Hi Sue,
Process Orders can be assigned to a Production Campaign. You use Process Order when using PP-PI. You may or may not use Production Campaign. It depends on the type of resource you are planning and executing. Production Campaign is primarily used to define time periods on the capacity when you produce certain type of products considering sequence dependent capacity planning.
For exmaple you have a resource - vessel or tank which can be used for producing multiple products but you need to do setup and cleanout activities after each type of product. So if you have process orders for Product A followed by Product B and then Product C and back to Product A - you end up having non-productive time (when setup and cleanup activities happen).
Instead you create Production Campaigns on the resource whereby you define for certain time in future you are only going to produce Product A followed by Product B and then C. In such a case all the Production Orders in future for Product A are assigned to Production Campaign for Product A and likewise. This reduces the non-productive time and also optimises the sequence dependent production plan.
This is only possible when the rate of production is quite higher than the rate of consumption (demand) else you cannot produce sufficient quantity in stock to meet the demand till the next production campaign is scheduled.
Hope this helps.
Somnath

Similar Messages

  • Purchase order vs planned order vs process order vs production order

    Hi,
    Kinldy explain difference between the  Purchase order,  planned order,  process order and production order?
    Thanks & Regards
    Ravi kumar

    Hi Ravi,
    In simple terms:
    planned order - A procurement proposal generated by the system to meet a need, this can then be converted to a production / process order (for internal procurement) or into a purchase reqn & in-turn to Purchase order (for external procurement)
    Purchase order - A firmed procurement proposal which is sent to your vendor (external procurement) to supply the items as per your order
    process order - A firmed procurment proposal which is used for in-house procurement, this is used in process industries eg: chemicals, oil & gas etc 
    production order - A firmed procurment proposal which is used for in-house procurement, this is used in discrete production industries
    Based on the above am quite sure you should be able to figure out the differenced. If any doubts revert.
    Regards,
    Vivek

  • How can we tell the client that use process order or production order (proc

    Dear guru,
    My question on what reason we can tell the client that u have to use process order or production order .
    On what scenario we suggest client that use process order or production order

    Hi,
    Process manufacturing is primarily designed for the chemical, pharmaceutical, food and beverage industries as well as the batch-oriented electronics industry
    Discrete manufacturing is u201Cthe production of distinct items such as automobiles, appliances, or computers,u201D whereas process manufacturing covers u201Cproduction that adds value by mixing, separating, forming, and/or performing chemical reactions. It may be done in either batch or continuous mode.u201D
    Letu2019s think about what your company manufactures. Does it require mixing chemicals? If so, you may need an ERP system that does things like calculate ingredient quantities.
    If your company assembles products from many component parts, youu2019ll require discrete manufacturing functionality
    Other approach:
    If the finish good cannot return back to its basic components, your manufacturing is Process. For instance, the finish good is a can of soda. It cannot return back to its basic components such as carbonated water, potassium benzoate, aspartame, citric acid, and other ingredients. But if the finish good is car or computer, your manufacturing process is Discrete because it can be disassembled and the parts, to a large extent, can be returned to stock. Therefore Bill of Material (BOM) of discrete manufacturing consists of component parts for assembly while Process manufacturing consist of formulas, recipes and other ingredients
    Process manufacturing is scalable. If a formula calls for 1,000 pounds of cake flour, but you only have 500 pounds, you can still bake cakesu2014just not as many. Conversely, in discrete manufacturing, one missing part means waiting for it before the finished assembly unit can start rolling off the production line
    The obligatory requisite for process manufacturing is Lot Potency and Shelf Life where as discrete manufacturing values Serial Numbers, ECNu2019s and assembles.
    If it is discrete manufacturing ---go for Production order
    If it is process manufacturing ---go for process order
    thanks and regards
    Venkat V

  • Difference between process order and Production order

    Hi Experts,
    Can any buddy tell me the difference between process order and production order. Why process order is used for process industries. Why do we use recipe for it and routing for production order ?
    Regards,
    Amit

    Hi Amit
    There is a difference between production order and process order.
    Supposing a 10,000 lit tank is being manufactured in discrete manufacturing. You have to follow the necessary routing steps and can make by physically seeing its development stage by stage. For this type production you can have a production order.
    In case of process of order if some chemical in a reactor is loaded with intial temp of 30 C and need to be heated to 80 C then there is phase change. Hence we use Heating as an operation and the change of temp is phase. For such type of process we process order.
    Hope this is useful. Pl reward.
    Nanduri

  • Process orders and Production order in PP

    Hi,
    In our case Process orders are used in most of the case ,than production orders. Pls tell wheather Process orders are also pulled by the extractors(PP) and behave similar in all the Standard PP reports. and what is the diffrence between Process orders and Production order??
    Regards
    Nair

    Hi
    In PP, you can see Production Planning and Production Planning -Process Industry
    Production order is for manufacturing industry
    Process order is for process industries where input raw material is processed to arrive at end product.Process order keeps shop floor person aware of processing status.If your client's business have many processes than manufacturing you might come across more processing orders
    Regards
    N Ganesh

  • Process orders and Production orders??

