I am creating a process order . while creating the process order system is throwing error as Auto batch numbering not set up for material type XXXX in plant xxxx . System is not allowing to create process order.
How to resolve the issue.

Check in CORW   and switch off batch creation  to isolate the problem if needed.   Also see whether you have any batch managed compoents   for which you have set master data for automatic batch determination.
There is no setting for material types and plant for batch.  May be the error message is not correct.  What is the message number?

Similar Messages

  • Problem in process order creation.

    Dear Sir/ Madam
                             i am facing a problem while process order creation.
    the problem is:
    Error when calculating cost for order ATFEDEC11  "see log Log is deleted when saving
    Do you still want to save?"

    Hi,
    The log for production order preliminiary costing is not saved. Therefore, once the order is saved, there is no log available anymore (this is by the way a question of PP; none of the logs is saved).
    Hope that helps...
    Regards,
    Declan

  • REGARDING PROCESS ORDER CREATION

    Hi All,
    While creating the process order for material, system showing the message that "Manual process order cannot be created for this product". But if we try with another user id, i could able to create the order for the same material.
    Plz suggest the solution to get rid of this error.
    Thanks
    Arvind S

    Hi,
    The message "Manual process order cannot be created for this product" clearly indicates that the user is not authorized for Manual process order creation by COR1 transaction for this material and may be this material is planned through MRP or SOP etc. and in critical or certain situations manual process order creation is allowed to another user/user id for the same material ( type of materials/material code).
    Some time organizations put such restrictions through enhancements. You can search the exact reason or logic of restriction by the help of ABAP consultant.
    Regads,
    Narresh

  • External Number gneration for process order creation

    Hi,
       I need to generate external number range for process order creation and at the time of goods receipt.
       How can I do this in the include ZXVBZU02.
    Regards
    SAi

    You might want to try search first:
    http://www.google.com/search?hl=en&source=hp&q=externalnumberrangeforprocessordersite%3Asap.com

  • TCODE for Process order creation against Sales order

    Hi gurus,
    Pls tell me what is the TCODE for Process order creation against Sales order
    Eg. CO07 is for production order from sales orde

    Typically, in MTO scenario after the sales order is created you run MRP which will create planned order and then you convert that into production order using MD04.
    Or if you have SD settings correctly directly from the release of Sales Order it will create planned order or production order.
    please check and revert back.

  • Problem during Process Order creation

    Hi,
    I have problem while creating Process Order.
    I have maintained all the basic data required to create the process order.
    When I Release the order, I am able to create the control recipe also, but PI sheet is not generated along with it. System gives the message "No PI maintained in customising for CRD for which control recipe is to be generated "
    If I maintain the same, then system is unable to create the control recipe.
    What may be the problem here? What i can do to rectify this situation?
    Pavan

    Hi Pavan,
    1. Maintain PI in SPRO of process management
    2. Assign this PI to one of phse in master recipe
    3. Plz check wheather ur created Control receipe destination or not.
    4. if not then maitain the same in Spro.
    5.Check the ordre type dependent parameter i.e COR4 from SPRO
    see the Control recipe gerated in REL phse else maintai the asme in production scheduling profile.
    if possible plz send the sctren shot fir the same to
    [email protected]
    Regards
    Siddhesh

  • Error in Process Order Creation

    Hi Experts,
    I am facing a problem while creating a process Order in COR1
    I have got an error reading Master Data which is
    No task list for select.ID 04 for auto. task list selection found
    Please Help me out.
    Thanking You In advance.

    Dear Ashish,
    1.Check if a master recipe exists for the material in C203 and if exists means check the usage and status of the master recipe.
    that is value for status as 4 - Released General and usage - 1 - production .
    2.If no master recipe exists means then create one using T.Code C201.
    3.Then check the impact in COR1.
    Regards
    Mangalraj.S

