Product costing sales order scnarios

Hi,
My client requires
1) what will happen if after production order settlement to sales order customer does not requires some material say out of 100 tonnes 20 tonnes ,and they want to detach the same from this sales order and keep in stock or attach with another sales order.My question is cost which have been incurred will it be transferred to another order.
2) what if some sales return is there
3) how will system behave if after 1 process say one stage of production is completed and other 4 stages are pending whether the costs incurred on 1 production order is to be settled and then ra run is to be executed
4) If entire sales order is not billed say 5 tonnes are remaining what will be the status of cost incurred and inventory of 5 tonnes.
Client is having NON VALUATED STOCK scenerio
Any useful suggesstions.
Regards,
Shradha,

Hi Shradha,
This is an old issue. Let me try to answer you.
1) You can transfer from one sales order to another sales order. It needs SD customization.
2) Sales return has to be handled in a normal way as we follow in any other case.
3) Once the GR happens and Teco is done, the production order is fit to be settled. It will be taken care at the period end closing activities. Let me know who is the settlement receiver.
4) In your MTO scenario, the inventory is reserved against the Sales order.
Trust this helps a lot and let me see your reaction to continue my support to you!
Cheers,
Ashok Singh
+91-9884132189

Similar Messages

  • Error in product costing (sales order)

    Our products are configurable and the procurement type change with a
    particular value of configuration .My solution was that a dependence change the requirement type in sales order (modify VCSD_UPDATE).
    If an user generate a position in sales order, system create immediately an
    production order if a characteristic FUORI_MISURA ="FALSE" else MRP generate a purchase requisition (procurement type in master record is F30).
    Problem is that product costing in asles order consider in any way purchase value, never production cost.
    Can I modify the costing criteria with a dependance ?

    Hi Ajay,
    it is one of the requirement from our client.
    I have post this issue earlier and my client was accepted to do partial sales order settlement on daily basis, now three copa document was wrong value so i have reverse the document but system taken consider latest document,
    is their any chance to change COPA Settlement document ( Record type C)...i need add one characteristics i.e. material Group in the COPA Document
    Thanks & Regards.
    Vinu

  • Product cost by order, period(pcc),sales order differences

    can anybody explain the difference between product cost by order, period(pcc),sales order

    hi
    check the following link
    http://help.sap.com/saphelp_46c/helpdata/en/1d/39d448cd3011d19eb3080009b0db33/content.htm
    You have very good explanation here
    krishna

  • Description on product cost by order.

    Can anyone give me a example of differenct product cost ?
    1) product cost by order and product cost by sales order ?
    Also what is the difference between those two production order.

    Hi,
    In the SAP standard (as per the transaction codes indicated by you) it is not possible to include multiple plants. Either you have to execute for one Plant or for all plants. Probably, in Test run you can execute for all Plants and check the results, and then decide.
    Thanks
    Murali.

  • Reg:Product Costing  by order Configuration

    HI all,
    How to configure Product Costing by order.
    plz send me the configuration steps.
    regards
    JK

    We have  a make-to-order (sales orders) scenario where standard cost estimate is updated in material master as standard price for finished products. We use CK40N to update the price.
    We also have a make-to-order ( projects) where we do run standard cost estimate in CO version 1 but do not update  standard price in material master.  The standard price is zero in material master , before GR from production.
    In a make-to-order scenario , you can choose to implement  to update or not update standard price in material master.
    Hope this helps you.
    rgds,
    Rajesh

  • COGS determination for Free of cost sales order

    Hi All,
    We have an issue regarding the COGS determination for Free of cost sales order. We created a free of cost sales order. But i need to know whether this sales order items will hit to COGS or not? If so how do i check whetehr its has been charged to COGS or not? and we have an issue raised saying thst one material in this sales order has not being charged to COGS. So please help me to solve this issue. Ihave checked the account assignment in GBB-VAX. And is there anyting to do with the settlement profile for COGS determination?.
    Thanks and regards
    Uday

