Procurement Type changed in PS

hi
I used procurement PFS (Third party requisition for WBS) and 3rd party
order. When I added the articles to network activity, a window will pop-up where I can enter the address (using address, customer or vendor).
The issue is when I cancel the address, Procurement type changed
to "Purchase Requisition for Network" and "3rd party order" check box
is unchecked.
Once both indicator changed, I can NOT go back and add or change
address.
Steps for Reconstruction    
1. Create or add material to network activity (TCode CJ20n)
2. Procurement type is PFS and Item is non-stock material
3. window will pop-up to enter address or customer or vendor
4. Press Cancel to close the window WITHOUT entering address or
customer or vendor
Message: CN358 The component with lose its route character
Procurement type changed to "Purchase Requisition for Network" and "3rd
party order" check box is unchecked.
Regards,
Sri

Hi
If you are procuring the material via third party then the details needs to be filled in for customer / vendor , as this is standard SAP , and this is how the system will calculate for the customer/vendor postings in other modules and is required for the reporting purpose also. This would be already defined in the config , check the config settings.
Thanks ,
DHRUV
Edited by: Dhruv Kumar Malhotra on Oct 6, 2009 12:04 PM

Similar Messages

  • Reg : Procurment  Type Change From F to X

    Hi,
        Can we able to change the Procurment Type From F to X  in MRP 2 View ?

    I dont think so, a material once declared as externally procured, cannot be change to both.
    regards,
    Sudhir

  • Change Procurement type

    Dear  All
    How can i change the Semifinished or other Material procurement type<b>.(convert F[/b<b>](External Procurement)</b> To <b> Both Procurement(X).)</b>
    <b>condition</b> :-Already Purchase order And other trasaction is still going on that particular SFG.
    Regards
    Pankaj Agarwal

    Hi Pankaj,
    You need to find which MRP profile was used to create the materail you are refering to.
    Go to the change mode of the material select MRP2 View, now go to menu "Environment" --->"MRP Profile" --->"Display". Now system would show which MRP Profile was used and its defination, in your case "Procurement Type" field must have been defined with "Write-protected".
    You can change the defination of it using transaction "MMD2" or "MMD7" if you want to check the usage of it and decide based on that.
    Hope this helps you. Reward your points,
    Regards,
    Prasobh

  • Material Type Change Implication

    Hi all,
    What are the implication of changing the material type of existing materials?
    Kiki

    Hi Kiki
    Implication of material typpe change. First of all you can change if the stock is nil.
    1) If you have maintained different storage location for different material type. The location will change.
    2) Further The valuation for each material type is different.
    we have to change accordingly.
    3) Screen group selection is based on the material type, this will change.
    4) Procurement type will be based on the material type.
    5) Material group is based on material type.
    6) Even base unit will be different for different material type. in some industries for Ex FERT and HALB will be in PC, EA etc., and ROH will be in Kgs.
    Hope this will clear your doubt.
    Regards
    J . Saravan

  • Wrong procurement type showing in the material master

    Hi,
    I am creating a material Procurement type is comming as E in the MRP2 view, To where it is comming?
    I have checked the material type setting in the tcode OMS2 and it below are showing there:
    Ext. purchase orders   2
    Int. purchase orders   2
    Hence it's allowed int. and ext. proc. then why in the material master procurement type is comming E not X.
    How can I change it?

    Check to see if you have assigned an MRP Profile which has defaulted Procurement Type. If this is the case, you will have to remove the MRP Profile before you can change the entry. Or you can maintain the MRP Profile by deselecting "Write-protected in material maintenance" and selecting "Only default value in material maintenance" for Procurement Type. The Transaction is MMD2.
    BR,
    Krishna

  • Material procurement type

    Hi All,
    For one material my client create with the procurement type F wrongly.
    then they need to change the procurement type as E.
    but we found that field is grayed. how to chage the field to enterable and we need to change the procurement type
    thanks
    vbakyaraj

    Hi
    See the below config to change field selection for transaction MM02 for the field procurement type in MRP 2 view
    Logistics General ---> Material master -
    > field selection
    Select your field and group it under a seperate group. And make it as editable in Field slection for transaction mm02.
    Regards
    Antony

  • Special procurement type is APO relevent?

