Process Order Confirmation COR6N - By using Shift Management Functionality

Hi,
I want to confirm Operations/Phases by using T.Code COR6N.
Here i want to identify which Shift i have done confirmation by using shift management functionality.
It can be done for CORK. While doing Cofirmation for Order by using CORK, we can use this functionality.
The same i want to use for COR6N.
I have done as per following link
https://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/c0fa9a04-376a-2c10-c396-86d32ac80614
Is there any option to use this functionality for COR6N ?
Pl suggest
Regards
Nag
Edited by: nag1975 on Mar 29, 2010 3:06 PM

Hi Srinath,
Go to T-code CO86 directly or go to SPRO> Production planning for process industries>process order--> operation>>confirmation and then hide the field for scrap by clicking the radio button. I think this should serve your purpose.
Please let me know if you have any issues.
Regards,
Abhijeet

Similar Messages

  • Problem during Process Order Confirmation - COR6N

    Dear All,
    We are into process industries
    Till now we are creating different BOM for each section and different process orders for each BOM.
    For example Pulverize, Acid MIXING, Continuous Rotery, Blending and Packng.
    Now we have created new BOM for FG - showing all input/output of  RM, SFGs.  In Recipe, define operation for each section. and assign operation to material.  I have attached screenshot of Recipe Operation.
    During process order confirmation, system shows movement type of all material perfectly during each phase. But during confirmation of last phase system does not show 101 movemet of FGs.
    I have checked in Recipe, control key is ok i.e. Automatic GR,  in OPK4 setup is also correct.
    We have created new BOM and Recipe. There is no change in other configuration parameter.
    Thanks and Regards,
    Nirav

    Hi Nirav
    The automatic goods receipt is defined by the operation/phase control key.
    Control key PI03 has the automatic goods receipt setting by defaul.
    Analyzing the screenshot I could observe that this control key is assigned to all the opration/phases, however, it should only be assigned to the last operation/phase, where the goods receipt will actually take place.
    For all the previous operations/phases you should use a different control key, without automatic goods receipt, such as PI01.
    BR
    Caetano

  • BAPI For Process Order Confirmation

    Hi,
    For Process Order Confirmation we are using the following tcode. COR6N. in the t-code we are include a new field (Shift Field) with help of CONFPP07. and we made the field as mandatory also. in cor6n it is working fine.
    now we are using the bapi for same Process Order Confirmation. here the new field is not available. we want to include the new  ( Shift ) Field also. we are using the following
    BAPI Fm: BAPI_PROCORDCONF_CREATE_TT .
    Regards
    Sathis

    BAPI_PRODORDCONF_CREATE_TT to confirm a production Order
    Erwan

  • ABAP Programming Error when saving the Process Order confirmation in COR6N

    Hello,
    We have an issue related to Process Order confirmation using Tcode COR6N. When we enter all the inputs to confirm( Activity, yield and phase) and click on save it gives ABAP Programming Error (Exception condition "SEQ_NOT_FOUND" raised).
    Any inputs in this regard, would be appreciated.

    Hello
    I can observe that you have implemented the report ZOPSECRE and that an inconsistency was found.
    This repor corrects inconsistent orders which do not have an operation or a sequence, or the two of them.
    The report checks whether there is at least one operation or one sequence and creates both including status objects.
    Therefore, you need to have the default valus for the operation generation defined on OPJG for this order type/plant.
    BR
    Caetano

  • Problem with creating Process order confirmation using BAPI

    Hello,
    While creating Process Order confirmation using BAPI_PROCORDCONF_CREATE_TT, material document is getting created. But a line item is inserted in the table AFRU without material document number. When it is created manually using the transaction COR6, the table is getting updated with material doc in the line item. Can anyone let me know what other attributes to be passed in order the update the same?
    Thanks in Advance.
    Regards, Senthil G.

