of Investment Order - Auto creation of Sub asset for settlement

    < MODERATOR:  Message locked.  Please post this in the [ERP Financials - Asset Accounting|SAP ERP Financials  - Asset Accounting;. >
    Dear experts
    Request your help on Investment orders settlement.
    We are doing settlement of Investment orders to sub asset numbers, where sub assets are created well in advance.
    Our client want system to create sub asset numbers automatically, while doing the settlement of Investment orders itself.
    Is it possible ?, If possible, please let me know, what are the settings I need to do to meet this requirement.
    Thanks in advance
    S. Habib Pasha.

    Hiya,
    Go to IMG --> Controlling --> IO --> Actual Postings --> Settlement --> Automatic Generation of Settlement Rules.
    There is no SAP Standard created for settlements to sub-assets, so you'll need to create one using option 4 there "User-Defined Strategies for Automatic Generation ...".
    Once this is done, get an ABAP Developer to code the settlement rule by creating a custom project in that same transaction. The rule will be similar to the SAP Standard ones created in option 1 of the same node.
    Once this is done, create strategy sequences for this, and assign to Order Type(s).
    If your users can maintain a basic investment profile when creating the Order Master Data, the developer can be directed to pick that data (aka fields) for the creation of the subasset number.
    Hope this helps.
    Cheers.

  • Automatic creation AUC sub assets at the time of settlement

    Hi,
    I have created the investment profile,AUC asset class,Source structuce(Hard,Pave and Soft) and cost element group(Hard,Pave and soft) . Then assign these three source structure to Investment profile.
    I created WBS element under project and released the WBS.
    After that I posted the values against the WBS different cost element . At the time of AUC seetlement thru CJ88.I am getting Three AUC asset with Sub number -0(1000-0,1001-0 and 1002-0) automaticaly. But Business is expecting to settle automatically(1000-0(Hard),1000-1(Pave),1000-2(Soft) respectively.
    Is there any way to settle AUC sub asset wise(Eg: 1000-0, 1000-1 ans 1000-2)automatically.
    Please share your suggestion on this.
    Appreciate your help!
    Regards,
    Prakash Reddy.

    Hello VIrendra,
    I am trying to settle WBS to AUC settlement thru CJ88. In this case We need to settle WBS to  AUC sub number wise 0,1 and 2 respectively based on the cost element. Is there any settings required to create AUC asset sub number wise creation?
    Thanks& Regards,
    Prakash Reddy.

  • Error when uploading Sub-asset numbers using LSMW

    Hi All,
    We have a requirement in which we need to first load Main asset numbers from Legacy system through LSMW and then in the next load the sub-assets for the Main Assets created.
    We are using Direct Input method(program RAALTD11) in LSMW for transaction code AS91 for loading Main Assets.
    And then using a file with similar structure, but with sub-asset numbers filled for creating Sub-assets using AS94 and Direct Input Method.
    While doing this, we are getting error:
    AU 256 Different asset class <asset-class> in sub-number.
    I have seen that there is a similar thread in SDN but the solution provided there is not useful to us, so I am raising again.
    I am not using Batch input method, as it is giving rise to many screen errors like "<Field> is not an input field".
    Please let me know how to get rid of this error.
    Thanks a lot .

    Hi,
    ensure that the sub-asset has the same asset class than the main asset, no matter which inout method you are using.
    best regards, Christian

  • Accounting entries process in Fixed Asset Module

    Dear all,
    I don't know Accounting entries process in Fixed Asset Module. I don't know how to post accounting entries and manage fixed assets
    Anyone can share me documents that is relevant to business transaction in  fixed asset module.
    My ID: [email protected]
    Thank in advance
    Minh
    Edited by: Tran Binh Minh on Apr 21, 2008 5:04 AM

    Hi,
    Good Morning,
    We are using Oracle R 12 Version 12.1.3
    and the issue i m facing Corporate Book as we have not yet started Tax Book
    The Addition posted period is closed, but I want to change life in Open Period Mar 12 ( latest open period).
    Yes Depreciation Run for March 12.
    Please help
    Regards
    Anant Danve
    9820077180

  • Memo Value for Main Asset and Sub Asset

    Dear Experts,
    I am having the requirement that, all the main asset should have the memo value Rs 1.
    For this I have specified the memo value in OAYI. But system is taking the memo value for Main asset as well as Sub asset.
    But we don't want to keep the memo value for sub asset.
    I hope, I am missing some settings. Could anyone please help me to solve this.
    Regards,
    Aswin

    Hi:
           You need to review your copy settings for sub assets for your relevant class's screen layout in  SPRO...Financial Accounting,,,,Asset Accounting....Master data....Define Screen Layout for Asset Master Data....Select the screen layout which has been assigned to your asset class in OAOA. You will not find any field for value copied. So it is not possible to avoid this happening becuase it is done a t CO code level.
    Regards

  • Scrap Asset and its sub assets in one transaction code

    Please suggest if it is possible to scrap an asset and all its sub assets in one transaction as opposed to scrapping them separately in ABAVN.
    regards
    Rekha

    Click on the button Multiple assets and fill in there the main asset and sub numbers. You have to fill them all in. There is no transaction that you can do this with filling in only the main-asset number

  • Asset and sub asset simoultaneous retirement

    can i config the system such a way that for specific assets...if i retire the main asset the sub assets are retired automatically....

