Processing status & release status

Hi,
There is a configuration which says: DEFINE processing status.
  Can somebody expalin in details the use of it  .
In short i would like to know about the processing status & release status.
thanks,
prithika

Prithika,
Processing Status and Release status work closely both are interlinked. you can define processing status and assign it to condition record. Release status controls in which scenarios the condition record are found.
The release status can only be maintained directly for agreements. For condition records, this is done via the processing status.
Configuration for Processing status can carried out using
IMG --> SD --> Basic Functions --> Pricing --> Define Processing status
Here you can create processing status and Release status will be assigned according to the scenarios if it were "B",  "Release for pricing simulation" will be assigned to the processing status.
Using Tcode SM30, choose Table/View: "/BEV3/CHA_KOND".
Activate Enter Conditions Indicator
Click maintain and use the options provided.
Regards
Sathya

Similar Messages

  • How processing status "In Release " is set in purchase requisitions

    Hi Experts,
    How processing status, iun release is set in item details (Status tab page) of purchase requisition, also is it possible that release status is "release completed" even requisition is not subject to release strategy.
    how release active is set.
    Thank you
    Anand

    Hi
    The Stauses in the PR will be active opnly if you have the release strategy setup for the PR.
    "In release" is set when the PR is created & is subjected to approval & in the approval process.
    Relased is set when the PR is approved fianlly.
    Thanks & Regards
    Kishore

  • Processing and Released Status when we create a new Condition table

    Hi all
    I created a new condition table in M/03, and assigned one field to it, Generated and saved. Then added the condition table in the access sequence. There appeared two more lines below the field that i have assigned. One is Processing status and the other is released status, both are having green lights. what are these and what is its impact.
    inputs will be highly appreciated
    thanks

    I myself could find the answer

  • Process Status & Release Status for Condition Record

    Hi Gurus,
    Pls help me out in the the following scenario.
    I want to activate Authorization level check for Condition records.
    For example, Product price PR00 is being entered by first level.
    After verification done by second level only, that condition record to be used for sales order processing.
    I have gone through Process status & Release Status. But not getting full clarity on this.
    Rgds,
    Senni.B

    Hi,
    Please go through the following information.
    [Relase Procedure for Condition Record|http://help.sap.com/saphelp_47x200/helpdata/en/a4/af9e78e69611d2ace10000e8a5bd28/frameset.htm]
    [Release Procedure for PR|http://www.sap123.com/showthread.php?t=59]
    Reward if helpful.
    Thanks and Regards,
    Naveen Dasari

  • How to change 'Processing status' of Purchase Requisition

    Hi Workflow Gurus,
    I have query on Purchase Rquisition Item Release Workflow. My requirement is like,
    Whenever a PR approver rejects the PR item then the processing status of the PR item should be changed from "In Process" to 'Release Refused' without any user intervention i.e. in background.
    Please help me ASAP as I have my delivery deadline already coming in.
    Many thanks in Advance!!!
    Regards,
    Vikash

    Hi PJ,
    Mentioned  BAPI is not for changing the processing status but for Release status i.e. Blocked or released etc...
    I could get the solution by my own R&D. I am updating the database field EBAN-BANPR with required status and i am doing it in the Back ground.
    Its working fine now.
    Anyways Thanks for your quick response !
    Regards,
    Vikash

  • Purchase order processing status

    Hi
    I have a doubt regarding the purchase order processing status in the PO.
    Chk table EKKO field PROCSTAT.
    Can anyboby tell me the status sequence of a PO.
    ie: when a PO will have the corresponding status
    for ex if a PO is subject to release and if is released then the status will be 05 release completed.
    Likewise need to know for other status particularly interrested in knowing status 08, 04 and 01.
    Reg
    Raja

    >01 Version in process
    when Version Management is activated and it is processed once then this indicator will come
    >02 Active
    after po creation or if the po is on hold this will be used
    >03 In release
    when the po is subjected to release and Release is Possible
    >04 Partially released
    when PO is Partly Released  itemised release
    >05 Release completed
    release completed and now can be processed further
    >08 Rejected
    when the release of po is rejected or cancelled
    regards
    kunal

  • PO Std Workflow stuck "In Process" status

    Dear Experts,
    I have a case where a PO workflow is stuck "In Process" for over 8hrs. The background step - that has the underlining method to set status of PO to released is stuck and has not completed. (WS14000145)
    I am not sure of what could have been the problem - possible locking or anything else?
    Could you please suggest me a way out?
    Do I have kill the workflow (logically delete) and restart it again or have any other way around?
    Many thanks!
    Vj

    Well, it appears to be a locking issue.
    I found entries in SM58 and SM12. However I released them but the workflow still continued to be in Hanged - IN Process status.
    I then cancelled the workflow and then manually set released the PO documents.
    Then the PO documents were fine and were possible to edit.
    Thank you.

