Hi Gurus,
How do you exactly add/create Number Range Groups for process orders?
Thanks,
Kumar

Hi Kumar,
Assigning number range
There are two types of number assignment:
Internal
When saving a data record, the SAP System assigns a sequential number that lies within the corresponding number range interval.
External
When saving a data record, either you or an external system assigns a number. You need to ensure that the number lies within the corresponding number range interval.
In CO82..
Menu path Group -->maintain
In maintain number range group screen,
Group --> insert
Give text and from number and to number
say text = new order say For FG
range - 1xxxxxxxxx to 1999999999999 (tick ext check box if the range is external number range-manual input)
click on +
You can see your group at the end of list
In Not assigned group your new order type will be present
Place the curser on that order type and fallow the menu path as below
Edit -->select element
Select NEW order number range group check box
edit --> assign element group.
Now the number range is assigned to the order type. Save it, You will get a pop up, just ignore it.
Please try and come back.
Regards
R.Brahmankar

Similar Messages

  • PRocess Order Number Ranges

    Dear All,
    I have a Problem with process order Number ranges,
    please find the sequence below.
    21000200
    21000220
    21000240
    21000260
    21000280
    21000300
    21000320
    21000321
    21000322
    21000340
    21000360
    21000380
    21000381
    21000400
    21000401
    21000402
    21000403
    21000420
    21000421
    21000422
    21000423
    Please anybody help me in this.
    How to get contineus numbers.
    Where I need to check, Please specify.
    Thanks & Regards,
    Anand.M

    Dear,
    Go to SNRO t-code.
    In this t-code enter AUFTRAG object.
    This object is for Order type.
    Here you will get option No. of Numbers in buffer check it. This is the field which is responsible for number range buffering
    Regards,
    R.Brahmankar

  • PP Process order number ranges

    HI Gurus,
    I am New to PP i have one question.
    We have a client requirement like they have two plants and they will use same process order type but they want two different number ranges for 2 plants.
    Please help me to resolve this issue.
    Pranesh

    Old requirement, no solution. Number range is not plant related. Only solution is (not recommended) to have different order types for each plant.

  • Process Order Number

    Hello Friends,
    I have an issue which is when we create a process order and when we save it the process order number is not coming in continuous series and it is coming in randam numbers. Can any one give me solution for this issue.
    Thanks,
    KS

    Hi Niraj,
    Thanks for your response as per your suggestion i have checked the number range for Process Order and it is Internal only not external. Would you please hlep me out to close this issue
    Thanks,
    KS

  • Why after new changes in internal orders settings order number ranges lost?

    Dear Gurus,
    We have noticed that order number ranges are being lost from time to time.
    Than we have analysed that sometimes it happens after new transfers with new orders settings.
    Why the system behaves like that?
    And how can we avoid this problem?
    With best regards,
    Kamila.

    The process is as below to assign/change number ranges to order types
    Create Order type at KOT2 (KOT2_OPA) and enter Order Category ...say 01
    Enter Order type name and description and SAVE
    Select Number range Interval assingment Icon
    At last row of the number range screen you can see your newly created Order Type
    (Put the cursor on your order type and press F2) and Select the check box of group under which you need to assign and press F5
    Now the newly created order type has been assigned and new number range has been assigned
    So you can change existing order type also as mentioned above (even after posting made to that order types)
    This could be the reason for changing number ranges to order types
    Please take care while assigning number ranges to a new order types.  Do not touch number ranges of existing order types
    Srinivas

  • Service order number range creation

    Hi,
    Could anyone please tell me how can we create service order number range if we have done a new service order type creation, and what should we do: should we create the number range in development and then transport it to the production or we should directly create it in production.
    Thanks and Regards

    Hi,
    Please guide me what should we first do to transport the service order type transport request to prd.
    1.Should we first transport the request for other components of the service order type?
    2.Then should we transport the request for number range or we directly create it in production server?
    Please guide.
    Thanks and Regards
    Edited by: MPVash Vash on Sep 8, 2008 7:53 AM

  • Process Order number as batch number for produced materiai

    Hi gurus
    Is it possible in SAP to automatically set the process order number as the batch number for an semi finished good or finished good? Is there a config like that in SAP?
    Thanks

    Hi,
    Refer this [link|http://help.sap.com/saphelp_46b/helpdata/fr/e9/c6f9bdaa28d3119b440060b0671acc/content.htm]
    you have to use EXIT_SAPLV01Z_001 and EXIT_SAPLV01Z_002 in the case were you want to Copying the production order number to the batch number.
    Regards,
    Dhaval

  • Planned Order Number Ranges

    Hi Gurus,
    I am having two plants defined in one company code.
    Is Planned order number range plant specific?
    My planned order number range in plant-1 is 1000-2000 and it is same in the Plant-2. If I create the planned orders in both plants.
    What is starting number for planned orders in each plant?
    Can I create like this?
    Thanks in advance.
    Regards,
    Jejesh
    Edited by: jejesh yal on Sep 30, 2008 9:25 PM

    Hello,
    If you are creating Planned order using the MRP, you  can set the plant specific Number range for planned Order at OPPQ
    Please check with planned order Number range  tab at OPPQ
    Regards
    Pradeep

  • Demerger  Purchase order number range.

