Procurement Key 'F' - System will allow to create production order

Dear All,
Pls help solve below issue
Sub-assembly (HALB) material type with Procurement Key is 'F' - but System will allow to create production order, our management don't want to allow this. how to activate the error messges
I checked the system messages CO 046, 047, 048 - it will not help for these messages
Any way to control this (except user exit, badi)
Regards,
Sankaran

Hi Sankaran,
   What I infer from your statement is that user is able to convert planned order into Production Order (MD04 or CO040). You want to issue a warning message during this converion.
  You can configure warning messages through OPJB.
   Whether this material with procurement type F was setup initially with a different setup? Please check whether any routing details exist for this material and also check whether there is any special procurement indicator. One more check is with your MRP Group settings.
Hope this helps.
With Best Regards,
Srinivas

Similar Messages

  • Material status in master data set not allow create production order. but..

    Dear All expert.
    There is one case I don't understand,  the component material within BOM had been set material plant status which it is not allowed to create Production order ( Porder header Msg & PO/Network item msg = B in OMS4).
    If user use tx:CO01 for create production order, the error message block production order can't be created. It is good .
    However, when user is using Tx: CO41 to convert planned order to production order with that material ( status which not allowed to create production Order) . it is successfully without any error message ..  User successfully create production order without limit.
    Therefore,  is there any configure in IMG was wrong?
    thanks for reading.
    Marco

    Dear R.Brahmankar,
    I had followed your instruction to check. It is very helpful.
    when I check program in CO41 (saplcoup), I found that it only check material  status (FG) on top level of BOM .
    Its don't check component material.
    Function CO_ZF_CHECK_MATSTAT_POS  component item in BOM , the program will not check item plant status.
    When I use TX: CO40 to test. I found that CO40 with Program LCOSD1J - CHECK_MATSTAT_COMP have component material status check.
    I'm not sure is that genic CO41 don't have component material status check?
    ths alot
    Marco

  • Spliting the sales order qty when iam creating production order

    HI
    I have sales order haveing qty 100 ,then iam creating the production order with respect to salesorder number and item by co08.
    i want to split the order qty while iam creating production order .and after complitiung the sales order qty sysytem should not allow to create production order .
    how can i do this

    Hi,
    1. I dont think in standard it is possible.
    2. You need to find a control mechanism using the user exit only.
    reg
    dsk

  • Whether system will allow  to change the  PO Quantity , etc after GRN ?

    Dear Expert,
    Please let me know whether system(standard SAP ) will allow  to change the  PO Quantity , Net price and Price per unit after partial/fully accepting the GRN against the PO?
    regards,
    Kumar.

    dear,
    This is possible in 1 way and not possible in another way.
    I will explain you in details:
    If Po cretaed of 100 Qty........GRN done for 20 Qty.....Then you can go and can change PO qty to 20 .....
    There you can change Qty to 20....System will allow you to change the Qty...
    NOw If you want to change the qty less than 20 ( GRN qty)...Then System will now allow you to change it.
    Regards
    Utsav

  • When create RO against contract system should allow to create RO 10% tolera

    Hello,
    My scenario is when create release order (RO) against contract, system should allow to create RO against contract value 10% tolerance on total value of the contract.
    Please let me know what are the configuration settings needs to be done.
    For ex: contract value 1000 USD
    So system should allow to create RO against contract 1100 USD it means 10% tolerance on contract value.
    It seems nobady have idea on this issue
    Thanks
    Edited by: sapmm99 on Apr 19, 2011 8:11 AM

    you idea  is just in conflict to SAP design and as well it does not follow the good business practise and violates the meaning of a contract.
    a contract is a written agreement between vendor and you (customer) that fixes a certain quantity at a certain price for a certain period.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee0ee555c811d189900000e8322d00/content.htm

  • Results recording i have rejected but UD system will allow me to post

    Dear All,
    When i am doing results recording i am rejecting the particular item. But system will allow me to do UD for this one. There also i can accept those quantity. Here my client dont want that one. They are asking then what s use of doing results recording.
    There is any configuration is there to achieve this requirement.

    Hello
    There is no config for this requirement.  If the result recording is falied also UD has to be given to the lot. You have to post the material either block or to scrap or return delivery . Also even if parameters in result recording fails some parameters will not be critical and also there can be cases where want to segregate the good items and bad item.
    So in this case if you want to partly post the material , then UD has to be given allowing you to post to unrestricted.
    You cannot restrict the UD, but you can try restricting posting to unrestricted if any results are failed using Exits
    Regards
    GN

  • Cancelled invoices are also allowing to create Return order

    Cancelled invoices are also allowing to create Return order   with invoice references, how to restrict that so Cancelled invoice should not allow to create
    Return order with reference.
    Please help.
    If it is possible in standard how?

