Process Order release rejected

Hi All,
          I want release the process order but it shows the error like it is rejected .  in that i have seen the master data all are assigned to that process order and it shows like this  release rejected (check log) message no:C2039. what is this meaning

Hi,
           i got this errors.       
        E     CO     288     1     1     70000862               Order type PI01 plant 1000: No checking rule maintained for operation
     E     CO     118     1     1                    Release of order not possible
Edited by: chakri_man on Oct 3, 2011 11:32 AM

Similar Messages

  • Process order release reject.

    Hi Experts,
    Question related to Make to order (MTO)
    I was created one sales order successfully.
    Then I run MRP and i got Planned sales order.
    After that I converted that planned sales order sa process order.
    When i click on release icon, my proble arised.
    that is Released rejected.
    I checked the stock availability in MMBE/MB52, there I found lot of stock.
    But in the Process order message is comming that missing parts list.
    Can any body give me solution for how to release the process order.
    by
    M.Anand (Hyderabad)

    Hi,
    This has already been replied to in your earlier post...!!!
    check and revert.
    Cheers,
    Rajan.

  • Batch number coming automatically at the time of Process order release

    Hi All,
    I want the system generated batch number for header material to come automatically at the time of process order release.
    At present ,the batch number is entered manualy dering process order creation.
    Can anyone pls guide abt the settings required for the same

    Dear,
    Define the  production scheduling profile CORY then
    Auto Batch Creation = 2 On release.
    Then assign this to your FG or SFG materials in work scheduling view in material msater MM02. Then create new order and check.
    Now for automatic generation i have to set internal number asignment for batches.
    Batch will create for movement type say 101 SPROLogistics - GeneralBatch mangment--Creation of New Batches --Define Batch Creation for Goods Movements. so it will have same logic in MM for 101 GR against PO will be internal number range but no effect in SD.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Mar 12, 2010 12:40 PM

  • User Exit at process order release or save

    Dear experts,
    Can any one help me which user exit will be useful at the time of process order release or save (t code COR1/COR2).
    My requirement is to stop the process order release if there is any maintenance order is already released on that date.
    Process order should not get released in between the start and finish date of PM order for the same equipment.
    I could acheive this for PM side by using a user exit IWO10002, here if any process order is released for an equipment PM order cannot be released for the same equipment in between start n finish date of the process order.
    Please help me out in finding the user exit for process order release / save.
    Thanks in advence,
    Regards,
    Praveen.

    Hi,
    The following enhancements are available for process order management:
    For order maintenance:
    o   PPCO0006 to predefine entries for order header fields when creating
        an order
    o   PPCO0001 to provide information at the time of saving (for
        production orders and process orders)
    o   PPCO0007 to check or change header data when saving
    o   PPCO0002 to add additional checks that are to take place when
        setting the deletion flag or deletion indicator
    o   PPCO0003 to prevent changes in sales order items that would cause
        changes in the process order for static assembly processing
    o   STATTEXT to format the status line
    o   PPCO0008 to check components that have been changed or added
    o   PPCO0005 to change the storage location and the 'backflush'
        indicator in the reservation
    o   PPCO0013 to change the priority of the selection criteria for batch
        determination in production orders or process orders
    o   PPCO0014 to restrict the selection of process orders that are
        offered when creating external relationships
    o   PPCO0020 to display additional information for another tab page in
        the process order header
    Regards,
    Dhaval

  • Suggest the user exit when process order released then save

    Need to update batch value from component's batch field to FG batch field. Need at the time of process order released and saved. Can you please tell me which user exit to use?

    Hi,
    The following enhancements are available for process order management:
    For order maintenance:
    o   PPCO0006 to predefine entries for order header fields when creating
        an order
    o   PPCO0001 to provide information at the time of saving (for
        production orders and process orders)
    o   PPCO0007 to check or change header data when saving
    o   PPCO0002 to add additional checks that are to take place when
        setting the deletion flag or deletion indicator
    o   PPCO0003 to prevent changes in sales order items that would cause
        changes in the process order for static assembly processing
    o   STATTEXT to format the status line
    o   PPCO0008 to check components that have been changed or added
    o   PPCO0005 to change the storage location and the 'backflush'
        indicator in the reservation
    o   PPCO0013 to change the priority of the selection criteria for batch
        determination in production orders or process orders
    o   PPCO0014 to restrict the selection of process orders that are
        offered when creating external relationships
    o   PPCO0020 to display additional information for another tab page in
        the process order header
    Regards,
    Dhaval

  • FEFO logic in batch determination for process order release

    Batch determination for a particular material in a process order was following FIFO logic . We needed to change it to FEFO hence we made the necessory changes in COB1 how ever the process order relase is still taking the batch whihs is not the first expiry batch
    Kindly help in batch determination with FEFO for process order release.

