Procurement of non stock items without using material master?

Hi Experts
My company follows third party scenerio with non stock items . The procurement process starts from creating a PR thru network by entering a material master and other purchasing information in component overview. I have come to know from some sources that in case of non stock items we may process the same  by not using the material master and just entering a material description and other purchase related information. So, my questions is:
Is it possible to follow the procurement process for non stock items without using material master? And if it is Yes, then how will i maintain the tax coditions which i generally do for material and vendor combinations.
Thanks

Hi Chandra,
It is mostly used in projects where you are directly procuring materials for projects and no need to track the inventory.
But i think it is better to create to material Master and use that Material with item cat L so that at any point of time we can track inventory .
Muzamil

Similar Messages

  • Entry Aids for Items Without a Material Master - usage

    Hi
    Can anyone tell me what's usage of "Entry Aids for Items Without a Material Master"  (spro-mm-purchasing-mat master-entry aids..)
    and what it controls???

    Hi,
    In this step, you can assign a purchasing value key and a valuation class to a material group.
    The assignment of a purchasing value key provides you with default values for reminder levels etc. in purchase order items without a material master record and without an info record.
    The assignment of a valuation class to a material group enables the system to determine different accounts for the individual material groups.
    This is usally useful for creation of PO and account posting for materials without an MMR.
    When you create a PO you mention only the material group, based on which the purchase info like the Deadline monitorying, over/under delivery tolerances, Vendor evaluation etc gets incorporated into the PO. The account posting will get captured against the Valuation class maintained to the Material Group for which the GL account mapping will be done against the V.Class in the OBYC.
    Regards
    Merwyn

  • What  is use of  Item Category N(non-stock item) in BOM creation

    Dear Experts,
                       What  is use of  Item Category N(non-stock item) in BOM creation ?
    regards
    rajakarthik

    Hi,
    This item category is used for components which are not kept in stock if they are used in a bill of material (BOM). Non-stock items can be entered in the BOM with or without a master record. To enter a non-stock item without a master record, you must simply enter a descriptive text.
    When you use this item category, the system automatically creates a purchase requisition for these components,
    Special functions
    The following functions are supported for non-stock items
    • You maintain purchasing data for non-stock items in the bill of material.
    • In the planning run, the system generates purchase requisitions
    instead of dependent requirements for components that are procured directly. When you configure your R/3 System for MRP, you can define whether direct procurement is triggered by the planning run or by production order management.
    • Product costing processes take valuation data from the BOM item.
    The system determines the release strategy on the basis of the price data you enter. The material group is required to produce a purchase requisition.
    Pavan

  • Procurement of more quantity than required in case of non stock items

    Dear Experts,
    Requirement is given below.
    I have one maintenance order with non stock item category N for quantity 5 pieces which is actual need.But user wants to procure 50 pieces against order and consume 5 pieces and rest will keep as stock.
    But in case of procurement against non stock item the moment we received the Goods (GR), all procurement quantity  will goes to consumption account and postings will happen accordingly.Correct me if i am wrong.
    Now my requirement is to keep the remaining stock 45 pieces (5 pieces consumed against actual need) as stock and to be consumed whenever there is a need.Can it possible to keep as stock in storage location which was procured against order as non stock item.
    How can i resolve this issue.
    Please somebody can help me.<<Text removed>>
    Thanks in advance.
    Reddiy.A.V
    Edited by: Matt on Oct 12, 2011 6:46 AM

    For the orders which you consumed, do the reversal of that material document. Also create one GR for the qty which has been returned to vendor & keeping the stock to storage location.
    In future, define those as stock items, so that this work around won't be required.

  • Non stock items procurement with excise duty

    Dear Experts,
    We are using TAXINJ procedure , For non stock (without material master) items procurement , we are manataing tax codes with BED 10  % ECESS 2% and SECESS 1% and in J1ID excise rate mantaning with CHAPTER ID , but in the case of non stock items there is no material master so there is no chapter id for that , even i have mantained without material id and chapter id combination also , but while creating PO with this taxcode excise duty are not caluclating ,  please tell me what we need to do caluclate excise duty for non stock items.