    Dear Gautam,
    I am also facing the similar problem and looking for a suitable solution. In case you if you could implement some solution to prevent creating return sales order with reference to cancelled invoice , then please update me too.
    Thanks & Regards,
    Pawan Patel

  • Update error while creating production order (TCODE CO01)

    Hello,
    We have created new plant into development server for testing. We have created production Order few days back at that time we have not faced any problem. But from last two days , when we create new production Order , system gives following error:
    ORA-00947: not enough values
    DBIF_RSQL_SQL_ERROR" "CX_SY_OPEN_SQL_DB
    SAPLCOVB" or "LCOVBF10"
    HEADER_POST"
    and
    Update was terminated
    System ID....   DEV
    Client.......   500
    User.....   HPLSU
    Transaction..   CO01
    Update key...   4B6E4F48C08D027FE1008000C0A802F3
    Generated....   08.02.2010, 10:35:48
    Completed....   08.02.2010, 10:35:49
    Error Info...   00 671: ABAP/4 processor: DBIF_RSQL_SQL_ERROR
    Our work is held up.
    Please also note that If we increase the QTY in the existing Order ( already created few days back) , System accept the same and Order is saved.
    We are looking for the solution for the above.
    Early reply will be highly appreciated.
    thanks
    harish

    Hi Rishi,
    You better check with your BASIS team.
    Check this link also
    Supervisor Error ADM0015
    Regards,
    Satyajit Kumar
    Edited by: Satyajit Kumar on Feb 8, 2010 7:47 AM

  • How can serial numbers be produced during creating production orders???

    In our company,the basic manufacture process are as follows:
    1.CO01  Create production order
    2 MB1A  Goods issue to production order
    3 CO11N Produciton order confirmation
    4 MB1A Goods Receive
    For some finished product with serial number management, when doing MB1A goods receive ,we
    will input the serial numbers into the SAP for the first time.That means the serial numbers
    was produced when doing MB1A.
    But for some reasons,we wish when we create a production order,the serial numbers can be
    produced for the finished product.That means we will release a production order,the serial
    numbers can be produced for the finished product of the production order,can be auto
    produced or by input manually.
    We do not want the the serial numbers to input into the SAP until doing MB1A.
    What can we do to produce the the serial numbers for the first time after release a
    production order?
    How can serial numbers be produced during creating production orders?
    Thanks very much for any reply!!

    You should configure the SN profile to allow that the order can be released w/o SN;
    but... for the other issues, we have used and user exit that - after saving the order - generates a SN according to a given logic. 
    We could not fina dan easy way of creating the SN after relasing the order or when doing the GI.
    Regards

  • Can i create production order using process material ?

    Dear All.
    Please help me.
    I want to create production order using process material (material type is PROC).
    For may knowledge, process order is standard for the process material, but my customer want to use the PP module for the process material.
    But I cant convert the planned order of precess material to production order in MD05.
    The system message is "System does not support planned orders for process materials."
    The followings are my test steps.
      1. Master Creation
          - Material Master, BOM, ROUTING
    In standard, process material (Material Type : PROC) need creation of master recipe. But due to my clients need (Using production order
               for the process material), I create the work center and ROUTING
      2. DM Creation
          - In MD61, I create the planned independent requirement (Type : LSF)
      3. Planned order creation for the process material using MRP
          - In MD01, I run the total MRP, the the planned order is created.
            It's order type is "LA"
      4. Converting the planned order to Production Order
          - In this step, the system give the error "System does not support planned orders for process materials."
             and can not do anything.
    I want to know that the above case is possible, and how.
    Please Help meu2026..

    Hi
    First of if yur want to create production order or process order why do you go for material type :PROC.
    you can create the same material as FERT & go ahead.
    I do not understand the logic to select the material type as PROC.
    Pl. go through SAP library where PROC is used.
    Regards
    YMREDDY

  • Usage of rounding profile in manual created production order

    Hi,
    We are making usage of various static rounding profiles.
    For each of the materials produced, the rounding qty can be different, depending on the workcenters used to produce the materials (but for one material, there is only 1 rounding profile possible)
    This works fine as long as we create planned orders via MRP runs (rounds up according the values set)
    However, this rounding value is not taken into account (proposal, warning, error,..) when a user creates a planned order manually via MD11 or a production order via CO01.
    Furthermore there is no warning message or whatever at the moment a user is converting a planned order (with a correct calculated rounded value) into a production order and manuaaly adapts the order qty.
    As were are talking about a few 1000 different materials, the production planner cannot know all by heart and the rounding proposal would be excellent.
    Anybody an idea how to implement this ?
    Thanks and regards?

    Hello again,
    thanks for you prompt answer.
    This would certainly solve our problem in case we would have always one and the same quantity to produce for a given material; but this is not always te case.
    Perhaps it was not clearly explained in my first mail, but we would like to work with one (1) ROUNDING PROFILE per material.
    Example, material A can be produced in multiples of 14; as such it should be possible for the production planner to create production orders for 14, 28, 42 , 56,..... pieces. When entering a order for eg. 25 pieces (= example the qty needed for a certain sales order), the system shpuld round to 28.
    Other materials (having another rounding profile) are produced in multiples 3, im mulitples of 5,...
    For this particular plant we have about 50 different rounding profiles in place.
    So it somewhat logic that a production planner does not know all these by heart.
    If you have a solution for this as well, please let me know.
    Anyway already my thanks for feedback.
    Regards.
    Danny

  • FM to Create Production Orders

    Hi All,
    My requirement is to create Production Orders with positions ( Components, Operations, and Documents ).
    BAPI_PRODORD_CREATE creates Procduction Orders with header data and explodes the Material if it has a valid BOM.
    In my requirement Material will not have any valid BOM. So the BAPI is not suitable for me.
    I have also tried the FM CO_ZF_PRODUCTIONORDER_CREATE but no luck.
    Does any one know other FMs to create Production Orders with positions?
    Thanks
    Bhasker.

