When a confirmation is of the process order executed the open reservations for this order should be closed but it will only do so for a limited number of items.
When looking at process order xxxxxx it will show a final issue for materials say A, B and C but it will leave all the other items open and will therefore generate requirements for these items in MRP.
How to solve this?

Dear Sosal,
use Mr. Bramhankar's proposal, if u want system to propose by default in confirmation screen. if u set this for partial confirmation also it will be final and confirmation and reservation gets cleared.
one more option is while confirming the order either in CORK/COR6N select manully automatic final confirmation and clear reservations. ur issue will be resolved
sree

Similar Messages

  • Goods Issue- Process Order Confirmation

    Hi,
    During Process order confirmation, in Goods Movement tab the BOM components with qty are displayed. But some components OTHER than BOM items ISSUED for the process order is not displayed in the goods movement tab. Why?
    Is there any additional configuation to be done?
    Thanks....
    JK
    Edited by: J K on Apr 15, 2008 6:04 AM

    Hi
    As said by Mr sateesh,
    If u r doing confirmation phase/operation wise(COR6), then the material assign to phase/operation is only seen according to phase/operation wise.so have to check in which phase u have confirm the component quanity.
                    or
    If u confirm the process order collectively(CORK), then their must missing in OPK4 (confirmation Parameter) of All component tick at Goods Movement.
    Kindly check the same & coem back if their is any other issue
    Parminder

  • ABAP Programming Error when saving the Process Order confirmation in COR6N

    Hello,
    We have an issue related to Process Order confirmation using Tcode COR6N. When we enter all the inputs to confirm( Activity, yield and phase) and click on save it gives ABAP Programming Error (Exception condition "SEQ_NOT_FOUND" raised).
    Any inputs in this regard, would be appreciated.

    Hello
    I can observe that you have implemented the report ZOPSECRE and that an inconsistency was found.
    This repor corrects inconsistent orders which do not have an operation or a sequence, or the two of them.
    The report checks whether there is at least one operation or one sequence and creates both including status objects.
    Therefore, you need to have the default valus for the operation generation defined on OPJG for this order type/plant.
    BR
    Caetano

  • Product Costing - Process Order Confirmation

    Dear Experts,
    We are facing a situation with our Product Costing Scenario :
    Under SFG Process Order Confirmation, there are Ten Phases to finally confirm the order. First Phase is for Raw Material Issuance. From Second Phase to Ninth Phase are relevant to Activity Types. Tenth Phase which is final phase, in this point Goods Receipt posting is generated.
    At first phase, system posts Raw Materials Goods Issue (Movt Type 261) to Process Order:
    Entry : RM (Cr), Consumption (Dr).
    Client needs the system to post one more entry at the same time by : WIP (Dr), Inv Change (Cr).
    Reason:
    According to client, they have made consumption entry in finance but what if all raw materials are not consumed as yet and factory comes under fire, then how can they claim insurance on those Raw Materials which are not consumed and are still in the IN PROCESSING Stage?
    My Answer was:
    - They can find all material costs in Process Order as Debit Item.
    - They can also calculate WIP but cannot post WIP in Finance unless the order is settled.
    Ultimately, as per my knowledge client cannot check the unprocessed Raw Materials report in FI but they can check in CO. And this is the point of reservation from client.
    They need an entry in Finance for WIP to claim insurance in case of fire and therefore they need a posting of  WIP entry immediately after Goods Issue of Raw Materials to Order.
    Can anyone please guide me further regarding this scenario and if any one can suggest any work around then it would be highly appreciated!
    Regards,
    Zain Bashir 

    Hi Zain
    This is a very unusual question
    Buddy, there is something in accounting called as "Going Concern Concept" which we all were taught in our accounting days.. That means when you do business, do it with a mindset that you are goinig to do it for long / for ever.. Accidents dont happen every day and you cant build a system around such things
    Assume there is a fire (God forbid).. After the accident, you wont even know how much was  lying there unconsumed which got gutted in the fire..
    And insurances not just covers the stock lying consumed, but also stock manufactured and stock in the process of manufacturing (WIP)
    And most importantly, dont expect SAP to throw up a figure at the click of a button.. Does your client really think that they will simply submit the report generated from SAP as-is to Insurance people?? SAP is just a technology enablement, which requires human intervention at various places
    My opinion - Dont build system for such requirements
    Br. Ajay M