    Hi chandu, you maintain a A blank material in J1ID ( ONLY SPACE under material coulmn) and other details as usual.
    You issue will be resolved.
    for eg
    s.no___Material__________________plant_____Chap id ____mat typ
    1___    blank( dont enter anything) ___1000_______ abc_____ Raw material
    2.____ 100-100___________________1000______ xyz_____Raw material
    Cheers
    Kris
    Edited by: KRISHNA AKULA on Jan 28, 2011 7:08 AM
    Edited by: KRISHNA AKULA on Jan 28, 2011 7:11 AM

  • Asset procurement & Non stock item procurement

    Hi,
    I want to procure Asset items. For that do i need to maintain asset master & material master both. Than create Purchase order with AAC as A. Will the PO be framework order or standard PO?Can anyone pls let me know the steps
    Also for non stock items do i have to do GR. In that case the goods are coming to stock as i have to give storage location during migo. What is the procedure?

    Hi,
    For procuring Assets, you will have to maintain Asset master & material master both in your system. You place a PO for the material (which you define as your asset & want to capitalize) & maintain AAC as A- Asset. Then at the item level, you assign the asset code to the masterial. After you post the GRN, the debit entries are posted to the asset.
    You have to post the GR for non stock items as well as stock items. The non stock item will be consumed dirctly to the acount assignment you have mentioned. For stock item, the inventory posting will be done. For stock item, the storage location will flow from the PO (if mentioned) otherwise you will have to post it yourself at MIGO in tab 'Where' at Storage Location'.
    Regards,
    Prashant Kolhatkar

  • Stock and NON-Stock Items procurement

    Hi,
    Please let me know why classic scenario cannot be used fpor Stock items and Extended classic can be used for both stock and non-stock items.
    What is the exact difference.
    Regards,
    Manu

    Hi Sanjeev,
    Thanks for the reply.
    But if PR is transferred to SRM from MM and classic scenario is used and the resultant PO is created in MM then will transfer the PR with/without account assignment.
    Pls let me know.
    Thanks,
    Manu

  • Stock & Non stock item

    Hi Experts,
    Could you please tell me how to recognised the stock material.
    Like if we consider material type NLAG it is purely non stock item.Like wise which are the material type is consider for stock item.
    How can we identified the stock material.
    AR

    Hi,
    Stock material is kept with value and Qty both.
    while
    Non-valuated material (Material Type UNBW):
    This type of material is managed on a quantity basis, but not on a value basis. This makes sense for materials of low value, stocks of which nevertheless have to be monitored (for example, operating manuals).
    Non-stock material (NLAG) (Material Type NLAG):
    Inventory management is not possible for these materials either on a quantity or value basis. For frequently required consumables, the use of this material type nevertheless enables you to store the information required to create
    purchasing documents (such as texts and units of measure).
    When a material is procured directly for consumption, no material master record is necessary. In connection with consumable materials, you can distinguish between the following cases:
    • Consumable material without material master record
    • Consumable material with material master record that is not subject to
    inventory management (on either a quantity or value basis)
    • Consumable material with material master record that is subject to inventory management on a quantity, but not a value, basis
    Regards,
    Pardeep malik

  • For non Stock items ?

    Hi ,
    For non stock items (which do not have material code ) , what price we will put in PR ?
    In live scenario, suppose a  requestor from HR dept is raising a PR for non stock material.
    Suppose the material is procuring for first time in that company .
    He doesnt know the price for that .
    So what price he will put in the PR?
    Please tell me in live scenarios , what people used o do ?
    regards,

    Hello Sandeep,
    While creating purchase requisition, normally user dept will put the approximate price for that material/service. sometime user will put even price as 0.01 (currency) also in PR and purchasing dept will put the negotiated price at the time of Purchase order creation.
    Hope this helps.
    Regards,
    Arif Mansuri
    Reward if answer is helpful.