    Hi,
    I don't think, this is possible. 
    The purpose of subnumber is to control subsequent acquisition to the main asset and/or represent complex fixed assets with their component parts.
    You can retire all the subnumbers with multiple option in ABAON but I don't think you can default retirement of all subnumbers when you retire main asset.
    Best Regards,
    Madhu

  • Delete Asset Master with Sub-Assets

    Hi Gurus,
    A client of mine has an Asset with out any values, but it has sub-assets under it with values and depreciation.
    Is it possible to delete the main asset and still have sub-assets? If not what is the way I can delete the main asset and still retain sub-assets?
    Thanks.
    regards,
    Raj

    Hi Gurus,
    Thanks for the replies.
    The user has in the mean time went ahead and deleted the main asset that did not have values, now we are able to only see the asset when we go to the report (asset balance report), but not able to see when we go to Display Asset (AS03).
    Is there any way we can undo this?
    Thanks.
    regards,
    Raj

  • Sub Asset No layout Change

    He Experts,
    My client req is --  when they  are trying to create sub-asset number for all Asset classes,
    depn.key, useful life & original depn. start date are not editable.
    Please advise me how to edit dep key and useful life in sub asset master.
    Thanks in advance.
    Regards,
    nagesh

    Hi,
    In transaction AO21 you can check the screen layout for mainnumbers and subnumbers. You have the options 'Required', 'Optional' and 'No'. In order for the field to have ready for input you need to choose at least 'Optional' and allow this for 'SbN' (subnumber).
    To check which screen layout is used in your asset class, you have to go to transaction OAYZ.
    Kind regards,
    Brigitte

  • Asset PO relating to sub assets

    Hi all sap guru's
    if one asset is there sub assets up to 100
    if i want raise the PO for 100 sub assets number it very difficult...
    user have to enter 100 sub assets  at item level,
    and also for each and every item one prinout will come....
    is the any solution to avaoid this ???

    Hi, another possibilty is to generate one line on the PO and have the split assignment field activated so that it is possible to enter 100 sub assets with a percentage setting of 1% each.  The main drawback is that the PO will then be set to have the goods receipt non valuated meaning that the asset values will only be posted at the time of invoice receipt.
    Hope this helps

  • APP-OFA-48392: Depreciation has been processed for this asset

    Hi,
    we are working in oracle applications 11i.
    In Oracle assets module, on the attempt from the user to modify the description of an asset item (from asset workbench -open) , when clicking the DONE button, the following error shows up:
    APP-OFA-48392: Depreciation has been processed for this asset for the current period in book...
    Please rollback depreciation or close the current period to perform this transaction
    Any ideas please...

    Hi
    If you have run depreciation for a particular period and thereafter try to make modification to any asset in the same period - the system will not allow you to do the same.
    If you have to make the changes than perform either of the following steps as mentioned below:
    1) rollback the depreciation for the current period by running the Rollback Depreciation program from the SRS Window
    OR
    2) Close the period by running the depreciation and thereafter make the changes to the asset in the next period.
    Without doing the above, the system will not allow you to make the changes to the asset.
    Hope this helps.
    Thanks
    Manish Jain.

  • Created  "sub asset" with reference to DEACTIVATED Master asset

    Hi experts
    We are facing something strange in our system (ECC6 SP22)
    We have some Master assets whitch are DEACTIVATED.
    We just note that we have possibility to create "SUB ASSETS" (I don't know how to say it in english) by referece to DEACTIVATED master assets.
    Is this normal?
    We would like to this prohibited. How can we do??
    Thank you in advance.
    Kind Regards

    Hi,
    Yes, it is a SAP standard behaviour, where you can create sub assets under deavtivated main assets also.
    If you want to stop this, you need to write an user exit for transaction AS11 with the help of your ABAPer.
    Regards,
    Srinu

  • Copying the same interval to Sub-asset master

    Hi Friends,
    My client is using 4.6c Version. The main asset master is having two time intervals in the time dependent data tab. With reference to that main asset, when we are creating the sub asset master all the time intervals are automatically copying to sub asset. But they don't want to copy all the intervals and want to have only latest interval to subasset.
    I have tried the same thing in ECC 6.0, it is copying only the latest interval. But it is not in 4.6C. Any suggestions please..
    Thanks & Regards
    shankar

    Have a look in the the field status settings from your asset, there you define these copy rules

  • AR process and Sub process documentation

    Hi,
    I am working on AR process and sub process …Can any one please mail me the   documentation / links on
    AR high-level process &and AR sub process like….
    Manual invoicing (where there is no SD invoice)
    Direct debit Process,
    Automatic matching of Incoming payments,
    Remittance advice/ payment advice,
    Debit Not process & credit note process
    Electronic Bank Statements
    User exits (on payment advice)
    Credit managment process
    Points will be awarded accordingly
    MY mail id is [email protected]
    Thanks
    Sireesha

    I would suggest reading the pdf files from Siemens.
    you can also find some files in www.easymarketplace.de
    but the best thing to do would be to practise a lot in a test system and get the overview from people who worked in AR for atleast 6 months....
    the pdf files, though they are comprehensive are very intricate and never explain the entire business scenario in simple words..