Hi, there seems to be a lot of posts out there regarding this topic, but I can't seem to get a specific answer out of it all?
I am adding a new R3 Source System (R2) to my BI System in addition to the existing R3 Source System (R1).  I would like all of my BI Objects to have the same connections (Transformations, etc.) to my new R3 Source System (R2) that I currently have for my R1. 
What do I have to do to make this happen?  Is there a defined process for this?
Do I have to manually copy the transformations for everything? (This would be sooo difficult due to volume)
Please add clarity to this situation if you can...
Thanks!

Hi,
take a look:
Fresh source system clients in production BW system
Fresh source system clients in production BW system
Threads are about fresh source system clients but maybe they are useful for you.
Additional:
Change Source System
Copy Transfer Rules
This doesn't seem like an uncommon scenario. Surely I don't have to manually recreate all of these datasource transformations?
In my mind you have to recreate if you are not using standard BI Content which you only have to activate.
Regards
Andreas

Similar Messages

  • Process chain too slow in source system .

    Good morning
    during a process chain from BW 3.0B to a source system R3 46C i've seen that sometimes it goes very slow also with few data to load.
    Here is the log of a BIREQU_* in R3 system:
    29.10.2008 03:07:29 Job started                                                                        
    29.10.2008 03:07:29 Step 001 started (program SBIE0001, variant &0000000370248, user name ALEDABWP)    
    29.10.2008 03:07:30 Asynchronous sending of InfoIDOCs 2 in task 0001 (0 parallel tasks)                
    29.10.2008 03:07:30 DATASOURCE = ZYIFB_STATO_RICHIESTE_URGENTI                                         
    29.10.2008 03:07:30 *************************************************************************          
    29.10.2008 03:07:30 *           Current values of selected profile parameter                *          
    29.10.2008 03:07:30 *************************************************************************          
    29.10.2008 03:07:30 * abap/heap_area_nondia......... 2000000000                              *         
    29.10.2008 03:07:30 * abap/heap_area_total.......... 2000000000                              *         
    29.10.2008 03:07:30 * abap/heaplimit................ 100663296                               *         
    29.10.2008 03:07:30 * zcsa/installed_languages...... DEI                                     *         
    29.10.2008 03:07:30 * zcsa/system_language.......... I                                       *         
    29.10.2008 03:07:30 * ztta/max_memreq_MB............ 256                                     *         
    29.10.2008 03:07:30 * ztta/roll_area................ 6500000                                 *         
    29.10.2008 03:07:30 * ztta/roll_extension........... 3000000000                              *         
    29.10.2008 03:07:30 *************************************************************************          
    *29.10.2008 03:07:30 1 LUWs confirmed and 1 LUWs to be eletedwithFBSC2QOUT_CONFIRM_DATA*_           
    *29.10.2008 07:20:00 Call up of customer enhancement BWBTE_CALL_BW204010_E (BTE) with 4.330 records*_    
    29.10.2008 07:20:00 Result of customer enhancement: 4.330 records                                      
    29.10.2008 07:20:00 Call up of customer enhancement EXIT_SAPLRSAP_001 (CMOD) with 4.330 records        
    29.10.2008 07:20:00 Result of customer enhancement: 4.330 records                                      
    29.10.2008 07:20:01 Asynchronous sending of data package 1 in task 0002 (1 parallel tasks)             
    29.10.2008 07:20:01 IDOC: InfoIDOC 2, IDOC no. 270934742, duration 00:00:00                            
    29.10.2008 07:20:01 IDOC: Begin 29.10.2008 03:07:30, end 29.10.2008 03:07:30                           
    29.10.2008 07:20:02 Through selection conditions, 0 records filtered out in total                      
    29.10.2008 07:20:02 Asynchronous sending of InfoIDOCs 3 in task 0003 (1 parallel tasks)                
    29.10.2008 07:20:02 IDOC: InfoIDOC 3, IDOC no. 271010440, duration 00:00:00                            
    29.10.2008 07:20:02 IDOC: Begin 29.10.2008 07:20:02, end 29.10.2008 07:20:02                           
    29.10.2008 07:20:07 tRFC: Data package 1, TID = C0A800031827490800917395, duration 00:00:06, ARFCSTATE =
    29.10.2008 07:20:07 tRFC: Begin 29.10.2008 07:20:01, end 29.10.2008 07:20:07                           
    29.10.2008 07:20:07 Synchronous sending of InfoIDOCs 4 (0 parallel tasks)                              
    29.10.2008 07:20:07 IDOC: InfoIDOC 4, IDOC no. 271010441, duration 00:00:00                            
    The strange thing is the time gap form 3 to 7:20. what could be the problem?
    Thanks
    Nick
    Edited by: Nicola Blasi on Oct 29, 2008 11:28 AM

