Process Order - Collective Close Technically

Hi Gurus!
I have two doubts:
1) I would like to know if there is any transaction code that I can close tecnically an process order. I know that this activity can be executed when we work with production order in the transaction COHV... But I didn't find any transaction for process order...
If yes, is there any techinical problem to do it? For example, It isn't good because we have wrongs in CO...
Could you help me with these issues?
Thanks in advance your atention!
Regards,
Valdevair

Hi!!
Thanks a lot!!
BR
Valdevair

Similar Messages

  • Close the Process Orders

    Hi All,
    Need to close the process orders which are in TECO ststus.
    There is no batch number assigned to the process order so no consumption of materials.
    The activities are in CRTD WRCE status which are not allowing the process order to close.
    Regards,
    Mallika

    Please follow the below path,
    Cor2 --> Process Orders --> Functions --> Restrict Processing --> Complete Technically.
    Once the Order are in TECO you cant do the change in its activity.

  • How to close old process orders dated 2006?

    I have a open process order dated back to 2006. There is a negative balance of -$100 on this order.
    Now in 2010 i want to close this order. The status of this order is TECO. However when i want to close this order, the system says i need to settle the negative balance first before doing so.
    Hence when i run the settlement to material the system says the process order is not technically completed yet because i have not done the final delivery yet.
    When i do final delivery using a current date in 2010, the system said it could not determine the object currency for the activity types used in the order since the cost center tied to the activity type has a validity date of up to 31/12/2006 only.
    In this case i am stuck one after another situations. How can i close this order without going through all the above conditions?

    Hi,
    One alternative is to change the Settlement profile setting (attached to Order type) in OKO7 to 'Can be Settled' from 'To be settled in Full' briefly, which allows you to close the Order even with some balance on it. Revert back the setting once you are done.
    Hope this helps.

  • BAPI for Process order change

    Hi,
    Can any buddy tell me the Bapi used for Process order change
    with following scenarios:
    Quantity change
    Resource change
    Rescheduling
    Control key change
    RM Change
    Recipe change
    TECO
    REVOKE
    Material shortage check
    Best Regards,
    Sheetal.

    Hi,
    BAPI_PROCORD_CREATE for process order create
    BAPI_PROCORD_CHANGE - Change Process Order
    BAPI_PROCORD_CLOSE - Close Process Order
    BAPI_PROCORDCONF_CANCEL for Cancel Process Order
    Confirmation.
    BAPI_PROCORD_COMPLETE_TECH - Complete Technically
    BAPI_PROCORD_RELEASE - Release Process order
    BAPI_PROCORD_SET_DELETION_FLAG - Deletion Flag
    BAPI_PROCORD_REVOKEUSERSTATUS - Cancel User Status
    BAPI_PROCORD_SCHEDULE - Carry Out Scheduling
    pls refer below link
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/200dd1cc-589e-2910-98a9-bb2c48b78dfa
    http://help.sap.com/saphelp_nw04/helpdata/en/e0/9eb2370f9cbe68e10000009b38f8cf/frameset.htm
    Regards,
    Sankaran

  • Process order problem in COR2 - Urgent Please

    hi i have a problem in COR2.
    After creating the process order i TECO Technically complete the same,
    and when i save the process order the system just hangs.
    When i debugged the code i found that issue is inside the functional module CO_ZV_ORDER_POST - Create/change end routine order.
    It does not do the commit work properly. this is in PRD so please help me to resolve this
    I checked for other system and the process order gets saved.
    What should i do
    please help

    just  compare the  function  module  in  both  PRD & DEV  so that  see the difference in the code level  or else  in the debug  mode  upto the  hanging  code level  ....
    i think it is because of the performance  issue  ....  so  need to  be   created the index  of the  table which  it gets  updated  .....
    becuase  as your FM is  for create/chande  .... so it  will be an  big  table  .... so see it  and   do the performace trace  and  create the  index ..
    ST05 ,SCI  , SM30    .... These are  some of the  tracscation code for   Code Insecptor , performance trace & SQL trace , Runtime Analysis..
    seee if the code is  same  in both  the system   ... then it is confirmed  as   performance  issue  ....
    if the code is  different   then it is  patch level  issue ...  tell to  basis  to check the  patch level  of that  both system  and apply it.
    reward  points  if it is usefull ...
    Girish

  • Problem in Process Order - Urgent

    hi i have a problem in COR2.
    After creating the process order i TECO Technically complete the same,
    and when i save the process order the system just hangs.
    When i debugged the code i found that issue is inside the functional module CO_ZV_ORDER_POST - Create/change end routine order.
    It does not do the commit work properly. this is in PRD so please help me to resolve this
    I checked for other system and the process order gets saved.
    What should i do
    please help

    Please check the OSS note - 1041204 - Controlling COMMIT WORK in production order BAPIs
    Hope this helps you.

  • Deletion Flag Process Order

    Hi Experts,
    Is there any transaction for Activating Deletion Flag for a pool of Process Orders collectively? Many thanks!
    Kumar

    Another alternative is to run the transaction COA5 (Archive Administration Preprocessing).
    This will allow you to set the deletion flag en-masse.
    The selection of the pool of orders is made in the selection variant.
    Requirements are that the process orders are settled, associated PI sheets, inspection lots and any linked purchase orders are complete.
    It has a good log on what process orders could not have the deletion flag set and why.
    Chris

  • COHVPI-closing process order error

    Dear all,
    Some of the process order is in TECO status
    I need to close the order.
    While doing mass process order to close the order by using COHVPI tcode,i got error for all material
    Inspection lot xxxxxx for the order xxxxxx does not have necessary status.
    By using qa32 i checked,for that lots status is released.
    So i tried to make results entries and usage decision,But no characteristics was maintained in results,so we are not able to do usage decision.
    The error message which i got for the materials ,inspection type was 03.
    So kindly let me know how to process it.
    Regards
    Rajasekaran