    Hi,
    In our case Process orders are used in most of the case ,than production orders. Pls tell wheather Process orders are also pulled by the extractors(2LIS_04_PEARBPL,2LIS_04_PECOMP
    ,2LIS_04_PEMATNR,2LIS_04_P_ARBPL,2LIS_04_P_COMP,
    2LIS_04_P_MATNR) and behave similar in all the Standard PP reports. and what is the diffrence between Process orders and Production order??
    Regards
    Nair

    hi,
    both are similar but varies with industries.
    Process order- used in chemical industries- involves process like heating, melting etc.
    Production order- used in car industries- assembling, drilling process
    Assign Points if useful
    Ramesh

  • Setup/clean-out orders for production campaign

    Hi experts,
    Can you tell me the steps that I have to execute if I want to create in APO PPDS a setup/clean-out order for a production campaign
    Regards,
    Arnulfo Cordero Pradel

    HI Victor,
    In the setup matrix you are suppose to maintain the dummy PPM detains aganist the setup groups.
    means: maintain the following information in setup matrix and try
    Setup transactiopn type: I
    Predecssr: Setup group 1
    Sucessor: Setup group 2
    Setup time: blank
    Unit: Min
    plan: Dummy PPM
    Product: Dummy product
    Regards
    Sravan maturu

  • Process order vs. production order

    Hi there,
    how can I differentiate a production order from a process order regarding table AFKO???
    Thanks a lot!
    Kind regards
    Max

    use table AFPO, the differenciating field is order cat AFPO-DAUTY.
    It is 40 for process order and 10 for production order.

  • Transaction COIF- Production & Process orders with Production Notes

    Dear All,
    Can anyone please explain the significance of transaction COIF.How to create production memos & how is it useful?

    This report list outs orders for which production memos are maintained, in long text for production order ther will be a section for production memo if text is maintained in this section then system will list this production order when COIF is executed.
    In production memo certain instructions can be entered which needs to be passed to shop floor, COIF helps to identify such orders where instructions are entered.
    in the co02 or COR2 thjrough menu you can check  header--->production memo , it will be active if test is maintained in long text under section for production memo.
    hope this will help
    rgds
    Anand

  • Reprocessing of Production order/Process order

    Hi friends,
    Can anybody explain me what is reprocessing of production order.
    Plz explain me in a step by step manner.
    Thanks very much.
    Kind Regards