    Hello , I am working with the same Bapi, can you please send me the code to fill the parameters, if I find the same error like you, I will send you the solution if I correct that.
    Thanks for your help.
    [email protected]
    Guatemala, Cempro ADATSA

  • In process order confirmation screen there should be 2 rows for down time.

    hi,
    We are using cor6n for process order confirmation, where we can put down time  with confirmation text at once,
    if there is two different down time, then user has to again  run cor6n with 0 yield  for put another down time, which gets more time.
    for this reason i have customised single screen entry profile by mentioning two down time & confirmation rows in screen.
    when i going for confirmation i put two different down time  after goods movemnt order get confirmed & settled.
    but when i see report in COOISPI  there is only one down time against order.
    system only considers last down time.
    hows the system consider down time?
    thanks in advance.
    regards
    sanjay.

    Hi,
    The report COOISPI considers only one line of the down time, it is not considering the 2nd row of the down time. You need to change the COOISPI program to read the 2 lines of the down time. You need to change the standard program to read the 2 down time lines.
    Thanks & Regards,
    V. Suresh

  • Create process order confirmation

    Hello,
    I use the Bapi 'BAPI_PROCORDCONF_CREATE_TT' to create a confirmation in our Z program to replace 'COR6N'.
    The only problem I meet is that it makes a material document for the good movements but don't write it in the table AFRU (field WABLNR).
    Do I miss something in the BAPI??
    I run the BAPI like that:
      CALL FUNCTION 'BAPI_PROCORDCONF_CREATE_TT'
        IMPORTING
          return                   = lwa_return
        TABLES
          timetickets              = gt_timetickets
          goodsmovements           = gt_goodsmovements
          detail_return            = lt_detail_return
    The tables gt_timetickets & gt_goodsmovements are filled with relevant values.
    Could anyone help me to know what make the doc no. to be written in AFRU?!!!
    Thanks in advance,
    Fariba

    Hi Fariba,
    I am facing the same kind of issue that you faced long back. If you have resolved this issue, can you help me by replying back to the thread Problem with creating Process order confirmation using BAPI
    Thanks in Advance.
    Regards, Senthil G.

  • Restriction during process order confirmation

    Hi,
    I want one validation during process order confirmation (mile stone) through t code COR6N  if resource capacity & shift intervals not maintained ( t code CRC2) then process order should not confirmed &  there should be error message. Plz advice how it is possible through customization.
    regards,
    sps.

    Dear shukla,
    Check with this User Exit,
    CONFPI02                                Process order confirmation: Customer spec. input checks 1
    CONFPI03                                Process order conf.: Cust. spec. check after op. selection
    CONFPI04                                Process order conf.: Customer specific input checks 2
    CONFPI05                                Process order conf.: Cust. spec. enhancements when saving
    If the above is not working then check with this BADI
    WORKORDER_CONFIRM at the time of saving,
    Regards
    S Mangalraj

  • Update Process Order Confirmations Back to SAP ECC

    Hi,
    Is there a document or step by step guide which explains how i can update  SAP EARP with process order confirmations from my shopfloor?  Below is the scenario i am looking for help in
    1. There is a SQL server table where the SHOP floor update the quantity manufactured against a Process order.
    2. I need to pick up that data from the SQL server table and update the ERP against that Process order.
    Can any one explain how this can be achieved.
    I checked the sample's and the templates in SDN but none of them actually show how to update any ERP?
    Please advice!!.
    Regards
    Suraj

    Check this one
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/60ac6bb8-a684-2b10-208d-b90883004a5e
    https://www.sdn.sap.com/irj/scn/downloads?rid=/library/uuid/204a13d0-399d-2b10-ec84-9c254cd7efd4
    You use this component to enable the shop floor operators to record their production order and process order confirmations using a touch screen user interface. In SAP ERP Central Component (SAP ECC) operators must complete many steps to confirm orders. Instead, you can use this interface, on a touch screen to enter the production performance easily and effectively. You can also use this component to obtain operators' work lists and information on their current activities.
    Regards
    Ram Upadhyay

  • Process order confirmation error in COR6

    Hi Gurus,
    I am working as sap manual tester and facing below issue in Process order confirmation in t-code COR6.
    Batch 456 for component 350515 does not satisfy BOM requirements
    Message no. Z_MFG017
    Need ur help.
    Regards,
    Imran
    Edited by: imran.shek38 on Jan 25, 2011 7:16 AM

    Hi,
    Please check whether the Batch-Management checkbox is maintained for the component in the Material Master (MM02).
    Also, check the Transaction MSC2N for this component and activate the checkbox for batch-managed item in the BOM.
    Hope it helps.
    Regards,
    Kaushik