    To process them cleanly, you should have at least one characteristic result recorded.  Why have you created an 03 lot with no inspection characteristics to begin with?
    What is the error message when you do a UD?  You should be able to do a UD on those lots where the order has a status of TECO.
    Craig

  • Goods Issue- Process Order Confirmation

    Hi,
    During Process order confirmation, in Goods Movement tab the BOM components with qty are displayed. But some components OTHER than BOM items ISSUED for the process order is not displayed in the goods movement tab. Why?
    Is there any additional configuation to be done?
    Thanks....
    JK
    Edited by: J K on Apr 15, 2008 6:04 AM

    Hi
    As said by Mr sateesh,
    If u r doing confirmation phase/operation wise(COR6), then the material assign to phase/operation is only seen according to phase/operation wise.so have to check in which phase u have confirm the component quanity.
                    or
    If u confirm the process order collectively(CORK), then their must missing in OPK4 (confirmation Parameter) of All component tick at Goods Movement.
    Kindly check the same & coem back if their is any other issue
    Parminder

  • PP - PI Process order - Technical complete problem

    Hi Gurus,
    I have created process order and generate Cont.recepie. Then I tecnical complete my PI sheet after report data. when i set technical complete in my process order. system says "It cannot be technical completed because status "CRCR" Contrl recepie created". How i can set status technical complete to my proc.order.
    kindly help
    Majid

    Hi,
    Inorder to TECO or close your order first you have to close the Control Recipe. To do so follow the steps:
    1. TCode: CO57
         Proc.Message Cat: PI_CRST (Message on control recipe status)
         Process Order Number
         Control Recipe Number
         Control Recipe Status: 00005 or 00004 or 00007
         After these entries save the Process Message.
    2. TCode C054
        Here send the Process message that was created in the above step.
    If the message is successful, the status in the order changes from CRCR to either CRAB (if control recipe discarded), CRFI.
    Then you can close your order.
    Regards
    Vinod

  • How to collectively close internal orders?

    Hi,
    Need your advise on how to collectively close internal orders. I'm trying to use tcode KOK4 but I can't seem to get the Close function in the function selection list. Appreciate your advise on the steps/tcodes to use to collectively process internal orders. Also, what is the proper order of closing internal orders? I need to run CO88 first before setting the internal order to status Close?
    Thanks!

    Hi,
    There are some pre conditons for closing the order like the order balance should be zero, there should not be any purchase order open against the order etc. So, please run the settlment to close the order. If there is any Purchase order open, then that also should be closed.
    Please check the status management configuration in SPRO>Controlling>Internal Orders, for getting the complete function in T.Code KOK4
    Regards,
    Rijo Paul

  • Process order CLOSE:Message no. BS013

    Hi Gurus,
    I am trying to CLOSE some Process orders which are TECO status,(All are TECO status, and Settled) but when I execute those it gives error messages, and the Log says,
    System status CRTD is active (ACT 112033 0011 )
    Message no. BS013
    Diagnosis
    Object ACT 112033 0011 has system status CRTD (Created).  According to this status, transaction 'Complete' is not allowed.
    Procedure
    You can only carry out the requested function if this is allowed according to the status of the object.
    your time greatly appreciated,
    Paartha

    Hi Partha,
    Our internal systems behave the same. The reason is that the activity
    cannot be set to TECO unless it has been Released. You can see for any
    activity that setting TECO is not allowed via Edit -> Status -> Complete
    Technically unless the activity is at least at status REL. Therefore,
    when you try to set TECO for the project you get BS013 because status
    CRTD is active for the network activity.
    The system shows TECO as an allowed option for the project as it is
    allowed but only as long as all pre-requisites are met. The alternative
    would be for the system to do the pre-requisite checks before deciding
    whether TECO should be shown as allowed or not. This would not be good
    from a performance viewpoint.
    Regards,
    Abhisek

  • Process Order Close with Inspection Lots

    At month end we need to close process orders that have not had their usage decison made, generally the inprocess inspection UD.  Is there any way to close these POs without having to enter a usage decision?

    > Hi
    > You can activate the inspection completed status
    > activated for the inspection lots with out making
    > UD.
    > Regards'
    > YMREDDY
    Your suggested solution to being able to flag the inprocess inspection lot as being completed without making a UD, to allow the process order to be closed, sounded very, very interesting, but we are not familiar with the file/record/configuration parameter you noted.  Is there any way that you might be able to clarify your answer, so that we can have our technical team figure out how to implement that change?
    Thank you very much.....this has had us stymied since we went live.

  • Cannot Close Process Order

    Dear All,
    We have an external phase for our process order. As the result of which we have a purchase requisition associated with that phase which is later converted into purchase order. After we complete the whole process cycle and try to close the process order we get a error messege number" C0434" which says purchase order stil exists.
    What does that mean?.
    Where can I find this messege on SAP portal?.
    Can someone please help me with this?
    Thanks,
    Hanish

    Hi Hanish,
    Have you checked the PO?? Is it still open??
    U can search for messages in the SAP service market place for any relevant notes if you have an S Id.
    For your issue you check the notes
    650829, 773397
    a brief of the note is given below.
    A purchase order is regarded as open if the final invoice indicator is not set. The final invoice indicator is also expected if it is a purchase order without invoice receipt (for example a stock transport order).
    Regards
    MIthun

  • Mass Close of Process Orders

    Is there any way to close multiple process orders at the same time?  I'm using COHVPI for doing mass TECO but it doesn't have a close option.
    Thanks,
    Rosalind

    Rosalind,
    Use transaction CORM for your purpose.
    Regards,
    Prasobh