    Hi,
    I change the special procurement type for a material in MM02 MRP2 view. CIF models are running fine. But APO PDS is not getting updated.
    What could the issue here?
    regards,
    shan

    Thanks..
    There are no CIF queues..
    I have made special procurement type "BLANK". BOM is still not updated. CIF models are fine.
    regards,
    shan

  • Special Procurement Type(SPT) u0096 Cross Plant Costing

    Hi,
    I am reviewing PC config as part of a post implementation analysis.  Is there a report the shows the cross plant costing relationships?  I am concerned that a MFG to hub relationship was not followed.  For example I have materials in MFG plant 1234 with a SPT from MFG plant 5678.  I also have materials in plant 5678 with SPT from plant 1234.  I am worried about a circular reference during product costing – not real sure which plant to cost first.  Any help is appreciated.
    Thanks,
    Bill

    Bill
    The SPT for Cost are the same as used on the MRP screens.
    The costing program looks to the field of Spec Procurment type fof Costing FIRST, if it is populated it follows the rules.  If not populated then it looks to Spec Procurment type on MRP, if not populated, rules in the costing variants are followed.
    Our product cost specialist maintains the field via CATT/and custom programs.
    Our specific issue was:
    Part A is manufactured in Denmark at Std price control
    USA plant acquires it from Denmark and uses as a component in equipment.
    The SPT on MRP drove both events.
    Processes changed and all parts made Denmark were store in the Belgium warehouse at moving average.
    The definition of the SPT was changed and suddenly Cost was coming from a moving average in Belgium.
    Not what we wanted. 
    So we created an SPT for Cost and populated Costing 1. 
    Now cost comes from Denmark and material comes from Belgium.
    Hope this helps
    Althea

  • Default Procurement Type for a Material Type

    Hello everybody,
    Is it possible to assign a default procurement type (for example: F) to a Material Type?
    If yes, can you explain me where (which transaction)?
    If no, can you explain me an alternative to do so?
    Thanks a lot in advance for your help...
    Regards,
    Rudy

    You can do this by configuring material type.
    Follow the path
    IMG->Logistic general->material master->Basic Settings>Material types-->Define attributes of the material type
    Select the material type and click detail button
    In the External/Internal Purchase order Subscreen---Set the following details
    Ext. Putchase Order should be 2 (external purchase order allowed)
    Int. Purchase Order should be 0 (No internal purchase order allowed)
    If u save the setting
    then when u create material master, Procure type would be F in MRP 2 screen and you cant change this value becuase the field is greyed out it will be only displayed

  • CK86_99 and CK86: display purchase group and procurement type

    Hi Gurus,
    I have a request
    Can I  insert the purchase group and procurement type in the layout of tcode CK86_99 and CK86 when we have a material item ?
    I have seen that we can define the control parameters for the Product Cost Controlling Information System.
    Tcode OKN0 but we have only the basic fields and we haven't the specific fields for division.
    Thanks in advance
    Marco Ferrari

    Hello Marco,
    I do not think you have any options to change the layout except for the fields that are available in the transaction screen. It is a standard report and is not a one based on report painter layouts. It would be helpful if you can consult an ABAP person who can throw some light or create a report for you.
    Kind Regards // Shaubhik

  • Procurement type in planned orders

    Good morning Gurus,
    I have some semi-finished materials whose procurement type is given as X in material master. When I run MRP I am getting planned orders for the same. But in the planned orders the system is giving the procurement type as E (in-house). Why is the system picking up E? The order created is LA.
    For materials for which the procurement type is F, the system is creating planned orders of NB. Here the procurement type is not changed. I am getting F only. This is ok.
    Why in the case of X, it is creating planned orders with procurement type E? Any settings?
    Thanks and Regards,
    Ram

    Hi Ram,
    The system behaviour is correct.
    While maintaining order profile, once can choose Procurement type as E or F (X can not be given here). The Procurement type for the material in the material master is X.
    While running MRP, the system would first try to create planned order with E if it is possible to produce the material in-house. In case, it is not possible, system should propose F.
    Even though the procurement type in planned order is E, it is very much possible to convert the planned order to Production Order as well as Purchase Requistion. This gives flexibility to the planner to take a call on whetner to produce in house or procure externally.
    I hope this is clear.
    Regards,
    Sandeep

  • Procurement type non editable field

    Dear experts,
    I have an issue please guide me,  For one material i am not able to change procurement type,  that field is graout (non editable)  material type is Raw Material.
    in material stock also exists,    what could be the reason,  how to  change
    please guide me
    Regards
    Chandu.