  • Process order confirmation error in COR6

    Hi Gurus,
    I am working as sap manual tester and facing below issue in Process order confirmation in t-code COR6.
    Batch 456 for component 350515 does not satisfy BOM requirements
    Message no. Z_MFG017
    Need ur help.
    Regards,
    Imran
    Edited by: imran.shek38 on Jan 25, 2011 7:16 AM

    Hi,
    Please check whether the Batch-Management checkbox is maintained for the component in the Material Master (MM02).
    Also, check the Transaction MSC2N for this component and activate the checkbox for batch-managed item in the BOM.
    Hope it helps.
    Regards,
    Kaushik

  • Create process order confirmation

    Hello,
    I use the Bapi 'BAPI_PROCORDCONF_CREATE_TT' to create a confirmation in our Z program to replace 'COR6N'.
    The only problem I meet is that it makes a material document for the good movements but don't write it in the table AFRU (field WABLNR).
    Do I miss something in the BAPI??
    I run the BAPI like that:
      CALL FUNCTION 'BAPI_PROCORDCONF_CREATE_TT'
        IMPORTING
          return                   = lwa_return
        TABLES
          timetickets              = gt_timetickets
          goodsmovements           = gt_goodsmovements
          detail_return            = lt_detail_return
    The tables gt_timetickets & gt_goodsmovements are filled with relevant values.
    Could anyone help me to know what make the doc no. to be written in AFRU?!!!
    Thanks in advance,
    Fariba

    Hi Fariba,
    I am facing the same kind of issue that you faced long back. If you have resolved this issue, can you help me by replying back to the thread Problem with creating Process order confirmation using BAPI
    Thanks in Advance.
    Regards, Senthil G.

  • PROCESS ORDER CONFIRM DURING UD

    Hello Experts:
    Here's my question concerning a customization in QM issuing UD.
    Std. results recording has been completed and valuated:
    UD is customized to require user to confirm all operations including QM operations have been Process Order Confirmed. This is o4  inprocess manufacturing.
    When attempting to enter UD, error pops up indicating QM Operation XXXX  has not been confirmed, do so to complete UD.
    Please explain the steps to execute P.Order confirmation via the COR transactions.
    Appreciate.
    Verroz

    Go to CO11N
    Enter process order and Operation xxxx in respected field and save the transaction. Do for all unconfirmed operation or for which you getting error message.
    You will be able to UD.

  • Ristrict Cancelling Process Order Confirmation (CORS) after FI MM period cl

    Showing current date as posting date after Cancelling Process Order Confirm:
    Issue with FICO and PP :-, after settlement (ko88) and all period end closing, system still allowed doing Cancelling Process Order Confirmation (CORS) and Showing current data as posting data
    For example:
    My order created on 30th September 2010 and order confirmed on the same day ie my posted date (30th September 2010)
    I have done order reversal on 3rd October 2010 and posting date should be 3rd October 2010 but system showing current data as posting data. Can you please guide me why this unusual behavior happening

    Hi Arun
    Is this  congif change will help me
              1)In BS22 first search for TECO.
               2)Double Click on TECO.
               3)New entry.
               4)Now search FI posting.
               5)Select status as Prohibited
    My Requirement : Ristrict Cancelling Process Order Confirmation (CORS) after FI, MM period closed, and Materail Ledger done
    I want to ristrict the (CORS) reversal of Process Order Confirmation after FI MM ML closed
    right now as per standard its giving warning masage as " Posting with carent date YES or NO, if you say YES then system doing CORS on system carent date, i want to restrict it
    Is above steps you refered will help me
    please confirm
    Regards
    MKbinnal