    Hi,
    Check any exits are there in DataSource and where the data is picking whether the code is working fine or not.
    Thanks
    Reddy

  • Processing error occured in the source system

    Hi Experts,
    I am extracting payroll data from ECC 5.0 to BW side, after the extraction I'm getting warning message proceesing error in the source system.
    In the source system apllication log the following warning message displyed.
    <u>No assignment of payroll data to BW month for country grouping 99</u>.
    I checked at BW side the data was available in the PSA and Data Target, but the status was in YELLOW for long.
    If any one come accross this , please provide good inputs....
    Thanks & Regards
    Kumar

    I have the same problem.
    The following text is ment to help me.
    Havent solved it yet, but explects to find the activity 'Assigning the Payroll Data to BW Month' in spro.
    best regards
    Ingrid
    Message no. HR_BW_PY99026 Assigning the Payroll Data to BW Month.
    Diagnosis
    No assignment is specified for country grouping 20 in the Customizing activity "Assigning the Payroll Data to BW Month".
    System Response
    The SAP standard "End Date of For-Period" is used for this country grouping.
    Procedure
    Enter an assignment for the country grouping in Customizing the DataSource 0HR_PY_1.
    Choose: R/3 Customizing Implementation Guide -> Integration with Other SAP Components -> Business Information Warehouse -> Settings for Application-Specific DataSources -> Human Resources -> Assigning Payroll Data to a BW Month.

  • Trying to setup new iCloud in system preferences and get error message: "iCloud encountered an error while trying to connect to the server."

    Here's the sequence of events:
    Setting up a new iMac.
    Migration Assistant was aborted during setup and a normal setup was completed.
    Then ran Migration Assistant from the newly setup account.
    It ran fine, but put all the data in a new account called "user".
    Renamed "user" to a new name, renamed the home folder to a new name following these instructions: OS X: How to change your account name or home directory name
    Delete the account we originally created, so just have one account with the name we want and all the data, email. Works fine.
    Sign into the App Store with the account we share for purchases.
    Now, the problem:
    Go to System Preferences to setup iCloud with a new Apple ID
    Get this error: "iCloud encountered an error while trying to connect to the server."
    So I'm unable to setup iCloud for photo stream, FaceTime, etc.
    Internet works fine, we can get mail, etc.
    Rebooting doesn't help
    Ideas?

    never mind the problem is gone this morning.

  • Error for setuping 2lis_02_scl in source system

    Hi ,Guy ,
         I used the datasource 2lis_02_scl to get the purchase data . i did the setup using one purchase order no(of course I deleted the setup table before did it). when checked the data by RSA3 , I found the system generated mass data(2400 records) .actually my purchase relevant data are as follows: 21 reordes of order item ,78 reocords of order schedule item ,158 records for order history ,and they have no more change after created . I don't know
    why 2400 relevant records in my setup table .
      Can anybody come across same problem ?thanks in advance .
    Jialiang.Qiu