    Rk
    The blw explation for inventory side, i don't have idea for prod order side
    If Batch Management is active for the materials then use following process;
    First create characteristic in CT04 for Batch Creation Date, under "Addnl data", enter Table Name MCH1 or MCHA (As per Batch Class 022 or 023) and Field ERSDA and save it.
    Assign this characteristics in CL02 in your Batch Class.
    CU70 - Create a Sort Rule and specify the Characteristic of Batch Creation Date and activate "Ascending" indicator.
    Now assign the Sort Rule in MBC1 and keep Selection criteria as "O" for the Strategy type.
    Now do batch determination in MIGO.

  • Process order release

    Hi,
    I am unable to release a process order. I am getting an error message - Release not possible. Am I missing any configuration settings?
    Please advise.
    Ranganath

    Hi Ranganath,
    The simplest thing to do is to check the Logs. In the process order display use menu Goto>Logs-->On release, this would give you the information why the release is getting rejected.
    Couple of problems could be that Order Control is not defined for the Process ordertype/Plant/Business condition combination. You could check this in transaction OPJK.
    Other reason why it may be failing is that due to shortage of Component stock or Shortage of Capacity. The control for this also defined using OPJK.
    Hope this would help you in resolving. Kindly reward your points,
    Regards,
    Prasobh

  • PR item text to be updated on Process order release

    Hi Experts,
    The scenario is mentioned below :
    The purchase requisitions would be created on the release of PRocess order.
    My requirement is to update the item text of the Purchase requisition ( with the process order data such as BATCH & Material ) on release.
    I have already tried quiet a few user exits, but beacuse the PR number is not yet generated in these exits,hence  I cannot use create_text or save_text.
    Please let me know if someone has any idea on how this can be solved.
    Hoping for a quick response.
    Warm Regards

    Hi
    Check the exits related to PR for Process order
    COZF0001
    COZF0002
    Try to fetch the Long texts of the PR's using the READ_TEXT and use the fun module
    CREATE_TEXT for saving the same in Process order by using the Right parameters like OBJECTName,ID,OBJECT and LANG in bothe cases for PR and process order.
    The tables link between the PR and the order is
    AFKO-AUFNR  = EBKN-NPLNR  ( process order number) in PR account assignment table
    use this link and try to save the text as mentioned above
    Reward points if useful
    Regards
    Anji

  • Process order release problem

    Hai All,
    I have created a process order and when i am releasing the same, following error is coming and system is not allowing to release the process order.
    Resource T-DTM100 in operation 0200 does not meet resource selection conditions
    How to solve the issue

    Dear,
    Please do check the classification of the master recipe the class maintained there?
    Also execute report RCCLUKA2 with the following parameters: Object table:      CRHD
    Class type:  019
    Please refer this link,
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/89/a42678461e11d182b50000e829fbfe/frameset.htm
    Regards,
    R.Brahmankar

  • Process order release date as batch manufacturing date

    Hi All,
    We have automatic batch creation during the release of the process order. Now the requirement is that proess order release date should be updated as Batch manufacturing date in the corresponding Batch data (MSC3N). How this can be done.
    Regards
    Vinamrath

    Hi Vinamrath,
    Hope your proess order release date and the batch creation date are same.
    In such case go to txn CT04 (create Characteristic) and create a  Characteristic say  "Batch manufacturing date". Then in the tab Addnl data maintain the table name as "MCH1 or MCHA" and Field name as "ERSDA" (created on-this is the batch creation date).
    In case your  proess order release date and the batch creation date are not same, then there is a field called " HSDAT" -date of manufacture.you can maintain this field name in addnl data.
    Maintain this Characteristic in classification (CL02)
    Then this will get updated in the batch and same can be viewed in MSC3N
    Regards
    Hari
    Edited by: Harikris_83 on Sep 29, 2011 3:05 PM

  • Process order Release COR1/COR2 depending on result of derivation

    Hi All,
    I have a requirement , where in Transaction COR1/COR2, I enter all the details and go to Release using the FLAG button at the time of doing Release i get one pop-up called Result of Derivation with Error/Warning/Information with either OK/Cancel.
    If i do OK , i can still release the Process order though i have Error in the result of derivation pop-up.
    My requirement is , if there is any error in this result of derivation i should not be allowed to Release the process order .So either the OK button should be disabled or i should display a error message at the time of saying OK ,if there is any error and don't allow release.
    Please guide some enhancements.
    Thanks,
    Rajendra

    With help of workorder_update badi

  • Process order release - user exit ?

    Hi experts,
    I need to build an interface where all the released (and all the updated)process orders need to be transfered from SAP to a warehouse system thru XI.
    I have identified an IDoc(LOIPRO01) which fullfill my needs but didn't find yet where to generate it.
    I'm searching for an user-exit triggered at the release of a process order.
    I have found this one:
    PPCO0007(Exit when saving production order) but the documentation says "a lot of data in the order header is only set once the customer exit has been processed"
    Any suggestions on how I can do this is greatly appreciated.

    Hi Fabien,
    Welcome to SDN.
    You can execute t/code <b>POIT</b> or standard SAP program <b>RCCLTRAN</b> to generate IDoc LOIPRO01.
    Prior to execute, please ensure you have done the configuration for ALE and IDoc.
    Hope this will help and let me know if you need further assistant.
    Regards,
    Ferry Lianto
    Please reward point if helpful.

