Production and planned order not scheduling
Dear Experts,
Created new plant ,scheduling parameters,order type parameters ,confirmation parameters.
Scheduling parameters: Detailed Scheduling ,Forward etc.
created BOM, Routing,WC.
Maintained Work center Scheduling Tab formulas entered,Routing Machine,setup time entered.
System showing at the of creating production order Scheduling Start time and end time is same.
scheduling not done in production order.
Anyone explain process for scheduling
Regards,
Naresh Reddy.
Hi Naresh,
The problem is mainly due to the work center scheduling formulas only. Maintain the scheduling formulas as SAP001 for setup and SAP002 for machine. In OPU3 check the automatic scheduling check box, adjust dates as 'adjust basic dates , adjust basic requirements to operation date' and recreate the production order.
Let me know if u are still facing the same problem after doing these settings.
Regards,
Krishna Chandra
Similar Messages
-
Mass update for production and planned order MRP controller
Hi Gurus,
It's anyway possible to mass update MRP controller for Production orders and Planned orders. If any please provide me step by step process.
Thanks,
B.Deethya.I feel You have changed the MRP controller in Material master and want to incorporate same in production order & plan order.
For Planned order Run MRP with delete and recreate mode, system will create a new plan order with MRP controller in Material master
For production order, Mass change is not possible, create a simple BDC or LSMW, And change the MRP controller -
Modeling dummy product and planned orders
Hi SAP Gurus,
I have requirement where i need to model particular business requirements on subcontracting and the same is resulting in need of modeling of dummy product and dummy planned orders. Please share your inputs on what would be impact of dummy product and dummy planned orders in ECC. and also how to make sure that it does cause any issues in costing.
I am modeling subcontracting requirement and i need to create following master data.
All the below products are at plant P.
P has the components as Q_D
Q_D has the components as Q
Q has the components as R
Where Q_D is the dummy product produced at plant P.
P and Q are subcontracted items to the vendor V.
P is the finished good, Q and Q_D are Semi finished goods, R is raw material.
When we plan we are creating Purchase orders for P and Q. And Q_D is made inhouse and we need to create planned order for it. how do we handle the planned orders created for Q_D. we dont want them to convert to production orders. we want a way to clear off these dummy planned orders once we close the POs of P and Q.
Please advise.
Thanks.
JagadeeshHi senthil,
Check if the forecast date is beyond PPDS horizon.
Also in product master on PPDS tab, you should maintain 4 in PP Planning procedure.
Bye.
Nitin -
Planned order not getting generated for FG
Dear Experts,
Planned orders not getting generated for the Finished Goods - X which is having MRP Type M0 - MPS fixing type strategy group 20 which is copied fron another FG - Y , its a new product and production plan has been updated through MC88 - Rough cut planning but the planned orders are not getting generated.
And for the material valid production version exists with selection method 3 and individullcollective as 1.
Please let me know what might be the possibalities and what all the key fields i need to check.
Thanks & Regards,
Sampath
Edited by: sampath s on Jul 13, 2011 11:31 AMDear,
In general MPS is run for High value items ( if you use like Gold , Platimum or A class items. ).
Always only single level is used for Explosion and planning. then only you can analyse the requirements at each stage before procurement.
Otherwise if you run MPS to multi level, Bottom most high value will be procured without any notice to authorities. Even you may cancel the process in mid way. At that time what will happen to the procured high value material.
So for that purpose only single item single level MPS concept is evolved.
Fo that you run MPS at single level so that only for the first level MPS will be carried out.
Check and revert back.\
Regards,
Alok Tiwari -
Req. delivery date and plan order finish date relationship
Dear Experts,
I have a question on setting the req. delivery date and plan order finish date relationship. Now, I want the plan order finish date is one day before the req. delivery date, is it possible to set it in configuration? Please advised! Many thanks!
Regards,
Matt YimMatt,
Please use a schedule margin key(SMK) in the material master MPR2 view which has float after production defined as 1day.
If there are no SMK with that defination then you can define you own in customisation and assign the same in the material master. (SPRO--->Production ->MRP->Planning ->Scheduling and Capacity Parameters->Define Floats).
Regards,
Prasobh -
How Can i Calculate The shortages against production or planned Order
Dear All
how can i get the shortages against production or plan order .
condition is Egg.----ITEM <b>X (available qty is 6000)</b>is using for three assembly .A,B,C
I have created one order For <b>A--5000 qty</b>. At this time <b></b> item x is reserve for Order Created Of A.
Now i have created one another order for<b> B--4000 qty</b>. then it would showing the shortage of 3000 Qty.
And same Order of <b>C Qty 5000</b> Material x would be showing the shortage
5000.
<b>Bcoz Shortage of 3000 is for B And Now i want only Shortage Of C.</b>
How can this procedure done.
Rgds
Pankaj AgarwalHi Prasobh
Don't mind
Points is not so major issue for me.Till i m not getting right answer or near by sothat i cant concentrate on point .almost all answer was clarify by me already . then if i cant get the right solution then i will take help from experts like u.nothing more.and point of view we have already touched with this community and i have given points more of them.so don't mind . take it as a challenge definitely u will get superior point from me.