    Hi,
    One reasonmay be the records will split in the systesm I'll tell one example.
    Just 2 days back I tested for 2lis_12_vcitm, one record is created in ECC and then I tested it in RSA3 I got 3 records (it won't include shipment), but the data will match with ECC (ECC Vs BW), so in that way there may be some splittings will happen.
    Just take one order no and check you come to know that how the data is splitting.
    Thanks
    Reddy

  • Transport InfoSources to New Source System

    Hi.
    When implementing BW in our QA environment, all InfoSources, and their related InfoPackages, Transfer Rules, Update Rules, etc.) were created using a temporary R3 QAS source system mapping (ex.TMP).  We are now removing this temporary client and  I now need to change my InfoSources (along with customized Start Routines, InfoPackages, etc.) to point to a new QAS source system (ex. PRM). 
    Note that this new source system is already identified as a source system for BW and all DataSources created on TMP have been transported to PRM.  Subsequently, all DataSources have been replicated from PRM to BW. 
    However, I'm having trouble on the BW end.  I can't easily
    transfer the InfoSources, etc. to the new source system.  I've asked some BW / Basis folks and they suggest transporting the InfoPackages out-of and then back-into the BW QA client.  Is this possible?  Is there a better way to push my InfoSources, InfoPackages, etc. from the old source client (TMP) to the new one (PRM)?  Thanks!

    Dear Dave
    Please do not attempt to change the logical system name your self, as I feel that you have not tried it before.
    This is some thing that your basis people have to do. Depending on the size of database this change can take from 2-24 hours (not exact times, but just some thing to show the magnitude of the task).
    Good luck
    /FZA
    Message was edited by: Fariborz Zangoui

  • We would like to test old deltas from the source system( copied to new)

    Hi Gurus,
    The scenario is
    They will make a DB copy of the Prod system onto a QA system, the Copied system will have
    its system ID changed(SID) to a new one.
    There will be deltas available in the RSA7, as this is a copy of the  3 weeks old prod
    system. Now the delta's will be available on the Copied system pointing to the BW Prod system.
    We would like to test these delta's to BW Dev. why we would like to do the delta's to the
    BW dev system is to check whether we can do system copies without clearing the delta's on
    the source system.
    After the system copy we will do all the activities necessary to reflect the system changes
    a. Like BDLS, We20, we21,ALE checks, RFCDES, RSLOGSYSDEST, RSBASIDOC, etc on the source system to
    reflect the changes of the BW Prod system to BW Dev system.
    b. Likewise, we will perform all the above activities on the BW dev system by changing the
    existing source system to the new source system( performing BDLS,we0, we21, etc)to reflect
    the new Source system with the new (SID).
    c. We will check the source system connection
    d. Replicate the datasources on the new source system
    e. Activate the Transfer rules for the new source system.
    Now for us to do delta's from the new source system to the Bw dev system we need to change
    underlying tables in source system to point the delta's, arfc TID's etc to the BW dev system.
    We can change the entries in the TRFCQOUT, ARFCCSTATE, ARFCDATA tables to point the LUW's and
    destination to the BW dev system.
    What I presume is if we run the BDLS on the Copied system to change the BW prod system to BW
    and also  the underlying Tables for the LUW's and etc will still be pointing to BW Dev. I would
    like to know if this is the case .
    Lastly, appreciate if anyone can say if this is possible to do without having to clear the
    BW delta queue on the source system.

    Hi Ramesh,
    Appreciate a lot for your response, but i would like to know if we can reflect the entries in table RSSDLINIT(Last Valid Initializations to an OLTP Source) and RSSDLINITSEL(Last Valid Initializations to an OLTP Source)  in the BW system on the copied source system
    tables ROOSPRMSC(Control Parameter Per DataSource Channel), ROOSPRMSF(Control Parameter Per DataSource Channel) by executing the ABAP program RSSM_OLTP_INIT_DELTA_UPDATE after we do the BDLS conversion on the new copied source system.
    After the BDLS conversion I reckon the entries in the RSA7 queue, ARFCCSTATE, TRFCQOUT tables willl reflect the BW Development system instead of the BW Production system isnt it.
    response much appreciated.
    Kalyan

  • New source system for HR extractors - easy way to change source system?