  • Process Order/Confirmations/

    Hi,
    I am from BI team and did have little(no) knowledge on PP. However I have to Pull Goods produced from R/3 on a daily level for each plant.
    Can any one give some hints??
    I was observing few tables like AUFK and AFRU-LMNGA fields and got confused which table can help me.
    also i would lile to understand the relation between,
    Planned Order, Process Order, Confirmations and PLANT...
    Can any one help me??
    regards,
    Hari

    Dear Srinivas,
    Thank you for looking into this.
    Objective:
    To bring all the ACTUAL quantities produced on daily basis for each Plant from R3
    to BW.
    In my AFKO table I found entries as below
    Order  - Qty-                   PLANT
    123  -   15,000 Tons  -     US01
    In AFKU
    Confirm-item- Order-Yield- Quantity-  POsting date
    345       -          10     -123-     15,000 -           09/09/2006 -       US01
    346        -         20    - 123 -    15,000      -      09/09/2006   -     US01
    354  -               10   -  123  -   15,000     -       09/09/2006    -    US01
    354   -              20  -   123   -  15,000    -        09/09/2006     -   US01
    Can I assume that on 09/09/2006 total qty produces as 60,000 Tons?
    thanks for u r time..
    regards,
    Hari

  • Process order confirmation without 101mvt type

    our client is  a process industry.client need during process order confirmation Background 101 not happen.
    Step : 1 Process order create
    Step : 2 Goods issue The material -261
    Step:  3 Process order confirmation   (No 101)
    Step:  4 Goods Receive (MIGO) 101 happen 
    Following Steps Process only,
    cork-only activity confirmation only,after Activity  confirm GR will Happen , how to configure in the system,any user exit or sap note there in the sense tell me?
    Thanks For Advance

    Hi Thiyaharaajan,
    For Goods issue i believe you are using MB1A/MIGO. You also use backflush to automatically issue the material during confirmation.. For this maintain Backflush - 1 in material master MRP 2 view.
    Also during confirmation for doing Auto GR (101 movement type) you need to assign the control key ticked with Auto Goods Receipt for Last operation/phase of Master Recipe.
    Thanks & Regards,
    Ramagiri

  • How to block order confirmation, before issue of raw materials?

    Dear Frndz,
    My client would like to block order confirmation, before issue of raw materials.Also, they do not want to use backflush concept.Pls help me out with the step by step process.
    Regards,
    Srini

    Srinivasan,
    You can think of using available user exits which are listed below,
    CONFPP01            PP order conf.: Determine customer specific default values
    CONFPP02            PP order conf.: Customer specific input checks 1
    CONFPP03            PP order conf.: Cust. specific check after op. selection
    CONFPP04            PP order conf.: Customer specific input checks 2
    CONFPP05            PP order conf.: Customer specific enhancements when saving
    CONFPP06            PP Order Confirmations: Actual Data Transfer
    CONFPP07            Single Screen Entry: Inclusion of User-Defined Subscreens
    Please take help from your ABAP consultant.
    Hope this helps you.
    SmanS

  • BAPI For Process Order Confirmation

    Hi,
    For Process Order Confirmation we are using the following tcode. COR6N. in the t-code we are include a new field (Shift Field) with help of CONFPP07. and we made the field as mandatory also. in cor6n it is working fine.
    now we are using the bapi for same Process Order Confirmation. here the new field is not available. we want to include the new  ( Shift ) Field also. we are using the following
    BAPI Fm: BAPI_PROCORDCONF_CREATE_TT .
    Regards
    Sathis

    BAPI_PRODORDCONF_CREATE_TT to confirm a production Order
    Erwan

  • Problem with creating Process order confirmation using BAPI

    Hello,
    While creating Process Order confirmation using BAPI_PROCORDCONF_CREATE_TT, material document is getting created. But a line item is inserted in the table AFRU without material document number. When it is created manually using the transaction COR6, the table is getting updated with material doc in the line item. Can anyone let me know what other attributes to be passed in order the update the same?
    Thanks in Advance.
    Regards, Senthil G.