  • Missing stock during Process Order creation

    Hello Masters.
    I'm facing a new problem here in my client.
    Thats the situation:
    We are trying to generate a subcontracting process order to delivery a semi finished material to a supplier in order to be packed. We already have a contract with this ssupplier, its been saved as a supplier, we already did this operation with him more than once.
    The question is that during the process to create the process order, system is giving us a message that there is no enough stock off semi finished material to be send to the supplier.  (it comes a message that is missing a small quantity to fiill the right amout we want to send to the 3rd party - something around 1,5% of the total amount)
    But if we go to MMBE we can see the same amount of stock we want to delivery to the supplier in free utilization.
    Besides we are using here WM we didn't see any difference that could give us the error.
    In QM inspection batch all the amount were released (321 movement) no sample quantity was taking/retained.
    The most insteresting part is the we did the same operation for the next batch of the same semi-finished material. I mean for the batch produced yesterday (monday may 9th) we already sent to the 3rd party for packing but for the batch from last friday, we are facing the issue.
    In this case we have the same kind of process order, same 3rd party, same materials, same process a so on.
    Please could you give me an idea where should I look for a solution.
    Thanks in advance.
    Harlen

    Hello Vivek thanks for your anwer.
    However, Ive talked to a QM consultant and presented the issue for him. He told me to use a SAP program QEVAC20 ( notes  48815 and 717622 ) to check possible inconsistences  between QM and IM stock.
    So We will try to use this report to check if there is an issue. Have you used this program before? Do you think it should help us?
    Due to the process to create the process order, there is no issue, no issue with batch number or inspection lot. The error message comes when we try to select the batch number of semi finished material in COR1 tcode.
    The message complains theat is missing a small quantity of the batch.
    Tks,
    Harlen

  • Automatic Reservation at the time of process order creation

    Hi Experts,
    As you are aware, when we create a process order and save, system automatically generates the reservation and the reservation will be for movement type 261. My requirement is like this. When system creates reservation, system should consider for which order type the process order is created and create a reservation for other movement type also.
    For eg. Iam having order type ZRRW. When system creates reservation at the time of order creation, system should check the order type and reservation should be created for a movement type Z11 instead of 261 in the normal case.
    Is there any user exit for the same. Please let me know.
    Else how can I post the goods issue with a movement type other than 261. MIGO is not accepting other movement types.
    Anticipating your reply
    Regards
    Prathib

    Hi Ayethebing,
    Thanks for the reply. we created the new movement types inorder to use the SAP standard reports and get the different types of goods movements based on the different processes.
    We can do the goods issue using the custom movement type through MB1A. But I was trying to use in MIGO and this is where system wont allow this.
    In MIGO, system will do the goods issue based on reservation only. The reservation is created at the time of order creation and it uses movement type 261 irrespective of the order type.
    I was trying to find out whether any option is there to use custom movement type to create reservation so that system would propose this movement type in MIGO for goods issue against process order.
    This is an interesting case but unfortunately dont have any option of user exit or Badi. Only one user exit related to reservation is to change the str loc and back flush indicator.
    @Sabine: Thanks for your reply. But the BADI that you provided wont serve the purpose.
    Thanks
    Prathib

  • At the time of Process order creation Batch determination

    Dear All,
    When i am creating process order at the time system not allowing me to execute batch determaination after release only it is allowing me to do.
    My requirement is At the time of order creation i want assign batches ( Execute Batch Detrmination)for the material.
    how to do this one, kindly hel me
    Regards,
    s.sakthivel

    Hi sakthivel 
    Go to OPKP (Production scheduling profile)  txn code and select in Batch management tab Automatic Batch creation at order creation (1) and check this profile is assigned to material in work scheduling view
    Regards

  • Process order convertion problem

    Hi All
    When I am converting the Planned Order to Process Order I am getting a error message Not able to determine the consumption account.
    Can anybody tell me how this problem can be solved.
    Is there anything I have to do in customizing
    Rregards
    Dhananjay

    Hi Dhananjay,
    check your material is been assigned to valution class in accounting view in MM02
    if it is assigned then check GL account is given properly to that valution class.
    take help of MM and FI consultant
    Thanks
    Bala
    IF useful reward

  • Process Order Creation without Standard Cost

    Hello All,
    I need a functionality.. If standard cost is not released for a period , system should not allow me to create a process order in the certain period.
    Is any standard configurations allow me to achieve this????
    Thanks & regards
    Mahesh
    Message was edited by:
            Maheshbabu M G

    Mahesh,
    Standard SAP allows creation of order without Std cost estimate. Only in REM you could make it give error.
    However I suggest you could implement the exit PPCO0006.
    In this the function module EXIT_SAPLCOZF_003 contains the import parameter CAUFVD_IMP which has material number (MATNR) and plant (WERKS). Pass these to table MBEW and get the value of STPRS (std cost). If this value is 0 then give the error.
    Hope this is useful....if so reward points and close this thread.
    Regards
    Ram

  • Availability check during process order creation

    Hi all,
    can anyone tell me significance of availability check during creation /change of process order?? ( in terms of business)
    how is the usual processs?