    Hi Arun Kumar,
    Reprocessing
    Use
    In the area of confirmation, you can separate confirmation entry from processing. As a result, errors may occur when confirmations, or the processes that follow them, are posted. You can eliminate these errors by reprocessing them. The following reprocessing functions are available:
    Confirmations
    Actual costs
    Goods movements
    Reprocessing Confirmations :
    Use
    You use this function to process confirmations for which errors occurred as they were being automatically processed. With this function, you can either delete or, if possible, eliminate the errors and post the confirmations again.
    Confirmations with errors can arise if they were entered in one of the following ways:
    Upload from a PDC system (see Upload)
    Online entry ( Fast Entry or Mass Processing)
    Entry via BAPI interface
    Possible errors include:
    Order does not exist (for entry via PDC system, BAPI interface)
    Order was locked
    Sequence of time events incorrect
    Individual capacity does not exist
    Work center or personnel number does not exist
    Features
    Reprocessing has the following advantages:
    Selection
    On the initial screen, you can enter your selection criteria for selecting the confirmations that you want to reprocess. Possible selection criteria are: Production order, plant, confirmation, WBS element, sales order, MRP controller, work center, created by, created on.
    Navigation
    The screen for reprocessing confirmations is split into two areas:
    Overview list of the confirmations
    Detail screen for the selected confirmation
    In the standard setting, the overview list is on the left and the detail display of the confirmation is on the right. To change the position of the overview list, choose  (move the list in an anti-clockwise direction, select the position of the overview list). This last setting is saved for the particular user who created it and is used again the next time the function is called up.
    Reprocessing
    The confirmation that you have chosen from the overview (cursor position) is displayed in the detail screen. In the detail screen, you can remove the error in the confirmation.
    The following confirmations can be reprocessed:
    Order confirmation
    Operation confirmation
    Time event confirmation
    Activity confirmation
    The layout of the detail screen is determined by the confirmation that you are currently processing. The layout can be set up flexibly for an operation confirmation (see Single Screen Entry).
    Display error
    To display a long text about the error for each confirmation, position the cursor on the confirmation and choose .
    Check confirmation
    You can check one or more confirmations. To check confirmations, select them and choose . In the Status field on the overview list, the result of the check is displayed with a symbol.
    Delete confirmation
    If a confirmation is not to be posted because, for example, it has entered the SAP System by mistake, you can delete it. To do this, select the confirmation and choose . The confirmation is flagged for deletion and is deleted when you save.
    Delete a line
    To delete confirmations from the overview that you do not want to process at the moment, choose . The confirmation is, however, retained for reprocessing at a later stage.
    2.Cost Determination Error Processing
    Use
    You use this function to gather information about errors in cost determination and if necessary to repeat it.
    If errors occurred when determining actual costs online, you can decide whether or not the confirmation and the error records are saved. If you are using Decoupling Confirmation Processes, the errors are recorded during the execution of the background job or during updating.
    Features
    This function includes:
    An error log which displays the cost determination errors in detail
    Errors are, for example: missing activity prices, invalid cost centers or incorrect assignment of an activity type to a cost center.
    Rerunning cost determination
    Starting a New Costing Run
           1.      Choose either
    ¡        Production orders: Logistics ® Production ®  Shop Floor Control ® Confirmation ® Reprocessing ® Actual Costs
    ¡        Process orders: Logistics ® Production u2013 Process ® Process Order ® Confirmation ® Recalculate Actual Costs
           2.      Enter your selection criteria.
           3.      Choose  (Execute).
           4.      Select the confirmation in question and choose  (Error Log).
    Analyze the errors.
           5.      If necessary remove the errors.
    To remove the errors, you have to exit the reprocessing function.
           6.      Choose Production ® Shop Floor Control ® Confirmation ® Reprocessing ® Actual Costs or Production u2013 Process ® Process Order ® Confirmation ® Recalculate Actual Costs or open a new session.
           7.      Enter selection criteria for the confirmations for which you want to restart the actual cost calculation.
           8.      Choose  (Execute).
           9.      Select the confirmation and choose  (Save).
    Failed Goods Movements Processing :
    Use
    This function allows you to process goods movements that failed when posting confirmations. After correcting any errors that occurred, you can then post the goods movements a second time.
    Features
    This function includes:
    Detailed display of errors
    Errors can be caused by insufficient information such as missing storage locations or missing batch numbers. Errors can also include locked material data, insufficient stock, or attempts to post goods movements in the wrong accounting period.
    Opportunity to correct failed goods movements
    Option of posting goods movements a second time
    Reprocessing Goods Movements
           1.      Choose either
    ¡        Production orders: Logistics ® Production ®  Shop Floor Control ® Confirmation ® Reprocessing ® Goods Movements
    ¡        Process orders: Logistics ® Production - Process ® Process Order ® Environment ® Material Movement ® Failed Goods Movements.
           2.      Enter your selection criteria:
           3.      Choose  (Execute).
           4.      Select the goods movement that you want to reprocess.
           5.      Choose  (Display Errors) to display the errors that have arisen, in detail. To leave the message, choose  (Continue).
           6.      Select the required goods movements and make the necessary changes (for example, Edit ® Replace ® Storage location).
    For example, you can delete incorrect goods movements.
    When incorrect goods movements are deleted, the system does not carry out an automatic adjustment of reservations.
           7.      Choose  (Save) to restart the execution of goods movements.
    When you are reprocessing the goods movements for the confirmation, you can go to the goods movements overview.  Choose  Change Details, to change the goods movements.
    Hope this details is enough for clearing your doubt.
    Revert if any doubt and reward if useful.
    Regards,
    Tejas

  • Target Vs Acual Cost Comparison for multiple process orders

    Dear SAPians,
    I want to take a report for target vs actual cost for all process orders and product cost collectors created in a particular period. I have checked the standard report KKBC_ORD that serve my purpose but for a single order. I want the same report for multiple process orders and product cost collectors.
    Is there any standard report or should I create a report painter report. I have tried to create a report painter report based on library 7KO, but target cost was not showing for selected order.
    Kindly suggest.
    Shirazi

    Target Costs are available in library 601 for internal orders (and can be used for process/production orders).
    Regards,
    Adrian

  • How to get the list of all process order which are settled?