    Hello , I am working with the same Bapi, can you please send me the code to fill the parameters, if I find the same error like you, I will send you the solution if I correct that.
    Thanks for your help.
    [email protected]
    Guatemala, Cempro ADATSA

  • Problem during Process Order Confirmation - COR6N

    Dear All,
    We are into process industries
    Till now we are creating different BOM for each section and different process orders for each BOM.
    For example Pulverize, Acid MIXING, Continuous Rotery, Blending and Packng.
    Now we have created new BOM for FG - showing all input/output of  RM, SFGs.  In Recipe, define operation for each section. and assign operation to material.  I have attached screenshot of Recipe Operation.
    During process order confirmation, system shows movement type of all material perfectly during each phase. But during confirmation of last phase system does not show 101 movemet of FGs.
    I have checked in Recipe, control key is ok i.e. Automatic GR,  in OPK4 setup is also correct.
    We have created new BOM and Recipe. There is no change in other configuration parameter.
    Thanks and Regards,
    Nirav

    Hi Nirav
    The automatic goods receipt is defined by the operation/phase control key.
    Control key PI03 has the automatic goods receipt setting by defaul.
    Analyzing the screenshot I could observe that this control key is assigned to all the opration/phases, however, it should only be assigned to the last operation/phase, where the goods receipt will actually take place.
    For all the previous operations/phases you should use a different control key, without automatic goods receipt, such as PI01.
    BR
    Caetano

  • Update Process Order Confirmations Back to SAP ECC

    Hi,
    Is there a document or step by step guide which explains how i can update  SAP EARP with process order confirmations from my shopfloor?  Below is the scenario i am looking for help in
    1. There is a SQL server table where the SHOP floor update the quantity manufactured against a Process order.
    2. I need to pick up that data from the SQL server table and update the ERP against that Process order.
    Can any one explain how this can be achieved.
    I checked the sample's and the templates in SDN but none of them actually show how to update any ERP?
    Please advice!!.
    Regards
    Suraj

    Check this one
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/60ac6bb8-a684-2b10-208d-b90883004a5e
    https://www.sdn.sap.com/irj/scn/downloads?rid=/library/uuid/204a13d0-399d-2b10-ec84-9c254cd7efd4
    You use this component to enable the shop floor operators to record their production order and process order confirmations using a touch screen user interface. In SAP ERP Central Component (SAP ECC) operators must complete many steps to confirm orders. Instead, you can use this interface, on a touch screen to enter the production performance easily and effectively. You can also use this component to obtain operators' work lists and information on their current activities.
    Regards
    Ram Upadhyay

Maybe you are looking for

  • Time Machine and Seagate External hard drive

    I connected my Seagate External Hard Drive (300GB) to my MacBook pro for the first time. I got a prompt asking if I would like to use this as a backup disk with Time Machine. Absent-mindedly, I hit "NO". Now the Hard drive is not showing up in the li

  • Get managed metadata column name in CAML Query

    Hi All, In my pages library, I have a managed metadatda column named "MyProduct". When I try to retrieve this in my Caml query, the column data is displayed in a different format like : System.Collections.Generic.Dictionary`2[System.String,System.Obj

  • Setup solution monitoring

    Hi all I am hvaing a starnge issue while doing the sytem monitoring set up. I have included the system in smsy and assigned the logical component as well.These logical components are assigned to the solution which i have created in DSWP. But now i am

  • How Do I Repeat A Formula Over and Over?

    New to Numbers. Have a document with 90 rows. I have had to enter in the same formula over and over on every other row, except that I have to change the row #. i.e. The formula I use is: =SUM(C2:H2). Then the next line is: =SUM(C4:H4) I am up to row

  • Issue in WAD 7.0 regarding opening document from MIME repository

    Hi Experts, I am facing an issue in WAD 7.0 regarding opening document from MIME repository.. My requirement I want to have a button , on clicking of this button one excel file ( already located at MIME Repository) should open in a new window. To ach