  • Unit of measure for Stock and Non-stock Item in CJ20N

    When I attach Material to an activity (item Category N   Non-stock item) in Project Builder (CJ20N), It is peaking its Base unit of Measure as unit. Now when I try to change it, it is showing an error
    Item category N: Only base unit of measure M allowed
    Message no. CO344
    But for the same material if I change the item Category to L   Stock item, then it allows me to change the unit.
    Please guide me regarding this Behavior. Is there any customization, by doing which it will allow me do the same for Non-stock Item or It is not Possible.

    firstly I am assuming that the activity is internal processing type - doesn't matter really
    now to attach a material select actvity and from the template area click and drag material which will open the material detail screen in the work area
    because it is a non stock item I am assuming text description - in the requirements qty you enter the qty and next to it the units - changeable
    if you choose a material number maintained as material master then obviously the unit will be from the material master.
    If you are using an externally processing activity then in config check OPUU for the network type and see if order unit has been populated - that might be the problem

  • Is it possible to add value item and non stock item in one billing?

    Is it possible to add value item and non stock item in one billing?

    Hi,
    Yes,it is possible .Take example of service scenario,where material used in servicing and service charges(labour) can be billed in single invoice.
    Billing document type,Customer and other header data should be same.
    Reward points if useful
    Regards,
    Amrish Purohit

  • Item Category N (non-stock item) in BOM creation - Preq Generation

    Hi All
    I have a material component that is planned in APO and not in ECC6. We would like to keep the one BOM for the finished good. Problem is that when we perform the backflush in ECC6, the system wants to backflush the material and causes errors due to missing stock.
    So I assigned the material as a non stock item in the BOM but the system will auto generate  a purchase requisitions for Non stock bom components (item category N) when the process order is created. It is possible to turn off the auto creation of the purchase req for non stock bom components? 
    I have tried the following:
    - Explosion type in item data, created new key with 'Switch off planning' indicator set in system configuration
    - created new 'Z' item category with inventory management de-selected
    Both approaches causes system error: Puchase data of material in not maintained
    I also tried leaving as a stock item with the bulk material indicator selected in the item data. This does not work as the cif will then exclude the component when data is transferred to APO
    Funny enough, the system does not generate a purchase req for non stock bom items when using Repetitive Manufacturing. Any help will be greatly appreciated
    kind regards
    Grant brockelbank

    Hello Vivek
    Thank you for your response
    The item is a non stock item. I do not want this item to be backflushed at all. This can be achieved using the 'N' non stock item category but the problem is that the system will attempt to generate a purchase requisition when the process order is created.
    I do not want the system to generate a purchase req in ECC6 as this item is a planning material that is planned in APO (used for medium to long term planning in a simulation version). We are hoping to use the one Bom for ECC6 and APO planning. The generation of the purchase reqs is a bit of a waste as we will never convert them and there is potential to cause issues for purchasing.
    Any other thoughts?
    Thanks again for your help
    kind regards
    Grant

  • Selling Non-Stock item

    HI
    We want to sell a non-stock item.
    Pricing & Billing yes.
    Schedul line & delivery no.
    which material type, Item category group,  Sales item category    should be used.
    thanks . Thomas

    I created a new Non-Stock material.   ( material type NLAG, item category group  NLAG ).
    create a sales order.
    and billing document is not being generated.  ( sales item category  TAX is determined . I set the TAX . Relavant for order related billing ). .
    message there is no billing relevalne item in order.
    we want to do  Billing.
    but not  delivery & PGI.
    Regards\Adnan

  • How to assign account assigment automatically Non Stock Item ?