    Hello Friends,
    Is there any  standard report available to get the list of all settled  Process Order or  Production order?
    Thanking all of you in advance.
    Regards,
    Jitendra

    Hi,
    You can the below standardreports for knowing the list of Settled Process Orders :
    1. Use Tcode : COOIS and in the selection fields provide the Process Order Type, Plant and System Status As " SETT" and execute the same . System will list all the Process Orders which were settled so far.
    2. Use Tcode : CO26 with selection fields as above.
    Hope this will suffice your reqt.
    Regards
    radhak mk

  • How to manage two quantity of two unit in process order?

    Hi  Guys
    In our plant, we have actived the catch weight management. For products A, we have set the standard conversion relation as follow: 1 EA (basic of unit)= 2.5 KG (production unit).
    But when I create the process order for products A, I only can input the quantity of production unit(1000KG) and the quantity of basic of unit cannot be inputted. It will be calculate by standard conversion relation. Now I want to create the process order by using two quantity of two unit(1100KG 400EA). Because we want to see the production plan by using two unit.
    Is there some method to do it?

    Hi,
    maintain the unit of conversion in Units of conversion in Material master in addition data..from PC to CAR..here base UOM is PC. CAR alternate UOM.
    Now in material master in work scheduling view maintain CAR as production Unit as shown below..
    Now when u create process order you will get like this..
    Thanks
    Kumar

  • Process order confirmation below tolerance limit, devation to be trigger to QA person

    Hi Team,
    Scenario is related with process order :
    While order confirmation , if we need to confirm process order below tolerance need deviation to be trigger which is approved by QA , allow order confirmation .
    How we can map the above scenario, so that deviation to be trigger to QA person for approval and than order confirmation is done.
    This is related with pharma company.
    Or Should we can map above process in other way.
    Thanks
    Vinu

    Hi Vinod,
    Is this o process order or Production order, if production order I suggest you to use the trigger point functionality, if process order u will need to go for user exit and some coding.
    Regards,
    Amol Kale.

  • IDOC: Process order: Message type LOIPRO

    Hi
    I would like to know here no other way to download LOIPRO idocs as soon as the process order or production order are created/changed.
    Currently i'm using program rcclord and rccltran to create idocs. The problem I see here is that during every execution ALL orders, disregarding of the status (i.e. closed orders as well), will be exported.
    G.
    Message was edited by: Giovanni Baumann

    Hi Baumann,
    You can use the BADI WORKORDER_UPDATE
    I am using this for releasing Process Orders. I hope this will help you..
    *Appending the Selection Screen fields.
    *Process Order
      s_rspar-selname = c_selnam1.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-aufnr.
      APPEND s_rspar TO t_rspar_tab.
    *Material Number
      s_rspar-selname = c_selnam2.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-matnr.
      APPEND s_rspar TO t_rspar_tab.
    *Planning plant
      s_rspar-selname = c_selnam3.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-werks.
      APPEND s_rspar TO t_rspar_tab.
    *Order category
      s_rspar-selname = c_selnam4.
      s_rspar-kind    = c_kindp.
      s_rspar-low     = im_ord_header-autyp.
      APPEND s_rspar TO t_rspar_tab.
    *MRP controller
      s_rspar-selname = c_selnam5.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-dispo.
      APPEND s_rspar TO t_rspar_tab.
    *Logical System
      SELECT  SINGLE rcvprn INTO v_opt_sys FROM edp13 "#EC *
       WHERE  rcvprt = c_rcvtype AND mestyp = c_messageid.
      s_rspar-selname = c_selnam6.
      s_rspar-kind    = c_kindp.
      s_rspar-low     = v_opt_sys.
      APPEND s_rspar TO t_rspar_tab.
    *Message Type
      s_rspar-selname = c_selnam7.
      s_rspar-kind    = c_kindp.
      s_rspar-low     = c_mesageid.
      APPEND s_rspar TO t_rspar_tab.
    *This statement will submit the programme RCCLORD using the table RSPARMS
    *which holds the fields to be filled in the selection screen for RCCLORD and return
      SUBMIT rcclord USING SELECTION-SCREEN 1000
                     WITH SELECTION-TABLE t_rspar_tab
                     AND RETURN.
    Cheers
    Prasad

Maybe you are looking for