Process Quota Arrangement

In SAP SRM 210 training material, page 334 (under main topic Unit 8: Sourcing), it is clearly stated that every requirement fitting a quota arrangement is sourced automatically by the system. But that did not happen in our system implementation (assuming standard SAP is used and no configuration needed). The picture captured in the training material SRM210, page 334 showed that, in Process Quota Arrangement, at Quota Arrangement item level, there are 3 columns in which values are updated. The value will be updated in the 3 columns after Purchase Order created with refer to quota based vendor selection. The 3 columns are Release Quantity, Current Percentage and Target Percentage. After PO created, system gives current release quantity and current percentage in the quota arrangement. However, in the real implementation, I did not see the column available for automatically update except the target percentage column. We want to see if the Quota Arrangement updates the column Release Quantity and Current Percentage but both columns are not updated. We use standard SAP-SRM7.0, but the result is not as the same in the SAP SRM210 training material, provided by SAP.
Anyone know the solution?

In SAP SRM 210 training material, page 334 (under main topic Unit 8: Sourcing), it is clearly stated that every requirement fitting a quota arrangement is sourced automatically by the system. But that did not happen in our system implementation (assuming standard SAP is used and no configuration needed). The picture captured in the training material SRM210, page 334 showed that, in Process Quota Arrangement, at Quota Arrangement item level, there are 3 columns in which values are updated. The value will be updated in the 3 columns after Purchase Order created with refer to quota based vendor selection. The 3 columns are Release Quantity, Current Percentage and Target Percentage. After PO created, system gives current release quantity and current percentage in the quota arrangement. However, in the real implementation, I did not see the column available for automatically update except the target percentage column. We want to see if the Quota Arrangement updates the column Release Quantity and Current Percentage but both columns are not updated. We use standard SAP-SRM7.0, but the result is not as the same in the SAP SRM210 training material, provided by SAP.
Anyone know the solution?

Similar Messages

  • Can someone pl explain Quota arrangement process in MM?

    Hi Folks,
    I am new to MM, could someone pl explain the quota arrangement steps step by step anything with screen would be very helpful
    for beginners like me with examples. 
    Also could some also pl tell me the Source priority in terms of Source of supply?
    Thanks.
    Steve

    Dear,
    Quota Arrangements :
    In simple words: Distributing the requirements quantity between potential source of suppliers (Vendors) - basing on their order fulfillment capacity.
    In business terminology:
    Quota arrangements allow you to define target percentages and distribute them between two or more purchasing contracts. A quota arrangement ensures that a contract is guaranteed both a minimum sales volume and a percentage of the total purchasing volume of the product category or product. A quota arrangement has the highest priority in the sourcing process.
    Quota Arrangements
    Quota Arrangements means a mechanism enabling the system to compute which source of supply to assign to a requirement for a material.
    If a material can be obtained from various sources of supply, each individual source of supply can be allocated a quota arrangement. The quota arrangement is valid for a certain period of time and specifies exactly how the receipts are to be distributed amongst each source of supply.
    We can set the quota arrangement for in-house production as well as for external procurement. Setting quotas permits the automatic apportionment of a total material requirement over a period to different sources.
    Sources of supply can be:
    - an individual vendor or outline agreement
    - another plant, from which material should be procured
    - a production version
    Quota Arrangement Usage
    The quota arrangement facilitates the determination of the applicable sources of supply for the following at a certain time.
    Purchase orders
    Scheduling agreement delivery schedules
    Planned orders
    Purchase requisitions
    Materials planning and control
    In customizing activity, we specify for each material master record which quota arrangement rule is allowed. We group the usage combinations you have chosen under different keys.
    We have to assign quota arrangement usage key to material master record in purchasing or MRP2 view (Maintaining Material Master Record T.Code MM01)
    The quota arrangement usage determines whether a material is included in a quota arrangement and which operations lead to a quota arrangement.
    We have to maintain the quota file for the material. Here we define the sequence of the sources of supply, the quotas per source of supply and numerous other parameters in the quota file.
    Maintaining the Quota File
    A quota arrangement file consists of quota arrangement records identifying the source (such as a vendor or an internal plant), the validity period, and the quota allocated to each source.
    We can maintain the quota file. Following are the steps for maintaining this file.
    T. Code: MEQ1
    The initial screen for maintaining quota appears.
    Enter the material number and the plant for the material that you want to use to maintain the quota file and choose. The header screen for maintaining quotas appears.
    Enter the Valid to date for the quota arrangement item.
    We can only define continuous validity periods for one material. In the first interval, the system sets the current date in the Valid from field. The Valid from dates of the other intervals are set continuously so that the day after the end date of the last quota item is set as the start date for the next item.
    If we want to work with splitting quota arrangements, we will enter a minimum quantity here.
    Double-click on the item to process.
    The item screen now appears.
    Here we will define the source of supply and other control parameters per item.
    Allocating the source of supply to the quota item determines the procurement type that the procurement proposal receives. Therefore, we can specify via the quota arrangement that, for example, 75% of a material is produced in-house and the other 25% is procured externally.
    Save entries.
    Regards,
    Syed Hussain.