    Dear All,
    How to assign account assignment automatically at PO level for Non Stock Item Material for expense charges ? Since our user does not familiar with the GL Account code.
    Regards,
    Setiadi

    Setup for Automatic Account Assignment
    SPRO-IMG - MM- Valuation Class and Account Assignment- Account Determination-Account determination without wizard
    1. Define valuation control T Code OMWM
    2. Group together valuation areas T Code OMWD
    3. Define valuation class T Code OMSK
    u2022 Account category reference
    u2022 Valuation class
    u2022 Material type / Account Cat Ref
    4. Define Account grouping for movement type T Code OMWN
    5. Configure automatic posting T Code OBYC
    Maintain Transaction/ Event Keyu2019s for your Chart of Accounts
    BSX - Stock Posting / Inventory Posting
    PRD - Price difference
    GBB - Offsetting entry for stock posting
    WRX - GR/IR Clearing
    Let me know if you need more detailed setup procedure-Switesh!
    Edited by: Switesh Nage on Dec 4, 2011 9:33 AM

  • Tools & spares need to change as non stock items..

    Dear All,
    My client wants to make spares and tools as non stock items..previously they were stock items and they are around 2000
    materials so instead of creating new materials with new material type i have decided to change material types of existing materials using MMAM..
    Please tell me is this a right process to do?what will be the effect of this?
    What is a correct procedure for this?
    Thanks,
    Naren

    Hi,
    You check for the prerequisites
    Prerequisites
    1 .If you use the material ledger, the material must be settled in it.
    2. If the old material type did not require you to specify a price control (for example, standard price or moving average price) for the material, the new material type must not be configured such that it allows only standard price as the price control.
    3. If the material has been maintained from the Production Resources/Tools view, this view must also be allowed for the new material type.
    4. .If the material is not a configurable material, the new material type must not be allowed only for configurable materials.
    5. In Customizing for the Material Master (in Define Attributes of Material Types), the following indicators must have the same setting for the old material type and for the new material type:
    Material for process indicator
    Manufacturer part indicator
    6. If inspection plans are required for quality management inspection of the material, they must be allowed for the new material type.
    7. The Material type ID indicator (presently used only in Retail) must be the same for the old material type and for the new material type.
    If the material is already in stock, or if reservations or purchasing documents exist for it, the following conditions must also be met:
    1. . The stock values of the material of the new material type must be updated in the same G/L account as the stock values of the material of the old material type.
    2. Quantities and values of the material of the new material type must be updated in exactly the same way in all plants as quantities and values of the material of the old material type.
    3. If there is a transfer requirement for the material and if quants of the material exist, the new material type must also allow the material data to be maintained from the Warehouse Management view.
    If the material, whose material type you want to change, was handled in batches and if, due to the maintenance statuses of the new material type, the material can no longer be handled in batches, although batches still exist, you cannot change the material type.

Maybe you are looking for

  • How do i add an email to a FaceTime and an iMessage account?

    I have another email besides my apple ID i would like to us eon face time and iMessage, so i go to add it in the settings, after entering my new setting it says verifying, i have let it set for a good 30 MINS and even hit resend email a few times, bu

  • Sap career in which module - reg.

    Hello Guru's This is challa, from Hyderabad, i have lot of doubts in choosing the sap career. I found many sap modules in which i can't find to choose. i am working as a Logistics executive (import & Export) in a company, i am very much interested in

  • How enabled Single Sign-On with a System SAP WAS ABAP (Run application BSP)

    Hi. I need to run any application BSP from a System SAP WAS ABAP, without entering SAP user and password. Using the windows authentication and without SAP Enterprise Portal. What authentication methods I have to apply for enabled Single Sign-On with

  • Duplicate Copies of Files

    Whenever I try to import files into lightroom from drive C:, LR seems to go into a loop making duplicate copies of all the files in the directory I'm trying to import from. This behavior seems to extend to trying to delete files from the directory wh

  • Icloud deleted recurring event and send notifications to everybody. I never used icloud and never deleted this event.

    I never used icloud and never made any changes to my icloud. Today icloud sent notifications to 100 people that the event was cancelled. I didnt made any changes. Those 100 people wrote "very good feedback" This event was created not in icloud, it wa