    Hi
    Our HR module is going to be seperated from the ECC module and thereby placed on a new server and have its own source system.
    In BI we have to handle this as well so that all 7.0 transformations and 3.5 transferrules etc. have to be mapped to the new HR source system. It there a smart way to do that and how would you do it?
    Thanks and kind regards,
    Torben

    Hi Dhanjayan
    Thanks for your reply.
    That would be an option to collect all source system dependent objects in a transport, however by doing that we will also collect objects for all the other areas than HR and it will therefore be a huge task to remove non HR related objects.

  • Source System Conversion in Remote Process Chain

    Hi all!
    I' working with BI7 SP12 and facing the following problem:
    <b>There is no source system conversion for Remote Process Chains, when transporting Process Chains with Remote Process Chains from DEV to QA.</b>
    First the following warning appears:
    DEV-Destination of Remote Process Chain does not exist on QA-System.
    ==> The is correct because the DEV-Destination should have been converted to QA-Destination.
    Then the following error appears:
    Process Chain with the Remote Process Chain was not succesfully checked.
    <b>All source system conversion tables are maintained correctly!</b>
    The source system conversion works for example for InfoPackages correctly.
    But for Remote Process Chain there is neither source system conversion for the Destination nor for Callback Destination. Both should be converted.
    Do I have to do it manually??
    Or do I have to create the DEV-Destination in SM59 on the QA-System??
    ==> We want to avoid this...
    Thanks for any ideas...
    kj

    Please note:
    When I create the DEV-Destination in SM59 on the QA-System,
    the transport gets no warnings and no errors...
    But there is still no conversion of the source systems for the Destination and the Callback Destination of the Remote Process Chain to QA-Destinations...
    So, i think:
    There is no automatic source system conversion of Remote Process Chains and I have to adjust it manually in the QA-System...

  • Bw extraction process starting after a process/job in source system

    Hello gurus,
    I want to start a extraction process (a chain process) in BW system after a background program (job background process) has finished in the source system (which is an R/3 system).
    My solution sound like this: I make a RFC function in BW that start the event XX, and planning the process chain to start at event XX (all this in BW side).
    In source system I call the RFC function when the desired background process has finish.
    I look for another solution (more simple maybe) for my task, or for any another suggestion.
    thanks

    Hi,
    Refer the note :135637
    (1) Create an event in the BW system
    Define a system event (for example SAP_BW_TRIGGER) with Transaction SM62.
    (2) Create a function module in the BW system
    Create a function module (for example Z_BW_EVENT_RAISE) with the help of Transaction SE37. For the source code refer to the attachment of this note.
    (3) Use the below code in code of the triggered job  in the R/3 System.Here BIMCLNT000 is the logical system name of the BI system. you need to cange it to yours.
    parameters: rfcdest like rfcdisplay-rfcdest default 'BIMCLNT000'.
    call function 'Z_BW_EVENT_RAISE'
      destination rfcdest
      exporting
          eventid = 'SAP_BW_TRIGGER'.
    Regards,
    Anil Kumar Sharma .P

  • Urgent Issue - Copy DTP and Process Chains in New Client Instance

    We have created new client Instance ( CLNT 510 ) based on our present client ( CLNT 500 ).
    We have all the process changes, application components from source system CLNT 500 and data ( both for master and transaction data ) in place for the CLNT 500.
    Now we need to use the CLNT 510 for our futher development. RFC connection has been established.
    Just want to know, do we need to create all the Application component trasfer , Transformation, DTP , Infopackages , Process chains again for the CLNT 510 data.
    please help.
    Thanks and Kind Regards,
    Pratap Gade.