  • Source determination,Quota Arrangement Process

    Hi,
    Plz tell me how to maintain Source determination,Quota Arrangement.step by step

    Dear,
    QUOTA ARRANGEMENTS
    If a quota arrangement exists for a material, it has the highest priority during source determination. Like source list, the quota arrangement facilitates the administration of sources of supply at plant level.
    If you procure a material from different suppliers, you can assign a quota to each individual supplier. A quota arrangement applies to a certain period and specifies how the receipts should be distributed among each source of supply.
    If a quota arrangement exists, this does not mean that the quantity of a single manually created purchase requisition is automatically apportioned among different sources. In such case, the entire quantity of the requisition is assigned to one source u2013 the source that is next in line receive the relevant order.
    Before you can maintain a quota arrangement item with the procurement type external procurement, a source of supply (info record and / or outline agreement) must exists.
    Create quota arrangement:
    LOGISTICS u2013MATERIAL MANAGEMENT u2013 PURCHASING u2013 MASTER DATA u2013 QUOTA ARRANGEMNET u2013 MAINTAIN.
    Specify number ranges for quota arrangement:
    SAP IMG u2013 MATERIAL MANAGEMENT u2013 PURCHASING u2013 QUOTA ARRANGEMENT u2013 DEFINE NUMBER RANGES.
    You must specify the business application for which quotation arrangement will be used, for example: in material planning or in purchase requisitions. You make this specification in QUOTA ARRANGEMENT USAGE filed, which is to be found in the plant-specific purchasing/materials planning data of the material master record.
    Set quota arrangement usage indicator:
    SAP IMG u2013 MATERIALS MANAGEMENT u2013 PURCHASING u2013 QUOTA ARRANGEMENT u2013 DEFINE QUOTA ARRANGEMENT USAGE.
    System assign quota rating to each source by calculation as u2013 Quota rating = (quota allocated quantity + quota base quantity / quota).
    ADDITIONAL ASPECTS OF SUPPLY SOURCE DETERMINATION
    Quota arrangements also can be source of supply.
    Quota arrangements for material requirements arising over a certain period divided up among different sources on basis of quota. Quota arrangements determine which source of supply is automatically assigned to a purchase requisition.
    SOURCE DETERMINATION
    The purpose of the source determination process is to automatically assign a source of supply to a purchase requisition, if source determination indicator set in the requisition header, the system searches for possible sources of supply for all the items of the requisition. Quota arrangements also can be source of supply.
    In source list specify a preferred source as fixed for a certain period, the system suggest just only this source, even if other potential sources exists.
    Quota arrangements for material requirements arising over a certain period divided up among different sources on basis of quota. Quota arrangements determine which source of supply is automatically assigned to a purchase requisition.
    Source list record consists of the following:
    1.Validity period u2013 Period of validity
    2.Key source data u2013 Number of vendor and responsible purchasing organization or number and item of outline agreement.
    3.Fixed source u2013 Within a validity period not more than one source should be flagged as fixed.
    4.Procurement plant u2013 if the materials can be procured from a plant or another point within your firm, enter the plant number in PPl field and leave the field for the vendor number empty.
    5.Blocked source u2013 To block a source. If you set Blocked indicator and enter only one validity period, the material is excluded from external procurement; that is, it cannot be ordered during this period.
    6.Material requirements planning  - You use MRP indicator to determine whether an automatic source determination process is carried out during the requirements planning run. The appropriate source is then automatically assigned to a purchase requisition, or scheduling agreement delivery schedule lines can be generated directly via planning run.
    If an attempt is made to order a material subject to a source list requirement from a source that is not included in the source list, the standard system issues an error message with the text: Source not included in list despite source list requirement. You can change this to warning message.
    If source list requirement defined for a plant, all materials in the plant level must be maintained with source list before procurement.
    Analyze source list:
    LOGISTICS u2013 MATERIAL MANAGEMNET u2013 PURCHASING u2013 MASTER DATA u2013 SOURCE LIST u2013 FOLLOW ON FUNCTIONS u2013 ANALYSE.
    Define source list requirement at plant level:
    SAP IMG u2013 MM u2013 PURCHSING u2013 SOURCE LIST u2013 DEFINE SOURCE LIST AT PLANT LEVEL.
    Source lists can be created:
    -Manually.
    -Create from within an outline agreement u2013 on outline agreement overview screen, select an item for which you wish to enter source list record and choose ITEM u2013 MAINTAIN SOURCE LIST.
    -Creation from with an info record u2013 you can enter vendor in the source list when creating or changing a purchasing info record. Choose EXTRAS u2013 SOURCE LIST. If the info record valid for entire purchase organization, you can create the source list for all plants of the organization in question. Choose the plant via GOTO u2013 PLANT.
    -Automatic u2013 can generate by system automatically.
    Create source list manually:
    LOGISTICS u2013 MATERIAL MANAGEMENT u2013 PURCHASING u2013 MASTER DATA u2013 SOURCE LIST u2013 MAINTAIN/DISPLAY.
    Generate source list automatically:
    LOGISTICS u2013 MATERIAL MANAGEMENT u2013 PURCHASING u2013 MASTER DATA u2013 SOURCE LIST u2013 FOLOW ON FUNCTIONS u2013 GENERATE.
    Regards,
    Syed Hussain