    Hi Friends,
    We have demerger of 1 of hte business of the company & new entity will be using same client which we are using.
    We will be Creating new Purcharse orders with open amounts for new legal entities.
    Here requirement for purchase order number range is as belows. How can we achieve this.
    Our advice for number range is to use a prefix + old PO number, to ensure the incoming invoices can be easily assigned.
    Thanks,
    Kiran

    HI,
       You may define external number range as shown below, for example:
       Assign the same as external number range for the PO Doc type:
       While creating the PO, maintain the number range externally with the required prefix + old PO number.
    Test the same and revert back.
    Regards,
    AKPT

  • Planned order number range in apo

    Where planned order number range  can be maintain in apo.
    I am converting agreed plan into planned order but planned order number has generated.
    Please somebody tell me.
    Regards,
    Sunill

    Planned order number ranges can be maintain in
    sproaposupply chain planningppdsglobal settings--maintain number ranges for orders.
    and then you assign the number ranges in
    sproaposupply chain planningppdsglobal settings--maintain global parameters and defaults (in planning tab )

  • Best Practice for Change Maintenance Order Number Range

    Hello
    We have decided that our Maintenance Orders will always start with the year of the open date. Example 201112345155
    Every year we will need to change the number ranges
    What is the best practice to change the order number range? What is the best approach here?
    I have also another question. Why the "Current Number" is not incremental?
    Thanks for the help

    Hi,
    The current number can be explained by use of buffering of the numbers. Buffering is defined via transaction SNRO, the  AUFTRAG object is relevant for orders. When buffering is active, a set of unused numbers are assigned to each application server.
    In your example -  The fiirst 20 numbers were taken from the available number range and assigned to the buffer (possible 10 numbers to each of two servers). As orders are created a number is assigned from the buffer. Once the buffer values are used a further set of numbers are taken from the number range and the current number is increased (by buffer value).
    -Paul

  • Cannot create work order number ranges

    Hi Gurus,
    I am working on ECC->XI->SNC systems. I want to maintain work order number ranges in SNC but I am encountering an error or "User is not assigned to a suitable business partner" and also there is no Append Row button to define work order number ranges. Can you please help me configure the user properly? Also, how will the Append Row button appear in SNC? I would appreaciate if you can also provide reference materials on this. Thanks.

    Hi,
    You are getting this error "User is not assigned to a suitable business partner" because the user through which you've logged in is not assigned to any Business Partner of type "Organisation".
    If it it is an internet user, you should assign it to your plant (if he is on the customer side) or Vendor.
    The relationship to be maintained it "Is SNC User of".
    Regards,
    Sandeep

  • Enhancement for Production Order Number Ranges

    Hi
    Are there any enhancements for production  order number ranges. We have the setting as external numbering but need to set the order numbers (alphanumeric) based on certain conditions.
    Thanks & Regards.
    Sam.

    Hi Sam,
    PPCO0007 .......check this one.....
    i guess it is helpful
    Regards,
    Bhaskar

  • Production Order Number Range - Not Continuous

    Hi Team,
    I have assigned the internal number range for my order type in CO82. When the system assigns the internal number (my production order is 10 digit number) to my production order, the number is getting assigned continuously. For example, if the last created production order number is 2481000001 , i am expecting the next number as 2481000002. But system is creating some number like 2481000023. In-between many numbers are missed. Why?
    Production Order Number Range Assigned: From: 2481000000, To:2481999999 (Internal Number range)
    Thanks

    Hi Caetano,
    As described in the note 62077, i can do the following setting.
    1.  Deactivate buffering: Choose 'Edit' -> 'Set Up Buffering' -> 'No Buffering'.
    2. If you want to change the buffer size only, enter the corresponding value in the field 'No. of numbers in buffer'.
    Case 1:
    If i activate the option "No Buffering" for object "auftrag", will it have any negative impact like performance of the system?
    Should i need to activate the option "No Buffering" for object "auftrag" before creating the production order?
    Case 2:
    I do not want to deactivate the buffering. But i will set the 'No. of numbers in buffer'as ONE (1). I think with this settings, the numbers will be always continuous. Will it have any system performance impact?
    Thanks

  • Process Order number as batch number

    Hi Gurus
    Is it possible to have my process order number automatically serve as my batch number for the produced material?
    Please help

    Hi,
    I guess you may not be able to assign the batch number same as process order number when you just cerate the order even in enhancements since you do not have new process order number avilable till the order is actually saved and order number is generated in update task in background.
    you can probabaly add batch number while releasing the order in CO02 transaction separately. Make sure create and release are not carried simultaniously in one session of CO01.
    Check and revert.
    Regards,
    Santosh Sarda