  • COR2 release flag(Process Order Release)

    HI all,
    can we release a work order from  cor2
    if yes where can we find that release flag
    Thanks in Advance,
    Suresh

    Hi Suresh,
    Please find the process for releasing process order .
    1.     Choose from menu Process order à Functions à Approval à Individual approval.
    2.     Choose Materials and on the Create Process Order: Material List screen release the order by choosing Release (Ctrl + F6). Batch determination and creation of control recipe are carried out automatically.
    3.     Save your entries.
    For releasing a process order which already exists please use following steps:
    4.     Access the transaction using:
    Menu     Logistic à Production–Process à Process Order à Process Order à Change
    Transaction code     COR2
    5.     On the initial screen, enter the necessary data.
    Process order          Your PO number     
    6.     Choose Enter.
    7.     Choose Release (Ctrl + F6).
    8.     Save your entry.
    Result
    When the process order is opened, material reservations for the required material components are created automatically or the specifications are transferred from the planned order. Purchase requisitions are created for material components or services that have to be procured externally. Capacity loads occur at the resources where the order is executed. The planned costs are also determined.
    The following constraints apply to an opened process order:
    ·     You cannot carry out a confirmation for the order.
    ·     Shop floor papers cannot be printed.
    ·     You cannot generate a control recipe.
    ·     You cannot carry out goods movements for the order; in other words, the components cannot be withdrawn.
    These constraints no longer apply when the order has been released.
    During releasing the availability of the materials will be checked again. Automatic batch determination is carried out for the materials PH-1710, PH-1720 (or PH-1810, PH-1820, PH-1830 and PH-2700 respectively). In addition to this, the control recipe is created, preliminary costing is carried out, and the process instructions are generated.
    Hope This Info Helps YOU.
    Regards,
    Lakshmi

  • Order Release Rejected

    Dear all,
    we have made a new order type for MTO.order gets created for planned order.If i release it i get a message saying Release Rejected.
    CRTD PRC  BCRQ MANC RELR SETC.
    Kindly help.

    Hi Rahul,
    Order release can be rejected for multiple availability checks 1) Non - Availability of Component stock 2) Non-Availability of PRT stock 3) Non-Availability of Capacity for the required resources. Check the transaction OPJK for the plant/ order type combination for business function "2".
    Or,
    Go to TCODE : OP45
    Select the task list Usage & go to task list type .
    There is a check box:Indicator: Usage only until release in order . uncheck this box & save the transaction.
    Regards,
    R.Brahmankar

  • Batch determination during process order release

    Dear Experts,
    I am facing a problem, and not able to figure out the reason. There is material having base unit as 'EA' and Issue unit as 'NO' and conversion is 10 NO= 1 EA. The same material is maintained in the BOM as 1 NO. At the time of creation of process order, system is copying the same quantity in the process order (1NO). When I release the process order, the batch determination is happening. Now the issue comes, instead of doing batch determination of 1 NO, system is doing batch determination for 1 EA (which is equivalent to 10 NO.!). Can anyone help me to find out the reason for same.
    Thank you.
    Sagar

    Dear Mohit,
    If you want to go for external batch numbering during order release then
    - Set no automatic Batch creation in order in T.Code CORY.
    This setting only restrict the automatic Batch Creation in order only.But to fulfill second your requirement of restricting order release or save without assigning external batch no you have to either go for,
    - User exit.Below are the user exits which are trigger at the time of order saving
    PPCO0006 to predefine entries for order header fields when
    an order
    PPCO0001 to provide information at the time of saving (for
    production orders and process orders)
    PPCO0007 to check or change header data when saving
    or
    - Create screen variant using T.code SHD0 and make Batch Field compulsory.
    Regards,
    Dhaval

Maybe you are looking for

  • HT4847 can you share icloud storage space with a family member?

    I used to have MobileMe family, and my wife and I are now both receiving alerts that we are running out of icloud space. Can you buy a shared icloud plan? Thanks

  • No alerts when connected with bluetooth

    Hello I have a 2013 Hyundai Elantra and a iPhone 5 running iOS 7.  When my phone is connected via Bluetooth and I'm listening to fm or xm radio my phone automatically places my text and email notifications to vibrate

  • Duplicate journal entry

    HI Expert, My client want to prepare on Functional Specification for identifying the Duplicate Entries in GL, Vendor and Customer A/c. there is already Standard report available in SAP but they needed other than that. Here the client is using SAP as

  • Using Dimension as a fact

    I have a scenario: let me create that with simple Prod/Cus/Ord tables so that everyone can understand (instead of using my business terms). Product table: prod id prod name Staff table: staff id staff name Customer Table: cust no customer name staff

  • Access to  rsa1 in many clients

    Hello gurus, Can i create in an instance bw, several clients with access to the transaction rsa1. I ask this because in  rsadmina table (table intermandant), the field bwmandt is individual. When I connect to another mandant (exemple 810) and I test