    Hi,
    During PGI a material document and accounting doc gets created which would hit COGS account.
    You're talking about one specific sales order in which for one material it didn't hit COGS account or any order you're creating now with that material has an issue? If its a specific material which has an issue always..then something is wrong with that material master setup. Also you can go to the reported Sales order--doc flow to the PGI document and check the accounting doc and if its not posted..check the analysis why its not posted?
    And if its one off then I would suggest 2 options:
    1) Reverse the goods movement, cancel the delivery or if billing has already been done..cancel the billing as well. And re-do the cycle. This always ensures correct posting.--> Recommended option.
    2) Manual adjustment in FI.
    And settlement profile is Controlling concept..not sure you would get any help on this in this forum.
    Regards
    RS

  • Production against sales order

    Hi all experts,
    I am creating a report for Linewise width wise handover
    summary(OK production against sales order)
    I am taking Date from MKPF and QTY from MSEG
    I need to show Work Center [ CRHD-ARBPL ]
    but dont know how to link tables
    can any one send me the code and link btween MSEG and
    CRHD or any other table which having ARBPL field linking with
    MSEG.
    Thanx in Advance ......

    Hi,
    CAUFV and AFKO tables are linked with table CRHD. These two tables are related to order. You can try these tables to get the desired data.
    Regards
    Amit parkhi

  • CO02. Product Cost by Order.

    Hi All.,
    When i am doing the Product cost by order for PP Production Order through CO02, it is giving the details of Itemization of cost for only Raw Materials.
    Then what about the Production Costs...or at this level.......cant we get the cost of production, production overheads....and also the material overhead.
    Please provide information to clarify this doubt....
    Thanks

    Hi Arun.,
    Thx for your reply, but what i am asking is different frrom the actual cost line items.
    At the order level, when we are checking costs....only Raw material costs are picking, then what about the other costs like
             Material Overheads,
            Production Costs & Overheads.......
    Thanks......

  • Product Cost by Period and Product Cost by Order

    Hi,
    For one client can we go for a group of materials(FERT) with Product Cost by Period and for some other group of materials materials (FERT) Product Cost by Order.
    My question is can both the concepts be used simultaniously for one client?
    Any difficultieis if you follow both the concepts simultaniously.
    I Would greatly appreciate your replies.
    Thanks!!!
    -Kumar

    Hi
    You can very well use both the scenarios at same time.. Absolutely no issues with it...
    Ensure that your Prod order types are separate for both the scenarios....
    Prod Order type for Cost by order will have FUL as settlement type and the order type for Cost by period will have PER....
    So, your user in shop floor needs to have that discipline of selecting the correct order type..
    If your identification is based on some field like Material group, you can also put a custom ABAP check which wil give an error message incase wrong order type is chosen
    For eg: Mat group ABC is allowed for cost by order... Order type for cost by order is Say, ZPP1... Your ABAP code can check if Mat group  is ABC and order type is not ZPP1, then issue an error message
    To put this check, use BADI WORKORDER_UPDATE
    Regards
    Ajay M

  • FG production on sales order but RM procurement on Sales Contract.

    Dear Gurus
    Here is the client requirement for Planning and Procurements of FGS and Rms.( Process Industry)
    1) Client wants to make sales Contract VA41 for FG in which they will create schedule line for item with delivery date in Month format with Quantity.
    From VA41 sales contract creation , they want their RMS to be Procured but NO MRP should be run or impacted for Final Assembly. In short NO MRP for FG
    2) After VA41,  they again want to run VA41 in which they will create ''With reference and in contract tab, they will make Customer PO with reference to above Contract. This number will give them a Qty Variance between customer's purchase order and the sales documents created.
    3) Again with Reference of Customer PO, they will make a Sales order from VA41 and this sales order they will Produce their FG.
    So FG Production is Sales order driven but RM procurement is Sales Contract driven.
    1) Which Planning strategy i should assign to RM and FG?
    2) What will be step by step configuration guide from PP and SD side.?
    Appreciate your reply
    Thanks
    Shailesh

    In SPRO
    goto SD>Schedule line>Define schedule line categories
    here check if the schedule line category associated with your mentioned order has a flag ticked for Availability.
    Availability check for sales
    You must carry out an availability check for the following transaction.
    The indicator is determined as a proposal in conjunction with the respective requirements type. It can be changed in individual shipping transactions. However, only one restriction is effective.
    Example
    You do not set an indicator for maintaining the requirements type. In this case, no availability check is carried out. This is independent of the selection in the respective transaction.
    You set an indicator for maintaining the requirements type. In this case you can decide whether or not you require an availability check for the relevant transaction.
    reward points if it helps
    regards
    Biju