  • 'Print Preview' in Me22n/23n and thru ME9F and PROCESSING STATUS

    Hi ,
    We are taking print of Purchase Order thru "Print Preview" button available in ME22N / ME23N.
    Although the print out is perfect but system is not changing the processing STATUS of message 'output type'.The status remains YELLOW ( processing program has not started yet).
    While If I take the print of same purchase order thru ME9F , we are getting the same Print and the status of output type also gets changed to Green " Processed Sucessfully".
    Could u pls let me know what is issue at my end.
    Regards
    Shrey

    Dear,
    The system always creates a new version when the purchasing document has reached a final state.
    This means one of the following processing states:
    ● Active
    If you do not use the document release functionality
    ● Release completed
    If you use the document release functionality
    For a new version of a purchasing document to be created, all messages must have also been transmitted.
    No new versions are generated for purchase orders that are on hold.
    Not every change to an external purchasing document results in a new version. The following changes lead to a new version:
    ● All print-relevant changes
    You define which changes are print-relevant in Customizing for Purchasing under Messages ® Fields Relevant to Printouts of Changes.
    ● Changes in document assignment
    ● Changes in address
    Address changes result in a new version only if the field ADRC-NAME1 has been defined as a field that is relevant to printouts of changes.
    ● Changes to master conditions
    Changes in master conditions result in a new version only if the field EKPO-NETPR has been defined as a field that is relevant to printouts of changes.
    Version Data
    You will find the version data:
    ● In the item details on the Versions tab page in Enjoy purchase requisitions (ME51N, ME52N, ME53N)
    ● In the header data on the Versions tab page of Enjoy purchase orders (ME21N, ME22N, ME23N)
    ● Under Header ® Versions in RFQs, conventional purchase orders (ME21, ME22, ME23), contracts, and scheduling agreements.
    There you can maintain version data (e.g. reason for change) and complete the version. In addition, the Value change field shows you whether and to what extent the value of a requisition or external purchasing document item has changed in comparison with the previous version.
    You can display the change documents for one or more versions by selecting the relevant versions and choosing Display Changes.
    Please check accordingly.
    Regards,
    Rahul.

  • Approved requisition still in IN PROCESS status.

    HI,
    I have a requisition which is approved by last approver but still its in IN Process status and I am not able to get PO for that.I tried with Auto Create option but its giving requisition not yet approved.
    Please suggest if any work around is there to get the PO generate.
    Regards,
    Prakash
    Edited by: user623462 on 08-Feb-2012 06:57

    Please post the details of the application release, database version and OS.
    Please see these docs.
    All Purchase Orders or Requisitions Getting Stuck in Pre-Approved or In Process Status - Troubleshooting Checklist [ID 1104843.1]
    Troubleshooting for Requisitions / Purchase Orders in Process or Pre-Approved Status [ID 225017.1]
    Troubleshooting Issues in Purchasing Document Approval Processing [ID 1319686.1]
    A Guide To Understanding The Requisition Change Order Workflow Process [ID 472487.1]
    How To Diagnose Purchase Order And Requisition Workflows in Deferred Status? [ID 884391.1]
    Thanks,
    Hussein

  • Changing purchase requisition with processing status B

    How can I restrict purchase requisition changes with processing status B regardless release indicator. Rel 4.7

    Hi Mitra,
    You will find your answer here.
    MRP controller for PR document type
    Do let me know if it helped, as I might have to explore this option for an upcoming requirement.
    Thanks
    Shailesh

  • Workflow in process status when work is completed and returned to inbox

    Issue...
    Once upgraded to ECC 5.0, our Workflows are still in process status after completing the work item and returning to inbox. Takes several seconds to go to completed status.
    More detail...
    In a number of our work items in custom workflows we utilize methods that display a custom transaction for review & approval in the workflow process. From within the custom transaction we issue the terminating event for the work item by means of Function Module "SAP_WAPI_CREATE_EVENT" once the user approves or disapproves the work item.
    This worked all very well in Rel. 4.6c. By the time the users were routed back to their inbox the work item had disappeared.
    We recently upgraded to ECC 5.0 and experience the following problem. Once the user has left the work item and are back in their inbox, the work item is still on display. It eventually goes away once the users refresh their screen after a few seconds. This is very confusing to the users and some of them even wanting to start executing the same item again....
    I was wondering if anybody has any ideas on how the completion/termination of the work item could be changed so that it completes faster and is gone from the inbox immediately.
    In our research we did come across OSS note 831443, which explains as of release 6.20 that work items will be locked while executing a method and that the terminating event can only be delivered once it is unlocked. Taking this into consideration, we tried moving the terminating event to the end of the method within the business object program, but the work item never completed, even after refreshing the inbox.
    Thank you for any feedback.