    Hi,
    Availability check for a material is carried out only if the material is
    1. A stock item
    2. Not a phantom item
    3. Not a bulk material.
    This can be carried out
    1. during order creation
    2. during order release
    3. when a created order is saved
    Availability check can be triggered either manually or automatically.
    For this we need to define in checking control(opjk)
    First define a checking group(ovz2) and checking rule and this
    must be assigned to checking scope.(opjj)
    In the checking scope(opjj) we should define
    1. which Mrp elements are to be considered during check
    2. which inventory categories are to be taken into account
    3. whether Replinishment lead time is to be taken into account or not
    4. whether check is also to be carried at storage location level.
    This checking rule must be linked to checking control(opjk)in which you can say
    1.No availability check for the material
    2.Availability check when saving the order
    3.What type of check is to be carried
    whether ATP CHECK or Check against PIR quantities
    4. Whether order should be released or not if there is
    any missing parts.
    The checking group is assigned to material master MRP3 view.Please check whether checking gorup is assigned to all the components in the BOM.
    Regards,
    nandha

  • Purchase order Creation Problem

    Dear All
                  For Local purchase NB order creation SAP Asking the Account assignement category.
    for only particular plant ,It should ask only Service orders. but why its asking the NB orders.
         Even Valuation grouping code already assigned for that plant.
    Any other settings required..
    Please guide..
    Regards
    Kumnar

    Dear All
    For Local purchase NB order creation SAP Asking the Account assignement category.
    for only particular plant ,It should ask only Service orders. but why its asking the NB orders.
    Even Valuation grouping code already assigned for that plant.
    "System Throughout the error "Account assignment mandatory for the material 200011"
    The material type is verp. and accounting view already extented for this plant
    Any other settings required..
    Please guide..
    Regards
    Kumnar

  • Process order release problem

    Hai All,
    I have created a process order and when i am releasing the same, following error is coming and system is not allowing to release the process order.
    Resource T-DTM100 in operation 0200 does not meet resource selection conditions
    How to solve the issue

    Dear,
    Please do check the classification of the master recipe the class maintained there?
    Also execute report RCCLUKA2 with the following parameters: Object table:      CRHD
    Class type:  019
    Please refer this link,
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/89/a42678461e11d182b50000e829fbfe/frameset.htm
    Regards,
    R.Brahmankar

Maybe you are looking for

  • Pointing Adobe 9 Pro to Shared Network Folder to Add Comments

    We currently use Pro7 as a standard in our company and put PDF's into SharePoint 2003 for review. All Adobe Acrobat 7 Pro.'s in our company point to a Z: drive for reviewing. When a PDF is posted into SP and opened via a link all comments can be seen

  • More info needed on BC Dynamic menus and using CSS with them

    Hi all, The BC Gurus tutorial on Dynamic Menus and how to style them with CSS made no sense to me, unfortunately. The presentation was too rushed and the screen too small to see what was happening. In a previous question I found out how to apply CSS

  • Add multiple elements to a tree control at once

    I am using a Tree Control to display customer and certificate information. However, adding 500 customer names or certificate numbers to the tree control one at a time takes for ever (well, 30000 ms). Is there any way to add multiple elements to a tre

  • Tasks not firing some times?

    Hi Experts, On the AD process form I have a task Get NEw Parent DN task which will compute the container field value and copies to process form container field value; there is another task container Updated. whenever process form container field valu

  • J2me with servlet

    hello experts Sir i want to call a servlet program in a j2me program i have found a program related to my requirment on net. But there is a problem that when i run as it is program according to net i give url="http://www.mycgiserver.com/servlet/corej