  • Rework Order after QC Rejection......for Production against Sales Order

    Hi All,
    Can you help me in the following issue.........?
    I have Make to Order production scenario. After Production Order is confirmed material goes for QC inspection and some quantity get rejected ( need rework).
    Since I have confirmed total quantity in order confirmation, if I create a rework order with reference to the sales order that will increase the production qty by the rework qty. But I need a rework order to rework on the rejected quantity.
    Let me know how to resolve the issue.
    Thanks and Regards,
    Samar

    Hi!,
    From your mail it seems that you are doing quality inspection on GR (inspection type 04). Please carry out following steps:
    1) At the time of quantity posting on usage decision please put rejected quantity in field against retuen to vendor (i.e. carry out 122 movement for the rejected material). By doing this you will find the delivered quanity on prod order reduced by the rejected quantity.
    2) Now create a production order without material (CO07) for the rejected quantity and put the original order as cost receiver in the settlement rule so that all the cost incurred during rework will be settled on original order.
    3. Confirm the origianl order / Final operation again for the reworked quantity and make the GR again. This will again create a new inspection lot.
    4. Carry out the result recording and UD for this new inspection lot.

  • BOM Production in Sale Order

    Hi all,
    I have a finished good is ABC, strategy is 20 (make to order).
    I have a variant for ABC, the quantity of components in ABC is 1 pc. When I create a Sale order, I have to choose some characterristics. It depend on requirement of customer. I can see cost estimate in cost report function of Sale Order and inform to customer. My question is "if I change the quantiy of component in ABC is 2 or 3 pc, the cost estimate will be change?"
    If not? how i see the cost of order after change component in BOM.
    Thanks all

    Dear,
    I have noy fully understood your question. What I understood is you have created Sales order and then you chnaged the BOM qty of sales order BOM. Will it chnage the  cost estimation?
    It depends. If you have chnaged the BOM after sales order is created, if you go for recost run, it may change. and you may get the correct cost.
    Are you looking for this?
    Raj

  • Multiple Selection of Products in Sales Order

    Hi Experts,
    my requirement is to select mulitiple products from the product F4 help pop-up in sales order items assignment block. To achieve this I have made the following settings:
    1.added the following code in SearchHelpResult.htm view layout of PRD01QR/SearchHelpResult.
                          onRowSelection        = "<%= lv_select_event %>"
                          selectionMode         = "<%= RESULT->SELMODE_MULTI %>"
                          selectedRowIndex      = "<%= RESULT->SELECTED_INDEX %>"
                          selectedRowIndexTable = "<%= RESULT->SELECTION_TAB %>"
    after this settings, I am able to select multiple products.
    2.I have created a button (Choose) for the component PRD01QR to transfer the products to the items assignment block.
    please suggest me on how to transfer the multiple products from the Pop-up to the items assignment block (BT115IT_SLSO)and create line items using the events.
    thanks and regards,
    S Reddy

    Hi,
    Redefine the method EH_ONSELECT_ORDERED_PROD.
    As you can see, they are getting the current entity,reading the Product GUID and setting it.
    Here is sample code snippet...
      DATA:  lr_context_node    TYPE REF TO cl_bsp_wd_context_node,
                  lr_cw                   TYPE REF TO cl_bsp_wd_collection_wrapper,
                  lr_it                     TYPE REF TO if_bol_bo_col_iterator,
                 lr_current              TYPE REF TO if_bol_bo_property_access,
                 lr_prd                   TYPE REF TO if_bol_bo_property_access,
                 lr_product_guid      TYPE REF TO comt_product_guid,
                 lv_outbound_plug   TYPE seocmpname,
                 lv_index                type sy-index.
      TRY.
       Check outbound plug
          lv_outbound_plug = prodsearch_popup->get_fired_outbound_plug( ).
          CHECK lv_outbound_plug = 'RETURNRESULT'.
          lr_context_node = prodsearch_popup->get_context_node( iv_cnode_name = 'PRD' ).
          lr_current = lr_context_node->collection_wrapper->get_first( ).
         while lr_current is bound.
        set product guid
          lr_product_guid ?= lr_current->get_property( iv_attr_name = 'PRODUCT_GUID' ).
          lr_cw      = get_collection_wrapper( gc_context_node_admini ).
          lr_it      = lr_cw->get_iterator( ).
          lv_index = lv_index + 1.
          lr_prd    = lr_it->get_by_index( iv_index = lv_index ).
          lr_prd->set_property( iv_attr_name = 'PRODUCT' iv_value = lr_product_guid->* ).
         lr_current = lr_context_node->collection_wrapper->get_next( ).
        CATCH cx_sy_ref_is_initial cx_sy_move_cast_error.
          RETURN.
      ENDTRY.
    Basically you have to loop at the products and populate admini.
    Regards,
    Masood Imrani S.