  • Assign Source of Supply User Exit with Quota Arrangements in ME57 and ME56

    Hi there,
    We are using Quota Arrangements to define Vendor rebate levels and we have enabled User Exit EXIT_SAPLMEQR_001 to provide a more informative popup to replace standard Source of Supply popup as need to display current allocation quantities and % allocation fulfiled.
    This User Exit is invoked during Assign Source of Supply during PReq processing (More precisely during Assign Source of Supply in ME51n and Automatic Source of Supply in ME57 and ME56) which all works fine.
    When used in ME51n and Source of Supply Assigned and PReq saved, the allocated quantity against the valid Quota Arrangement (EQUK-QUMNG) is successfully updated with the relevant amount
    When using ME56 or ME57 to Automatically Assign source of Supply via the PReq list, the User Exit is invoked correctly and on selecting Vendor and saving the PReq is update correctly, however the allocated quantity against the valid Quota Arrangement (EQUK-QUMNG) is NOT updated with the relevant amount
    I have searched SAP Notes and debuged with limited success but cannot find evidence as to why this difference is happening - I assume that it has something to do with User Exit but any advice gratefully received if anyone else has experienced this issue?
    Ben

    Hello Jerry,
    source will be determine based on the following points:
    Outline Agreement
    Info record
    Quota Arrangement
    Source List
    For more information, <a href="http://help.sap.com/saphelp_47x200/helpdata/en/75/ee11b255c811d189900000e8322d00/content.htm">Click here</a>
    Hope this helps.
    Regards
    Arif Mansuri

  • Subcon Quota Arrangement behavior during MRP

    Dear Gurus,
    Currently, we have a scenario wherein during subcon process there can be 3 Vendors active. During MRP, we would like to have an output as per below:
    Requirement: 1500
    Vendor A: capacity 500 - priority 1
    Vendor B: capacity 700 - priority 2
    Vencor C: capacity 500 - priority 3
    If I run MRP, I would like system to have PR's Vendor A with 500 then as the Vendors capacity is only 500 the remaining requirement should be passed on the succeding vendors. So from my example, Vendor B should have 700 and Vendor C should have 300.
    Is this possible using Quota Arrangement. I was trying to test but I cannot get my desired result.
    Please note that the settings in the material master is already set to Quota usage 4 and the lotsize is weekly with splitting quota activated.
    Thanks,
    Raymond
    Edited by: Raymond on Oct 10, 2011 11:17 AM

