Product cost controlling by sales order

Dear all,
My client is having mto scenerio (non valuated stock) ,When i am confirming actual activities like electricity
in production order the system picks planned activity rates and loads costs on production order,My client wants system to pick actual activity rates in place of planned rates so that production order should contain actual costs of all the activities.
another issue is regarding detachment of some say 10 tonnes out of 40 tonnes from sales order.the costs of 10 tonnes of finished product is taken from moving avg. price of material master of finished goods,which is dr, to stock account and credited to cost of production a/c,price control is "v" of finished goods and semi finished goods.I want to how moving avg. price is updated in material master and how to justify the correctness of that price.
Kindly provide me suggestions
Thanks and Regards
vijay

Dear all,
My client is having mto scenerio (non valuated stock) ,When i am confirming actual activities like electricity
in production order the system picks planned activity rates and loads costs on production order,My client wants system to pick actual activity rates in place of planned rates so that production order should contain actual costs of all the activities.
another issue is regarding detachment of some say 10 tonnes out of 40 tonnes from sales order.the costs of 10 tonnes of finished product is taken from moving avg. price of material master of finished goods,which is dr, to stock account and credited to cost of production a/c,price control is "v" of finished goods and semi finished goods.I want to how moving avg. price is updated in material master and how to justify the correctness of that price.
Kindly provide me suggestions
Thanks and Regards
vijay

Similar Messages

  • Product cost collector for sales order related production

    Hi Friends,
    This is Azam and here i am new to this discussion forum.
    we are in situation that use diffrent variant for configurable material in sales order related production,
    I would like to have some information about use product cost collector for this kind of sales order related production,
    also I want to know difference between prelimanary cost estimate or cost estimate for sales order?
    Please co-operate me.
    I would be highly appriciated if you can respond at the earliest.
    Thanks
    Azam

    Hi,
    Here, for each sales order item, you will have sales order cost estimate. This enables the system to compute the variances once the actual costs are booked against the production.
    In the case of preliminery cost, we get the preliminery cost for production order as a plan cost and is not being used for the computation of variance but only for comparision purpose which is very marginally used.
    Trust this helps much and do encourage our efforts!
    Cheers!

  • Cost Analysis by Sale Order

    Hello,
    I'm seeking to enable in BI a Cost Analysis Scenario with repect to the <b>Sales Orders</b>. That is, something similar to the analysis you can easily perform in the R/3 area <i>Accounting -> Controlling -> Product Cost Controlling -> <b>Product Cost by Sales Order</b></i>.
    For instance in standard report KKBC_KUN, you can choose a sales order number and get all the <b>cost elements</b> related to that sales order, with the corresponding costs.
    I have examined the following objects provided by the BW's Business Content:
    - <u>InfoCube 0PC_C01</u>: it contains only the costs related to <b>production orders</b>, and not the costs associated with sales orders.
    - <u>InfoSource 0CO_OM_CCA_9</u>: it seems interesting, in fact it delivers some header and line item data of the <u>Controlling Object Document</u>. Unfortunately it doesn't deliver the crucial characteristics <i><u>Controlling Object</u></i> and <i><u>Controlling Object Type</u></i>, which I definitly need for enabling my analysis scenario!!
    (By the way, are these 2 characteristics delivered by the BC? There exists a 0COSTOBJ characteristic, but it's not used by any object in the flow afterwards. Moreover, I can't find a standard DataSource in R/3 which I can use to load either its attributes or its texts, and see what data enter it..)
    Business Content for Product Cost by Sales Order), but none could help me.
    It seems really weird that it's not possible to carry out a <b>Cost Analysis by Sales Order</b> in BW, so if anyone has some suggestion it'll be very appreciated indeed.
    Thanks & Regards, Davide

    I eventually found the following SAP Note. No BCT for this analysis scenario....
    <b>Note 584791 - BW-BCT-CO: Costs not extracted on sales orders</b>
    <b>Symptom</b>
    In R/3, costs are posted directly to sales orders. The costs have to be analyzed in the BW system. In the standard system, however, this data is not extracted into the BW system.
    <b>Other terms</b>
    0CO_OM_OPA_1; 0CO_OM_OPA_6
    <b>Solution</b>
    1. There are currently no DataSources for costs on sales orders in the standard BW Business Content. Unfortunately, there are currently no resources scheduled for a new development in this area either.
    2. Therefore, the DataSources and the Business Content must be created in the customer project within the framework of consulting as a customer solution concerning the generic extraction options of the BW Service APIs or function modules you have programmed yourself for extracting data.
    3. Technical background information about costs on sales orders:
    The transaction data is available in the following R/3 tables
    COSS and COSP - Totals records or COEP - Line items.
    This concerns records for the VB* object numbers.
    The master data of the sales orders is contained in the VBAK and VBAP tables.
    The 0CO_OM_OPA_1 and 0CO_OM_OPA_6 DataSources only extract costs for orders with master data in the AUFK table. These types of requests always have OR* object numbers. Therefore, these DataSources cannot be used for sales orders.
    However, you may be able to assign requests from the AUFK table (for example, maintenance orders or production orders) to a sales order through the AUFK-KDAUF table field.