    Bhaskar,
    Try Using one of the following BAPIs:
    BAPI_PRODORD_CREATE_CAP_REQ BAPI: Create Capacity Requirements for Production Orders
    BAPI_PRODORD_CREATE_FROM_PLORD BAPI: Convert Planned Order into Production Order
    BAPI_PRODORD_CREATE_FROM_REF BAPI: Create Production Order with Reference Order
    Do't forget to reward if useful

  • T-code CO01 to create Production order:error message "No routing found"?

    I use t-code CO01 to create Production order.At the first screen I select material 72 and plant HJW1 .At the Header creen,I input the data in the General tab and press return but the sap show the error message "No routing found".But I have create the routing for the material 72 and plant HJW1.I don't know why the sap found no routing.So my question was how to found the reason about why the sap can not found the routing and how to resolve this problem.Thank you.

    Hi,
    Probably you would have created the routing today, with valid from todays date. But the order you are creating may be with start date in past and system is not able to find and valid routing for the day.
    I would suggest you to remove both the Basic "Start" and "End" and change the scheduling type to "Current date Scheduling", now enter. If system still not finding the routing, use the function "Read PP Master data".
    Regards,
    Prasobh

  • Prt availability.while creating production order

    while creating production order. system checking PRT availabilty
    if PRT is not there system throws warning msg
    PRT: Item: 0010  Material TESTPRT1 plant BP01 is not available.
    Message no. CF301
    Diagnosis
    You are attempting to use a PRT. However, the current status of this PRT does not permit you to use it.
    how can change into error msg.........
    thx in advance

    Hello,
    I've checked the WUL of the message CF301 and found:
    CALL FUNCTION 'CO_FU_FHM_AVAILABILITY_CHECK'
           EXPORTING
                index_imp             = affhd_sav-indbt
                tco11_imp             = tco11_tmp
           IMPORTING
                fhm_not_available_exp = fhm_not_available_tmp.
    FHM verfügbar
      IF NOT fhm_not_available_tmp IS INITIAL.
        CASE affhd_sav-fhmar.
          WHEN material.
            MESSAGE i301 WITH affhd_sav-psnfh
                              affhd_sav-matnr
                              affhd_sav-fhwrk.
          WHEN sonstige.
            MESSAGE i302 WITH affhd_sav-psnfh
                              affhd_sav-sfhnr.
          WHEN dokument.
            MESSAGE i303 WITH affhd_sav-psnfh
                              affhd_sav-fhmnr.
          WHEN equipment.
            MESSAGE i307 WITH affhd_sav-psnfh
                              affhd_sav-fhmnr.
          WHEN OTHERS.
            MESSAGE a886
                    WITH sy-repid
                         hlp-fname.
        ENDCASE.
    I'm afraid the attribute is hardcoded to be warning.
    BR,
    Tiemin

  • Creating Production order

    Hi all,
    Can somebody help me in creating production order. After putting the name of Material, Plant and Order type(PP01) system shows a error: Material ... not found in Plant 1000(check entry). The thing is I entered product in master data which I can see in Display material in master data.
    thanks,
    Shahrokh

    HI
    did u check all the assignments, please check whether you have maintaine dthe organisational levels for this material the plant, the storage location etc. and check whether the plant is linked to the same company code where you are cretaing the production order since cost centre datas gets affected you need to check those settings
    please revert if you still got error .
    Regards
    Vignesh

Maybe you are looking for

  • Reading From Binding Object

    Dear Sir We are populateing the Binding object from the backing bean as the following code : public String writeToOutput() { DCIteratorBinding process = getIterator("processIterator"); process.getCurrentRow().setAttribute("SimpleElemet", "Simple Elem

  • Firewire...I've never had so much trouble.....

    I'm a big researcher when it comes to buying things, in fact I drive myself crazy trying not to waste money on stuff that wont work. I've never had so much trouble in my life until I started researching a new laptop for audio work. I don't want to bu

  • Problem with Fixed File to Oracle - LKM File to Oracle (SQLLDR)

    Hi all, I have a problem when I try to load data from a fixed file to a Oracle table. I had created my Datastore as a File and with the "Inversion" I set all the columns definition of my fixed file. When I try to execute the interface, I have this er

  • Content Server Error Handler

    I have an Intranet site let's say www.xyz.com and it has restricted access. So before anyone gets to the site, they have to be authenticated. If a users press "Esc" for authentication(cancells Authentication), then the Site Studio Error handler is no

  • TS1424 itunes movie rental

    i rented a video on itunes, and it doesn't play the last 30 minutes.  Is there anything I can do to get it to play?