    Hello Tom,
    I've had quite a similar problem with the terminating event in a dialog while the workitem is locked.
    I came across the same SAPNote 831443, but it doesn't seem to tell the whole story there. As I found out, the status change (from "in work" to "complete") is just skipped over, while the workflow continues with processing, leaving a last workitem "in work" hanging out to dry when the whole process has already finished.
    Basically the problem is, or was, that a popup dialog was shown to the user after the processed the transaction, which held the lock open. I have found no logs, saying that there was a problem with a locked workitem, anyhow.
    At last I have found out, that basically there shouldn't be much coding between the <b>COMMIT WORK</b> statement and the coding that just ends the method with <b>END METHOD</b>. This kind of procedure does definitly apply to the newer Versions, as I didn't have any problems like this before. Mayhaps and only a guess is, that the unlock-operation was previously registered with a perform like PERFORM unlock_workitem ON COMMIT. or something similar. This defenitly has changed under the new releases.
    In your specific case I would recommend to register the event processing in the update task and end the workitem's method as soon, as possible. For example:
    CALL FUNCTION 'SWE_EVENT_CREATE' IN UPDATE TASK   ...
    If this still does not help, you could further disjoin the transaction processing from the event creation by adding
    STARTING NEW TASK
    IN BACKGROUND MODE
    or whatever the correct syntax was here. This will schedule another tRFC on the database commit, which then is defenitly be picked up by another work process of the application server, just right -- hopefully -- after the object's method has completed.
    If you're feeling good with this answers, or it least it gave you new ideas to look upon, please assign points as appropriate.
    Best wishes,
    Florin

  • Disable processing status "Locked" for tempaltes

    A template in cProjects has these processing statuses:
    - created
    - released
    - locked
    - obsolete
    I would to deactivate the status "locked".
    Is this possible? If yes, is it also possible if there are already templates that are "locked", or should i "unlock" then before.

    Hi Daniel,
    You can achive this through transaction BS12.
    Select object type DX1 (Project Template). Then Go to Allowed business transaction from the menu bar.
    Untick the business transactions DX07 and DX08.
    The above mentioned steps will decativate lock and unlock status for cProject templates.
    Regards
    Amit

  • Processing Status in Travel Request ESS

    Dear all Gurus,
    I am implementing travel request approval process on ESS/MSS. After employee submits an travel request via ESS the processing status is set to have 'Released for Approval' status. Once manager approves the travel requests via MSS processing status gets 'Approved' status.
    The problem I am having is when manager rejects Travel Requests. The processing status is changing to 'In Processing' instead of 'Rejected'.  Do you know what needs to be done so that the status  is set to be 'rejected' once the manager rejects the Travel Requests.
    Regards,
    Namsheed

    You can change the text as indicated below ie 1411965 has steps in it http://wiki.scn.sap.com/wiki/display/ERPHCM/Adding+Reject+or+Cancel+Step+to+Workflow+Template SAP NOTE # 1411965 - Status after action in FITV_POWL_APPROVER, provides more information on this limitation and the configuration steps. Status comes from Table PTRV_PERIO Field ANTRG (Travel Request or Trip Approved (Indicator)) ABREC (Open / To be Settled / Settled (Indicator)) i.e. we have only request status from 1 - 6 and settlement status from 0 - 4. See the domain fixed values. BAPI_TRIP_CANCEL can be used to enhance the statuses. Please check the class CL_FITV_POWL_UTIL and method GET_STATUS_AFTER_REJECT

  • Processing status in vk11 condition record creation

    Dear All
    i have a scenario where condition record is created in vk11 the processing status should be blocked by default,
    super user will remove the block or release it in vk12
    How to configure this
    Regards
    J

    Hi,
    1. First Go to SPRO --> Sales & DIstribution ---> Basic Functions --> Pricing --> Define Processing Status
       Click on new Entries Create
                      1 Not released A - Blocked
                      2 Released - Released
    2. Create Condition Record Using T-Code VK11 , after entering the Details with your combination  then click on "Shift+F8 " or Click on "Key" you will get one more screen in that we have to select the "Processing Status "  ( In your case Give 1 ) and save the condition Record  (or)
    In VK11 , after material Description we can find out the "Processing status " Column  , there you have to mentioned "1" and save
    3. Ask your Basis Consultant to whom you want to give the Release Approval , he/ she can give the approval in VK12
    Regards,
    Prasanna
    Edited by: prasanna_sap on Jul 3, 2011 8:25 AM

  • ESS - My Trips and expenses (Processing Status)

    Hello,
    In the ESS portal for Travel Management, the iView 'My Trips and Expenses' has a column called 'Processing Status'.  The description of the trip status in the portal is not the same as in the backend (ECC).
    For example:
        Backend: Trip status shows:    'Trip Completed / To Te Settled'
        ESS:       Trip status shows:    'Trip Completed / Released for approval'
    Does anyone know where the portal is extract this text 'Released for approval'?
    Thank you,
    Robert Cvetas

    Hi Jack
    The texts themselves come from the program SAPLPTRA_UTIL_TRIPS in the text elements but for the actual status, you can look to the AEND part of the cluster transaction PRTE and if you "F4" on the status in the respective column, then you will see the actual status reason.
    Hope it helps
    Sally