    Hi,
    Yes I have maintained below in MEQ1 just for testing but I cannot get the desired result:
                      Quota Percentage        Maximum Lot size      Priority
    Vendor A:   100                                 500                           1
    Vendor B:    100                                 700                          2
    Vendor C:                                           500                          3
    Set-up Weekly lotsize with splitting quota and quota usage 4.
    But during MRP execution, I think the system splits the requirement quantity into 2 and distribute to Vendor A and Vendor B then if it reached maximum lotsize it proposed to vendor C.
    our requirement is first to consider Vendor A then Vendor B then Vendor C according to maximum lot size and priority.
    Any idea if this is possible?
    Thanks,
    Raymond

  • Uploading of Quota arrangement using LSMW

    Dear Members,
    I want to upload Quota arrangement using LSMW.
    Pl advise.
    Thanks & Regards,
    Sanjay Kohli

    I am trying to upload quota arrangement using IDOC method, since there is no Standard/Batch Input Method as well as Bussiness object method available for it.
    I am not using Batch input recording method since no of vendors will varies depending on the plant & material comination.
    I am unable to load it using IDOC as I not able to identify process code for I DOC message Type LIPEQU.
    I slhall be thakful in case you can provide the same or alternative method to upload Quota arrangement in addition to Batch Input recording.
    Regards,
    Sanjay Kohli

  • Quota Arrangment

    Dear All,
    Can anybody define me the process of quota arrangement & its advantages.
    How i can map it befor/after the MRP is carried out .
    Regards,
    Gs Kothari

    Hi
    Quota arrangements allow you to define target percentages and distribute them between two or more purchasing contracts. A quota arrangement ensures that a contract is guaranteed both a minimum sales volume and a percentage of the total purchasing volume of the product category or product. A quota arrangement has the highest priority in the sourcing process.
    MEQ1                 Maintain Quota Arrangement                       
    MEQ3                 Display Quota Arrangement                        
    MEQ4                 Changes to Quota Arrangement                     
    MEQ6                 Analyze Quota Arrangement                        
    MEQ7                 Reorganize Quota Arrangement                     
    MEQ8                 Monitor Quota Arrangements                       
    MEQB                 Revise Quota Arrangement                         
    MEQM                 Quota Arrangement for Material
    http://erp.esworkplace.sap.com/socoview(bD1lbiZjPTgwMCZkPW1pbg==)/smdisplay.asp?id=E64A991AB88A479F95A733847345FE05&fragID=&packageid=DBBB6D8AA3B382F191E0000F20F64781&iv=

  • Scheduling Agreement and Quota arrangement

    Dear all,
    Kindly share with me the individual steps involved in in creating Scheduling Agreement as well as Quota arrangement procurement process with T.Codes and also the relevant configurations involved.
    Thanks a lot.

    Hi,
    Here is all about Quota arrangement :
    Following are the configurations.
    1) To specify number range for quota arrangement
    SPRO > IMG > MM > Purchasing> Quota arrangement> Define number range (Int or Ext)
    2) Set Quota arrangement usage indicator:
    SPRO > IMG > MM > Purchasing> Quota arrangement> Define quota arrangement usage
    On Application side following are the prerequisites
    1) Create Quota arrangement
    SAP Menu> Logistic> MM > Purchasing> Master Data> Quota arrangement > Maintain
    2)specify procurement type : Int / Ext
    3)Where appropriate specify the special procurement type For ex stock transfer
    4) Enter the vendor or supplying plant
    5) Specify the quota you want to assign to this source
    Please understand terms as below,
    Quota Rating = Quota allocated Qty +Quota Base Qty /Quota
    Quota Base Qty: Quantity used for manual control of the quota Arrangement (For example new source is included)
    Quota: Number that determines how requirement are apportioned among various sources .Decided by a Purchasing people based on confidence on source.
    I source determination source with lowest quota arrangement will always be assigned
    Example
    Source Quota    allocated Qty      Quota Rating
    M             1                   100                     100
    N              2                   150                     75
    O             3                     75                      25 *
    In above case vendor O will be assigned as low Rating *
    Now quota Base Qty will come into picture when new supplier is introduced. As you have seen that vendor with low quota Rating is assigned .In case of new supplier as no allocated qty earlier its Quota rating will always be low & all Qty will be allocated to him. To prevent this Base qty is added to allocated Qty so that accordingly it will determined accordingly
    If Quota base Qty is 100   & quota is 2
    For new vendor X rating will be
    Quota rating = 100 + 0 / 2 = 50
    I hope this gives you entire clarity.
    Vivek