  • Sales Order Report Showing Cost on the Sales Order & total invoice dollars

    I am looking for a report in SAP that shows you the Sales Order number, the cost on the sales order (NOT the average cost) the actual cost on the sales order detail line and then the total invoice dollars in month to date and year to date?
    Thanks,
    Linda

    You can use <b>T.code: COOIS </b> if Product Costing has been configured for MTO scenario whcih gives the costing details.
    You can also use To.code: <b>KE30</b> if CO-PA implemented.
    but if you want to link with billing, Please search for any reports in Sales information system.
    One more you can create a ABAP Query Report using T.code: <b>SQVI</b>
    Regards,
    Anbu

  • Error reading material cost estimate for sales order (KE292)

    Dear All,
    I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
    Message no. KE292
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
    However, no product cost estimate could be found for this sales order item.
    The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
    CO-PA Customizing settings.
    System Response
    The system cannot process the document any further.
    Procedure
    Check your Customizing settings."
    We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
    Regards,
    Nagaraju,

    Hi,
    When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
    If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
    Hence, try to run cost estimation and then do releasing.
    Thanks & Regards
    Ravi Kumar

  • How to transfer cost from old sales order (cancelled) to new sales order

    Hi Gurus
    I want to know, how to move cost from one sales order to another sales order.
    SD created sales order before 1 month and there was production order behind this. Production was completed and all the cost was moved to sales order and also SD has raised invoice on customer. This transaction was completed.
    The above order was rejected by customer due to some changes in the order. SD raised another sales order and production order was created to to additional work. Production transfered above stock (produce before on old production order) to new production order.
    My problem is stock is now transfered to new production order but cost is still sitting on old sales order. How do I transfer cost from old sales order to new sales order. SD cancelled old invoice and raised new one with full value (old + new work) on new sales order. Now cost is on old sales order and revenue is on new sales order.
    Please help.
    Thanks

    Hi
    I have reverse the sales order settlement, PP order settlement to sales order and I have also done KB11N for transfering the cost to the new production order.
    The only problem is I was unable to transfer labour hour confirmation as cost element used for this are not for transfering cost. If I will reverse the confirmation in PP order system will reverse material movement also which I don't want any more. Can you please tell me how to I reverse the Labour hours with out affecting goods movement?
    Many thanks

  • Costing Sheet in Sales Order

    Hi All,
    Can you please inform me why do we put the costing sheets in the Sales order under the Account Assignment TAB,
    How does this Cost Sheet affect the Cost of the Product,
    Please inform the Sales order costing cycle if possible...
    Regards
    Ashwin

    Costing Variant is assigned to Requirement class
    Requirement class is assigned to Requirement type
    Requirement type is assigned to Planning Strategy
    Planning strategy is assigned to strategy groups
    Strategy group is assigned to MRP3 tab in Material Master
    System picks the costing sheet in requirement class
    In this way product will be costed for Make to Order sale order costing.
    Srinivas

  • Sales order costing and valuated sales order stocks

    SAP Gurus
    Can somebody explain the key configurations and account postings in sales order costing and valuated sales order stocks in product costing using the specific tcodes.How the process moves from one configuration to the other?
    Use of examples will be appreciated too
    Thanks

    hi rback59
    Thanks  for  your valuable reply
    i completely agree with your point regarding valuation . but want to know what is the impact of recosting of a sales order . as system only picks first goods receipt cost all the time . then what is the use of recosting ?
    Thanks
    Sachin

  • Costing update in sales order

    they get the consumption of sales using customized transaction
    actual cost is zero
    user create the material master withot pricing
    we ask to update the material master and they do the costing run
    in material master standard costing estimate found
    after they  run the consumption report ,once again actual cost is zero
    i chech\ked in  costing status using CK11N ,std cost estimate found
    is it  possible to update the cost in sales order
    (redetermine or recalculate the pricng in sale order)
    so that my consumpotion report will update
    thanks
    Edited by: Suresh Kumar on Jul 26, 2011 4:59 PM

    Hi Suresh,
    I hope ur doing MTO Scenario.
    for this u need not do standard cost estimate.
    during sales order creation VA01 > extras tab > Costing. u can do costing for each customer aganist each sales order.
    not for each product.
    for do it u need to maintin some of the settings .Check Requirements Classes .
    if u maintain Costing ID              B Automatic costing and marking.
    in requirement tab if u maintain these settings when ever u save sales order it calcutes sales order cost estimate and released automitically.
    thanks
    kareem

  • Cost Calculation for Sales Order Collectively

    Hi,
    We need to recalculate sales Order cost. We can recalculate Sales order cost in SAP T Code VA02 for individual sales order. I am having approx 1000 sales order of which cost needs to be recalculated. Can any one help me How to recalculate Cost of these sales order Collectively.
    Thanks in Advance,
    Pawan Kumar

    Hi,
    I guess you should select B (carry new pricing). Although the system would try to reprice, in fact I guess that no pricing value would be change. If this doesn't fit your requirements then SD expert should answer your question (there are some ways you can control the pricing calculation, the ultimate way is some coding under REQUIREMENTS, but I would use it as last option).
    Benni