    >
    chandu wrote:
    > Dear experts,
    >
    > I have an issue please guide me,  For one material i am not able to change procurement type,  that field is graout (non editable)  material type is Raw Material.
    >
    > in material stock also exists,    what could be the reason,  how to  change
    >
    >
    > please guide me
    > Regards
    > Chandu.
    This procurement type is in material master right. You need to get it editable in spro.

  • Procurement type

    Hello,
    In the material master, tab MRP2, there is a field called Procurement type. Anyone can tell me where is it setup in the IMG?
    We have 4 types of procurement types (external, internal, both and none) and I would like to have a look.
    I've been reading that this field is automatically filled with information from the material master type, which informs exactly about which kind of procurement you can use. Is it defined in "Logistics- General -->Material Master -->Basic Settings --> Material Types --> Define attributes of material types"? The only field that I've seen there that could be related is under internal/external purchase orders.
    Any help? Thank you

    What do you mean with BESKZ domain? I am quite new in SAP.
    My problem is that I cannot select the blank, because procurement is a mandatory field and blank is not a good response to it. My intention was to change that "blank" for any other letter.
    I've changed the external and internal orders in the material type to no purchase orders allowed and the result is not good enough.
    Thank you for your quick answers

  • Procurement type Vs Price Control

    Dear All,
    We are maintaining price control as V for procurement type F, and S for E.
    Is there any possibility, for automatic change in price control when the changing the procurement type from F to E.
    Regards,
    Venkat.

    Hello Venkat,
    Price control is for Material master, but not for the procurement type. Once you set the price control in the material master (i.e. in Accounting view of the material master) system will calculate the stock value (i.e. for internal stock updation by value purpose) in the material master.
    As you said, material price control is V (i.e. MAP): Moving average price.
    And here,
    F ---> an Account assignment of Customer Individual requirement
    S --> Thirdparty Item category (i.e.TP is a type of procurement)
    E --> an Account assignment for Order
    It is not possible to change the price control automatically when you change the procurement type manually. Because the price control (i.e. V or S is possible) setup is done at Master data configuration (i.e. Material type configuration). But document (i.e. creation of PO) level it is not possible.
    Suggestion: Changing the price control of a material master always is not advisable. Because there will be lot of impact on Inventory and as well as Finance. And moreover it is a configuration setup for material type (i.e. property of a material or material master) in sap. Hence it is not possible at document level.
    Hope this will clarifies you,
    Reward, if it helps,
    Regards,
    Srin.K

  • Procurement type 'P'

    Hello All,
            What will be impact in the SNP planning if we have the Procurement type as 'P'.
    And in which case do we maintain the value as 'P' ?
    Thanks,
    Siva.

    Hi Siva,
    By using Procurement Type "P" you indicate APO that this material is not to be planned. One scenario where it was quite useful is when you mark the material status in R/3 material master not be planned. Over the period, business may not need those materials to be planned, however to have the visibility of existing stocks they would like to have this material in the system (No deletion). In that case, they change the status in plant-matl filed of MRPview 1 (not sure), which when CIFed will change the material in APO with Procurement Type P.
    SAP calls this as deactivation of materials
    How can materials in SAP APO be deactivated again?
    To indicate that a material is no longer relevant to SAP APO, you must first remove the material from all active integration models. To prevent further planning results being transmitted from SAP APO to SAP R/3 you must also set the procurement indicator (BESKZ) to P (Planned externally) for the location product in SAP APO. You can automate this process. For more information, see Logging Deactivated Material Masters.
    You can also set the deletion flag in SAP R/3 and transfer this to SAP APO. When the material is no longer being used, you can also delete the material in SAP R/3 and the product in SAP APO.
    Check out this link as well,
    http://help.sap.com/saphelp_scm70/helpdata/en/3a/d5d83773c3522be10000009b38f842/frameset.htm
    Regards,
    Rajesh Manoharan