  • Quota arrangement

    Hi
    My requirement is if we want to procure material of 1000 kgs . It need to be distributed 50% of the order between two vendors.
    I came to know that this can be done through Quota arrangement.
    Could you please guide how system generates 2 orders for this one requirement for  2 vendors and what quota arrangement settings needed..
    Please explain me step by step procedure since I dont know abt this process
    Thanks
    Jupudi

    Hi,
    You can maintain following fields -
    1) Initial Screen - Material / Plant
    2) Overview - Valid to / Minimum quantity above which the splitting will happen
    3) Select line & then go to Item
    4) Item Level -
         QAI - Blank
         P - Procurement type
         S - Special procurement type
         Vendor - Vendor Code
         PPI - Own manufacturing plant, if material is to be procured from in house
         Maximum Qty - Maximum qty, after which the quota arrangement is not valid
         Max. / Min. Lot Size - Maximum or minimum lots size for PRs
         Rounding Profile - Same as material master
         1x - Check if the vendor is to be considered only once during single MRP run
         Maximum Release Qty - Maximum quantity, which a vendor can supply during given time frame (for example - 1 Week / 1 Month)
         N / P - Specify time frame which applies to maximum release qty.
    Hope this helps
    Regards,
    Prashant

  • Quota Arrangement in LTP

    Hi Gurus
    In LTP Business Process my requirement is like this
    1) One Fert Material Contains one ROH in BOM of Qt1
    2) The ROH contains 2 vendors
    3) I want to give the quta of ROH in 40% and 60%
    SO in LTP i need 2 planned orders for ROH even if i my requirment for Fert is single
    Pl explain me the settings required for the same
    K.Prabakaran

    Hi,
    In MEQ1 , pls check the foll.
    1. Min Qty splitting - the minimum quantity that a lot must have in order to be apportioned among several sources of supply in the planning run.
    Check whether order qty is more than this min qty.
    2. Also check the valid from and to dates.
    Allocation by quota using splitting quotas is only carried out via a requirement planning run, subject to the following preconditions:
    Through the appropriate entry in the field Quota arrangement usage (on the MRP data screen 2 or Purchasing screen) it must have been specified that a quota arrangement is to be applied in the planning run.
    Regards,
    Sheik
    The indicator for the splitting quota must be set for the the lot-sizing procedure used for materials planning purposes in Customizing.

  • Error with LSMW IDOC method while maintaining Quota arrangement

    Hi
    I am trying to create LSMW using IDOC method for maintaining quota Arrangment.
    I used the standard Message type LPIEQU. Idoc is getting generated and when i tried to process this IDOC i am getting error "Function module not allowed: BAPI_IDOC_INPUT1".
    I used the process code as "BAPI" in message type LPIEQU configuration in WE20.
    If anyone faced this issue please let me know the reason for the error.
    sakthi.K

    see OSS Note 198252 - Special features of POI message category LOI*
    The message categories named are part of the POI (Production Optimization interface) interface.This interface and the message categories contained in it were developed for the transfer to non-R/3 systems.Therefore, an inbound processing in the R/3 system is not planned.

  • KANBAN with Quota arrangement

    Dear Guru,
    Ist possible to use Quota arrangement in KANBAN external Procurement (Scheduling Agreement)?
    If so, please advice me how to do it... i am new to KANBAN.
    Regards,
    Senthil