    Hello Jr Roberto,
    Hello Jr Roberto,
    We have company implementing mutiple SAP Implementations in different countries.
    Client for BW Dev is 400.
    Source system for Client BWD :
    ECC Client ERP Dev - 500 ( for Holland Implementation )
    ECC Client EPR Dev - 510 ( for German Implementation  - Instance of ECC 500)
    We are completed with the Client 500 implementation.
    We are starting the german implementation and they have created a intance of Holland ECC Dev client 500 for german implementation with german data.
    Now they have setup 2 rfc connection in BWD 400.
    Also finally when they move to QAS client they are going to integrate the data of the both countries into one client.
    Presenlty I need to use ECC client 510 client for our german development.
    We have around 40 SAP BI reports in our first implementation. and around 10 in our second implementation.
    Just want to know, what are issues to be considered in loading master data ( will it overwrite the master data from the client 500, if i extract the master data from client 510 )...and all the other issues like can I copy all the process chains...etc  from client ECC 500 to ECC 510, without creating all transformation, DTP , Infopackages to load all the master from client 510 again.
    I need a broad understand on how to go about the development ...starting with Application Components transfer from source system Client 510 ....to report development. ( if possible using the already created objects....infopackages , DTP etc..)
    your help would be really appricated Mr Roberto.
    Thanks and Kind Regards,
    Shekar.

  • How to transport source system dependent objects

    Hi everybody,
    I've read several questions about how to transport source dependent objects between systems and I still don't get whole picture
    say I have BWDEV attached to R3DEV and
               BWQA attached to R3QA
    and I want to transport transfer rules from BWDEV to BWQA
    1) should I create, by hand, the source system R3QA in BWQA and replicate its datasources in the first place?
    2) or it has to be transported from BWDEV and "some how" converted in BWQA
    3) where does the source system name mapping has to be done: in BWDEV, BWQA or in both
    4) in order to do the mapping of names in BWQA I need to create the corresponding R3QA, otherwise I don't have the entry under TargSrceSy when executing tc RSLGMP
    I really apreciate an step by step process for the above scenario
    thanks a lot

    Hi Juan,
    Let me try to shed some light. Before you can transport dependent objects in the BW side, you have to make sure that the necessary dependencies in the R/3 side have already been transported. For example, if you have a datasource in R/3, you have to transport that from dev to QA first (before you transport anything in BW). Then, in the BW QA box you have to replicate the datasource before you can transport any BW objects in the BW QA. Then before transporting anything to BW QA and after replicating the datasource in the BW QA you have to go to RSA1->Tools Menu->Assignment of Source System to Source System ID menu item and make sure that R3DEV is mapped to R3QA. It is only after all the said checks have been done that you can transport objects in the BWQA.
    Here are my answers to your questions:
    Q1: This depends on your datasource. Some datasources can be transported. Some can be created in the QA box itself. But in both cases, you have to make sure that DataSource exists in R3QA and then replicate it in the BWQA.
    Q2: The conversion follows the setup in "Assignment of Source System to Source System ID" in RSA1.
    Q3: The "Assignment of Source System to Source System ID" in RSA1 has to be done in the BWQA.
    Q4: Yes, you have to setup the R3QA Source System in the BWQA.
    Hope this helps.

  • PSA Source System Update Utility

    Hi,
      We recently upgraded our Sand box system to EPH1 SPS5. The PSA Deletion Process type now includes a 'Source System' field. Since our system was refreshed from Production prior to upgrade, the Source System Field in the PSA Deletion Process Type contains Production source systems.
    Is there a utility program provided by SAP to migrate the PSA from old to new? Or A program to update source system in the PSA?
    Thanks,
    Kartik