  • Product Costing - Process Order Confirmation

    Dear Experts,
    We are facing a situation with our Product Costing Scenario :
    Under SFG Process Order Confirmation, there are Ten Phases to finally confirm the order. First Phase is for Raw Material Issuance. From Second Phase to Ninth Phase are relevant to Activity Types. Tenth Phase which is final phase, in this point Goods Receipt posting is generated.
    At first phase, system posts Raw Materials Goods Issue (Movt Type 261) to Process Order:
    Entry : RM (Cr), Consumption (Dr).
    Client needs the system to post one more entry at the same time by : WIP (Dr), Inv Change (Cr).
    Reason:
    According to client, they have made consumption entry in finance but what if all raw materials are not consumed as yet and factory comes under fire, then how can they claim insurance on those Raw Materials which are not consumed and are still in the IN PROCESSING Stage?
    My Answer was:
    - They can find all material costs in Process Order as Debit Item.
    - They can also calculate WIP but cannot post WIP in Finance unless the order is settled.
    Ultimately, as per my knowledge client cannot check the unprocessed Raw Materials report in FI but they can check in CO. And this is the point of reservation from client.
    They need an entry in Finance for WIP to claim insurance in case of fire and therefore they need a posting of  WIP entry immediately after Goods Issue of Raw Materials to Order.
    Can anyone please guide me further regarding this scenario and if any one can suggest any work around then it would be highly appreciated!
    Regards,
    Zain Bashir 

    Hi Zain
    This is a very unusual question
    Buddy, there is something in accounting called as "Going Concern Concept" which we all were taught in our accounting days.. That means when you do business, do it with a mindset that you are goinig to do it for long / for ever.. Accidents dont happen every day and you cant build a system around such things
    Assume there is a fire (God forbid).. After the accident, you wont even know how much was  lying there unconsumed which got gutted in the fire..
    And insurances not just covers the stock lying consumed, but also stock manufactured and stock in the process of manufacturing (WIP)
    And most importantly, dont expect SAP to throw up a figure at the click of a button.. Does your client really think that they will simply submit the report generated from SAP as-is to Insurance people?? SAP is just a technology enablement, which requires human intervention at various places
    My opinion - Dont build system for such requirements
    Br. Ajay M

  • Not able to select Base unit in Receipt from production and Sales order

    Can anybody help me out for the below scenario
    I have defined Sales UOM , Sales Packaging UOM, Items per Sales unit and Quantity per Packing UOM  for all finished product in the item master.
    I have created Production BOM and Production Order (with Issue method is Manual because they maintained items batchwise ) for all Finished products. 
    Based on Production orders, I received finished products(Batch wise) through receipt from production.  But the base unit shows Yes and it is not allow me to change. 
    In Sales order, the quantity column shows the value of quantity per packing UOM instead of Items per sales unit. 
    For Ex. ItemA - 01 No (Item per Sales Unit)
                             3600 Pcs ( Quantity per Packing UOM)
                             Receipt from Production - 10 Nos
                             In Sales order - it shows 36000 (10*3600 ) instead of 10 nos
    Expecting favourable solution for that.

    The selectable units on the sales order are the inventory unit or the sales unit. So if you want to see in units of 3600 Pc-s you should define this as Sales Unit (not as packaging unit). Then you can show the item in this unit in the sales documents.
    (In the receipt from production document you should always use the inventory Uom.)
    Edited by: István K#rös on Dec 22, 2009 10:07 AM