    Hi Kumara,
    As per my knowledge Quota Arrangement is not possible to use in KANBAN with Schedulling Agreement.
    However pls find below the process steps for KANBAN WITH SCHEDULING AGREEMENT:
    You can carry out KANBAN with Replenishment Strategy- External Procurement in following two ways :
    1.     External procurement from Vendor to Main Stores:
    Basic rules and Prerequisites:
    u2022     MRP type should be u2018NDu2019 in MRP1 view of material master.
    u2022     Availability check should be u201CKPu201D in MRP3 view of material master.
    u2022     Material received from vendor is directly posted to unrestricted stock. Inspection at vendors place or vendoru2019s process control to ensure rejection free material. Inspection set up in Material master should be inactive.
    u2022     Backflush is not required and Material is issued against a Pick List for Production Order.
    Process steps:
    1.     Create supply area for Main stores. TC: PK05
    2.     If required, extend the material to main storage location. TC: MMSC
    3.     Make the necessary changes in the material master as explained above.
    4.     Create scheduling agreement. Put kanban indicator (X) in the additional data of item.
    5.     Create Kanban control cycle. TC:PKMC
    6.     Print the barcode. TC:PK17
    7.     Set the kanban status to EMPTY by scanning the barcode. TC: PKBC. A Schedule line will be generated for the supply of material to main stores.
    8.     View the demand source view. TC: PK13n
    9.     When the material is received at Gate, perform goods receipt into blocked stock (movement type 103). TC: MIGO
    10.     Once the material reaches Main stores scan the barcode to FULL. TC: PKBC (At the background GR with 105 movement will happen).
    2.     External procurement from Vendor directly to shop:
    Basic rules and Prerequisites:
    u2022     MRP type should be u2018NDu2019 in MRP1 view of material master.
    u2022     Availability check should be u201CKPu201D in MRP3 view of material master.
    u2022     Backflush indicator is must. It can be defined in the routing or in the material master itself. If Backflush indicator is set in the material master, then the material will be backflushed through out the plant (Material issue not required against production order). However if you want the material to be backflushed only when it is used for certain products, then Backflush indicator should be set in the routing ( in the component allocation against operations).
    u2022     Confirmation should be done for each operation in the production order either individually (CO11n) or collectively (CO15). Confirmation posts goods issue of components (relevant to confirmed operation/s) to production order
    u2022     Maintain KN01 storage location in the field - production storage location of MRP2 view in the material master. Back flushing will take place from this location. Field - Storage location for external procurement should be KN01 in the material master.
    u2022     Material received from vendor is directly posted to unrestricted stock. Inspection at vendors place or vendoru2019s process control to ensure rejection free material. Inspection set up in Material master should be inactive.
    Process steps:
    1.     Create supply area for kanban stores (KN01). TC: PK05
    2.     Extend the material to Kanban storage location. TC: MMSC
    3.     Make the necessary changes in the material master as explained above.
    4.     Create scheduling agreement. Put kanban indicator (X) in the additional data of item.
    5.     Create Kanban control cycle. TC:PKMC
    6.     Print the barcode. TC:PK17
    7.     Set the kanban status to EMPTY by scanning the barcode. TC: PKBC. A Schedule line will be generated for the supply of material to kanban store.
    8.     View the demand source view. TC: PK13n
    9.     When the material is received at Gate, perform goods receipt into blocked stock (movement type 103). TC: MIGO
    10.     Once the material reaches shop, scan the barcode to FULL. TC: PKBC (At the background GR with 105 movement will happen).
    Hope this helps.
    Revert if any doubt and reward points if useful.
    Regards,
    Tejas

  • What are the config steps for contract mass change and quota arrangement?

    Hi friends
    what are the config steps for contract mass change and quota arrangement?
    Regards
    Raj Kumar

    Process Flow
    The mass change process consists of four steps. You navigate between these steps by choosing the Next and Back buttons located at the bottom right-hand corner of the screens.
           1.      Search for contracts
    You search for and select the contracts or the contract hierarchy that you want to change.
    Contracts that have the status Closed cannot be changed.
           2.      Define mass changes
    You specify the changes you want to make.
    You make changes at header data level and at item data level by choosing the relevant change methods. A green tick appears next to each change parameter so that you can see where changes are already active.
    Once you enter this step, the documents you have selected to be changed are locked so that other users cannot make changes to them until you are finished with this process.
           3.      Simulate mass changes
    Here you can perform a trial run of your mass changes. This simulation step is optional.
    We recommend that you perform this step so that you can check how the change methods you have chosen will be processed by the system.
    You receive status messages about the change methods for each contract and can quickly see whether any errors arise in connection with the proposed changes at this stage. From this step, it is easier for you to go back and correct the error than after applying the changes.
    Background processing
    The system processes the changes in the background.
    If there are a large number of contracts to be processed, this step could take some time to complete. In this case, you can leave the transaction so that you can, for example, carry out other tasks in the meantime.
    The system sends you an e-mail once the simulation step is complete. The e-mail contains a link to the relevant screen in the application so that you can return to it when it is convenient for you to do so. If you have left the SRM application, you can only return via this link.
    Here you can see the status of the changes and, if necessary, you can correct any errors by going back to the Define mass changes step.
    The messages that you receive in the simulation step are not confirmation that a change has been performed. They simulate the messages you get after you apply the changes. You must complete the final step of the mass change process and apply the changes before they take effect.
           4.      Carry out mass changes
    Here you apply the changes to the contracts.
    You cannot reverse this step, which is why we advise you to perform the simulation step beforehand.