    You can find more information and discussion in this thread.
    Thread locked to avoid duplicate discussion
    Andy  ______________________________________
    Please remember to come back and mark the post that you feel solved your question as the solution, it earns the member + points
    Did you find a post helpfull? You can thank the member by clicking on the star to the left awarding them Kudos Please add your type, model number and OS to your signature, it helps to help you. Forum Search Option T430 2347-G7U W8 x64, Yoga 10 HD+, Tablet 1838-2BG, T61p 6460-67G W7 x64, T43p 2668-G2G XP, T23 2647-9LG XP, plus a few more. FYI Unsolicited Personal Messages will be ignored.
      Deutsche Community     Comunidad en Español    English Community Русскоязычное Сообщество
    PepperonI blog 

  • Error when activate a SAP source system

    Hello Experts,
    I have an issue when I try to create a new SAP source system but I cannot complete this operation because a Timeout error occurs when the system made the destiny verification, the source system can be created but not activated, I already create the RFC connection and they are OK, I add the new logical system of the source system in the configuration (SBIW) in the general settings,and the data source tree is show succesfully and sems to work OK and the data sources seems to be OK too.
    In the RSA1 transaction, go to source systems tree, choose the SAP source system called: "conexion a dev 200" -> right click and choose activate and the error occurs.
    I have a Myself source system already created and activated, I cannot find the source of the problems thata cause the timeout error in the new source system.
    Thank you vey much in advance,
    Niurka

    Yes, I try ti use the create automatically option first but it doesn't work, because says that we system already exists because here exist a myself source system with an RFC to R/# ( I don't know why), so I must use the manually creation option, I put the logical system, and all the requeriments of the screem. The system create the source system but when I try ti activate it, it is impossible to do it....!
    I hope that you can give some tips or solution for this issue,
    Thanks!

  • Source system in Development & Quality & Production

    Dear Experts,
    Normally we do developments in Development server,so we create source system connection to R3 Development server (say 120) and create DataSources, DTP and process chains based on the Source system 120.
    Now my Doubt is when we transport the developments to QAS, how will i get the data from R3 Quality Server 500 (because my developments -DataSources, DTP,Infopackages and process chains are connected to R3 dev 120).
    how should i do this?
    Please give me your valuable inputs.
    Regards
    BI Learner

    Hi Friend,
    In general this connections done by Basis people.
    So in your case automatically mapped quality r/3 to bw quality, but first replicate changes from r/3 quality to bw quality before moving changes from bw dev to bw quality.
    this scenerio is normal wherever you go either in production perspective also.
    SAP BW(Dev)---->SAP BW(Quality) and simaltaneously mapped SAP R/3(120)--->SAP BW(Dev),SAP R/3(500)---->SAP BW(Quality)
    llly mapped production also, this is general landscape.
    I try to give scenerio and hope it should helps out.
    Thanks-RK

Maybe you are looking for

  • Bugs After Upgrading to Lion 10.7.2 (Dashboard,Safari,iCal,System Configuration)

    I got a lot of bugs after upgrading my Macbook Pro from 10.7.1 into 10.7.2 1. Dashboard :      everytime i change something or add a new widget on dashboard, ex : wrote a new stickies, arranging the place of widgets. after shutdown or restart the cha

  • Is it possible to have 2 ipods on one computer?

    I just purchased the newest 30GB ipod after having last years model. Can I make a new library or download the new itunes without losing my old library?

  • I have a mac pro but need a monitor and can't use LED needs suggestions

    I have a mac pro running on snow leopard, version, 10.6.8.  Here is the graphic info that is one my mac pro ATI Radeon X1900 XT:   Chipset Model:          ATY,RadeonX1900   Type:          GPU   Bus:          PCIe   Slot:          Slot-1   PCIe Lane W

  • Sony Location+MacBook= (Will it work)

    Hey, I was wondering if the sony location free will be able to stream TV to my macbook. It can stream to a pc, but you have to install software, will it stream it to my macbook with that software or do i need a custom made software for macs only whic

  • Open Hub

    Hi Gurus, Im in BW 3.5. I m working on open hub services, I have a requirement where in , when I upload the data to a Application server path, the client want to have an alert message saying that, received or not whatever it might be. I have been tol