  • Copy Control between Sales Orders and Deliveries

    Hi Gurus,
    please can you tell me why copy control between Sales Order and Delivery doesn't work?
    At header level, into copy control, we can set 2 requirement routines, one as general requirement for copying (TVCPL-AUBED) and the other one as requirement for grouping orders into deliveries (TVCPL-AUZUS).
    At header level we can also set a routine for data transfer to define how data are passed from Sales Order header to Delivery header (TVCPL-GRUAK).
    Then we can set routines at item level, one as requirement (TVCPL-AUBED) and one as data transfer (TVCPL-GRUAP).
    When delivery is created with VL10A transaction, at header level only the first  general requirement routine is used (FV50B***). Grouping requirement is not used (we also set a break point and the program is not passing into this routine).
    Then it is used the requirement routine at item level (FV50B***).
    Please can you tel me how we camake working the routine for grouping requirement at header level?
    Thank you very much.
    Kind Regards
    Andrea

    Hi, we used standard routine even if to be sure we run also the generation report you mentioned.
    Please any other suggestions?
    Thank you very much.
    Kind Regards
    Andrea

  • Cost center in Sales Order/Credit memo request

    Hi SAP Gurus,
    There is a requirement from our client. They are processing Credit Memo from SD VF01 via Credit memo request. The want to assign Cost center in the line items which is greyed out at the time of processing in VF01.
    I also verified in the Credit memo request in VA02 even there is no field available for to maintain  Cost center in line item so that at the time of billing it can  derive.
    Please advice whether can we assign the Cost centers in Sales order/Credit memo request line items?.
    Regards
    NTH

    Hi NTH,
    In the standard system, the field cost center is only ready for input
    if the sales document category is VBAK-VBTYP= I (that is, order without
    charge). For all other order types, you can make it visible by entering
    an order reason provided that the combination of the sales area and the
    order reason has a cost center assigned in OVF3. To change this standard
    behaviour, USEREXIT_COBL_SEND_HEADER can be used. There you can find a
    short example on how to make a field visible and modificable in the
    account assignment screen.
    Moreover, please take into account that the account assignment to a cost
    center is possible only at header level. So it is not possible to
    insert the cost center at item level, you can only insert it at header
    level.
    The cost center determination takes place in
    FV45KF0V_VBAK-KOSTL_ERMITTELN and is reading from table TVAUK.
    This table can be maintained in transaction OVF3.
    If you wants to be able to enter the cost center manually in the
    account assignment screen (header level), you can use  the user exit
    FV45PF0C_COBL_SEND_PBO_VBAK (SAPMV45A) - there you can find a short ex
    ample on how to make a field visible and modifiable in the account
    assignment
    I hope that this information is of assistance to you. Thanks!
    Regards,
    Alex

  • Copy Control From Sales Order to Purchase Order

    Hi Experts,
    I want to ask how the copy control from Sales Order to Purchase Document can be done? Because they are instances that the users have some items in the Sales Orders not copied to Purchase Document.
    Thanks a lot!

    Hi Experts,
    I have seen the documentation for 3rd Party Sales, thanks to some suggestions. However, there is a report which does not work in our Test Environment, the program name is SDMFSTRP. As suggested by some forums, this is another way of connecting Sales Order to the created Purchase Requisition. So I'd like to ask if there are other ways to connect the 3rd Party Sales to the created Purchase Requisition.
    And also may I know your scenarios when there will be missing items from Sales Order to Purchase Requisition. There are some instances that from Indent Orders, some SO items are not copied to PR.
    Thanks a lot!

  • Re-Cost (CK55) Marked Sales Order Line Items

    My current client resets standards each quarter. They have requested to re-cost open CTO Sales Order line items and update the valuated sales order cost (EK01). I have reviewed the options available in CK55 - Mass Costing and find the processing log retrurns the following message:
       Cost estimate with status VO exists. See long text
       Message no. CK_MCSO014
       Diagnosis
       A cost estimate with the status VO already exists. This cost estimate will not be overwritten.
       System Response
       Processing continues with the next item.
       Note
       You can remove this message from the log with the customizing transaction User-Defined Error Management for Mass Costing of
       Sales Documents. The item will still not be costed, however.
    Short of manually re-costing each open sales order line item. Is there a way to re-cost open CTO Sales Order Line items?
    Regards,
    Dewayne Wesley

    I didn't realize there was a MASS Cost transaction.
    Is there a MASS delete Sales order Cost estimat transaction? That would help.

  • Add a new field in the item table control of sales order

    Hi Experts,
                   We have created a new custom field in Material master table. Now, they want to add the custom field from material master to the last field of item control of sales order.
    Please, let me know the steps to do it.
    Regards,
    M.Saravanan

    Hi,
      take program: SAPMV45A
    take screen 8459 and add the new field.
    Also add the validation in the flow logic.
    Refer
    https://forums.sdn.sap.com/click.jspa?searchID=10547810&messageID=3132651
    Regards