  • SCM Quota Arrangement Data transfer

    i am trying to do BDC recording for Quota arrangement header data (/SAPAPO/SCC_TQ1). while processing the recording (SM35) i am not able to get the subscreen in order to fill the header level details.
    Here is my recoding data:
    perform bdc_dynpro      using '/SAPAPO/SAPLOO_TR_QUOTA' '0010'.
    perform bdc_field       using 'BDC_CURSOR'
                                  '/SAPAPO/S_TRQTASEL-LOCNO'.
    perform bdc_field       using 'BDC_OKCODE'
                                  '=CHANGE'.
    perform bdc_field       using '/SAPAPO/S_TRQTASEL-MODEL'
                                  WA_TAB1-MODEL.
    perform bdc_field       using '/SAPAPO/S_TRQTASEL-LOCNO'
                                  WA_TAB1-LOCATION.
    perform bdc_field       using '/SAPAPO/S_TRQTASEL-VERSINDEP'
                                  'X'.
    perform bdc_field       using '/SAPAPO/S_TRQTASEL-QTDIRI'
                                  'X'.
    perform bdc_dynpro      using '/SAPAPO/SAPLOO_TR_QUOTA' '0100'.
    perform bdc_field       using 'BDC_OKCODE'
                                  '=%_GC 118 10'.
    perform bdc_dynpro      using '/SAPAPO/SAPLOO_TR_QUOTA' '0100'.
    perform bdc_field       using 'BDC_OKCODE'
                                  '=0121_OK'.
    *perform bdc_field       using 'BDC_CURSOR'
    *                              '/SAPAPO/S_TRQTAHALVIO-DVALTO'.
    perform bdc_field       using 'BDC_SUBSCR'
                                  '/SAPAPO/SAPLOO_TR_QUOTA 0121DETAIL'.
    perform bdc_field       using 'BDC_CURSOR'
                                  '/SAPAPO/S_TRQTAHALVIO-DVALTO'.
    perform bdc_field       using 'GS_0121-MAT_SINGLE'
                                  'X'.
    perform bdc_field       using '/SAPAPO/S_TRQTAHALVIO-MATNR'
                                  WA_TAB1-PRODUCT.
    perform bdc_field       using '/SAPAPO/S_TRQTAHALVIO-DVALFR'
                                  WA_TAB1-S_DATE.
    perform bdc_field       using '/SAPAPO/S_TRQTAHALVIO-DVALTO'
                                  WA_TAB1-E_DATE.
    perform bdc_dynpro      using '/SAPAPO/SAPLOO_TR_QUOTA' '0100'.
    perform bdc_field       using 'BDC_OKCODE'
                                  '=SAVE'.
    I have tried Bapi method also for the same
    Business object: BUS10009
    Method: SAVEMULTIPLE2
    But the data is not getting posted.
    Please give your inputs on the same.
    Regards,
    Avijit Khajanchi.

    Hi,
        check with Function module ME_UPDATE_QUOTA in function group MEQU.
    Thanks,
    Asit Purbey.

  • Quota arrangement - winning contract is not auto assign in SC

    My Problem: Winning contract is not auto assign to Shopping cart
    I created a Quota Arrangement (QA). It contains 2
    contracts, for example in line item 1, contain Contract with Supplier
    'A', with target percentage of 60%. In line item 2, contain Contract with
    Supplier 'B', with target percentage of 40%. I did not specify any quotabase quantity.
    For your info, the contract for Supplier 'A" is a Purchasing Contract,
    with target value of 80 (currency Malaysian Ringgit). Contract for
    Supplier 'B' has target value of 20 (currency Malaysian Ringgit). When Icreate a Shopping Cart, with quantity 5 (each-EA) and price per unit is
    2
    (Malaysian Ringgit), total is MYR10. When I go to Source of Supply tab,
    the system showed 2 suppliers from the 2 contracts. It did not
    automatically assigned to the winning contract. We still have to choose
    which contract to be assigned. I created another SC after that until theContract exceeded quantity, but the system does not proposed winning
    contract automatically. Please help.
    Cheers
    AIN

    yes, the contract have company code