  • Need a BAPI/FM for process Order Confirmation

    Hi guys,
    I need a bapi or Fm for process Order confirmation.
    thnx in advance

    Checck
    BAPI_PRODORDCONF_CREATE_ACT
    BAPI_PRODORDCONF_CREATE_HDR
    BAPI_PRODORDCONF_CREATE_TE
    BAPI_PRODORDCONF_CREATE_TT
    Better read the documentation of each BAPi using the tcode BAPI and proceed.
    I feel BAPI_PRODORDCONF_CREATE_HDR would do your purpose.
    Documentaion:
    <b>
    You can use this method to enter order confirmations for production orders.
    You can also transfer good movements, that are posted together with a confirmation. If no goods movements have been entered for a confirmation, they are determined using the standard logic for backflushing and automatic goods receipt for confirmations. </b>

  • Process order confirmation reversal

    HI friends,
    I am cancelling a process order confirmation using T-code CORS. The confirmation cancellation is happening, but the goods movements are not reversed. Help in resolving will be much appreciated.
    Thanks in advance.
    Warm regards
    Vivek

    Hi All,
    Sorry for the delay in response and thanks for your suggestions.
    The backflushing is activated. I checked in COGI transaction for the concerned order. I got several entries with different error text. The error text is as follows
    "You have no authorization for this transaction with movement type 102"
    "You have no authorization for this transaction in plant XXXX"
    "Deficit of SL Unrestricted-use 6,957 TO : 1030604 XXXX PL01"
    Please let me know how to resolve these errors.
    Warm Regards
    Vivek

  • Set loss quantity to a fixed percentage in Process Order Confirmation - C0R6N

    Hi Experts,
    How it is fixed the loss qty percentage at the time of process order confirmation.
    I want to set the loss quantity to a certain percentage when compared to the Total Process order quantity.
    For Example:
    If the Total processed quantity = 100
                            Yield Quantity = 20.
                             Loss              = 80.
    This kind of scenario should not happen, since Loss quantity is very much higher that the yield quantity.  I want to set the loss quantity  to a particular percentage ( say 20-30 %) of the total processed quantity so that the yield quantity will be higher than the loss quantity by a substantial amount. Are there any possibilities of doing this through configuration. If not what are the other options?
    NB: Scrap quantity is not maintained at the time of  process order confirmation.
    Regards,
    Umapathy.

    Hi Umapathy,
    Yield and Scrap are user entry fields where you can have restriction on entered qty by changing  under delivery and over delivery to error through OPK4 config as shown below. Agree that any qty can be entered in any field (Yield or Scrap)
    OR
    You can define the operation scrap. Read the below doc for more details.
    http://scn.sap.com/docs/DOC-52834
    OR
    Another option is to use exit and write your logic based on input yield and loss.
    Thanks & Regards,
    Ramagiri

  • Costing data from Tables of Process Order Confirmation.

    Dear Friends,
    In which table is the Costing relevent data for process order confirmation stored.
    We are developing a report for which we require  material specific-
    Target quantity / Actual quantity
    Target costs / Actual costs
    Thanks in advance.
    Regards,
    Vikrant Sood

    Hi,
    Using the Table : AUFM you can get the data.
    VVR

  • Sample Preshippment information in PI Sheet or Process order confirmation

    Dear Gurus,
    We are using the strategy 40. We need some information on sample sending procedure like preshipment or coshipment and quantity of delivery to the process order PI sheet to identify the production team to keep the sample ready before confirmation or receipt of the process orders.
    It is sepcific to some customer or material.
    Could you please help me how to configure / flow information from sales order or Material to PI sheet or process order confirmation.
    THanks in Advance
    Srini

    Hi,
    Process Massage will generate only after Completing the PI sheet.So after maintaining the PI sheet you have to press Complete button then only system will generate Process Massage regarding completion of PI sheet.
    But if you leave the PI sheet only with Save then it means still there are some entries are left or may be change.So in this case system will not generate process massage.
    Now first complete the PI sheet then check in CO54 with correct date , time and plant selection.Send it from here and then check in process order.
    Regards,
    Dhaval