Rgds
Pankaj Agarwal -
Order not scheduled according to allocations
What does an order not scheduled according to allocations mean?
Edited by: Anurag87 on Dec 1, 2010 12:13 PMhi,
as for as my understanding goes:
you have product allocation feature according to that, against the sales order allocation is not happening ?
in standard scenario, if once goods are release by PP consultant it will come and fall in UNRESTRICTED USE with that if i create a sales order first it wil get reserved against the sales order & you can see the same in SCHEDULED FOR DELIVERY beside it.
basing on your query,
i think so product allocation has failed in alloting the material against the customer or region.
please check this and confirm
balajia -
Copy Production Area Planned Orders to a corresponding processing plant
Hi All,
I am in need of design a dialog program which copy production area planned orders to a corresponding processing plant, In my requirement i am not able to find what are the tables involved and what is the bapi must be used to update the tables.
I appreciate if anyone come with tips to start with this requirement.
Thanks and Regards,
BabuHi folks,
Thanks for the prompt reply, i have one basic doubt, whether the order no must be passed by us, if i am not giving order no it will returns the error.
Thanks and Regards
babu -
VSF and planned orders same day
Hello,
When running MD04, forecast (VSF) and planned orders are landing on the same day. This is causing confusion for the users. Is there a setting that's causing this to happen? We are using checking rule PP. Should we be using A instead? The planned order should actually be showing up before the forecast because we don't want the inventory to show negative from the forecast. Any help will be appreciated.
Thank you.
MZHi MZ
On the standard MRP process, the planned order basic finish date will generally match the requirement date.
Check this document which explains the scheduling in more detail:
Backward Scheduling for In-House Production - Material Requirements Planning (PP-MRP) - SAP Library
BR
Caetano -
Colective Settlement and "CLSD"Status for Production and Maintenance Orders
Hi dear experts,
Is that possible to use transaction KO8G for collective settlement of Production Orders? Apparently it only works for Maintenance Orders.
The same applies for transaction CO99 for getting "Closed" status in Orders. Apparently it does not take the Production Orders, even if the selection "With CO Production Orders" is active. Is there any additional configuration we should do?!
We would like to do settlement (and mass set "Close" status after) for Production and Maintenance Orders at the same time.
Thanks in advance,
Lígia MoreiraHi,
You can use CO88 for settlement of production orders. Normally, CO99 should take production orders if the flag is switched. Do you receive any error when you do it?
Regards,
Eli -
Process Orders and Planned Orders data
Hi,
I am working on extracting process order and Planned Orders data into BW. I could not find any standard DataSources available for my req, so I want to develop generic extractor. the main key figures are Actual Labor and Machine Hours, Target Labor and Machine hours.
Please help me if there are any standard datasource available or ECC tables to pull the data or any standard function modules available.
Thanks,
ReddyHi Sanath,
Thanks for your reply. I want to pull Actual Machine hours, Target Machine hours, Actual Labor hours and Target Labor hours.
these fields are not there in PLAF table.
I am looking for a table or datasource which can give those details.
Thanks,
Reddy -
Production and Service order Release Log updation
Hi,
Can any one help me how to update the release log of Production and service order.
I have a requirements to add new custom logs to the production and service order release process.
sudhaAs far as I know the standard behaviour is that the PR is created upon order save and not upon the status of the order or items changing to released.
To get around this you can set user status and use status management to prevent the PR getting created or use the BADI CRM_SRV_FIND_LOG_SC to supress creation of the PR.
Hope this helps. -
Dependant Requirements and Planned Orders
Hi,
For dependant requirement, question is whether once the planned orders (of independent requirements) are converted to production orders, then only will the dependant requirements be converted to planned orders or it is converted once independent requirements are converted to planned orders? I.e. independent requirements are blown down all the way in MRP.
Thanks.
Rgds,
SueHi,
Let us take some example so that it is easier to explain.
Material A - Finished Good
Material B - Raw material
PIR generated for A - 100 Nos , MRP is run and Planned order created for A - 100 Nos. Now
For Mtl B Dep reqt is generated for 100 Nos.
If No stock is available then a planned order for 100 nos generated.
IF Stock is availabel then no planned order is generated.
When production order is created for Mtl A then the "dep reqt" status of Mtl B changes to
"ordres"(order reservation)status.U can check this MD04.
Thanks and regards,
Rajesh -
I just recently purchase an ipad with retina display it is also my first apply product and I am not liking it. First it won't stay connected to my wifi and it won't pair on my nokia N8 phone via bluetooth. Any suggestion? Thanks!
No one from Apple here - this is a user-to-user forum for the Apple Thunderbolt Display. If you don't like your iPad, sell it.
If you want to ask questions about your iPad, go to the iPad community forum.
Clinton -
Table for process order and planned order in apo
I would like to know the table for stratagy profile for particular process order and planned order.
in /sapapo/rrp3 there is one filed RECEIPT/Reqt.Element ( process order ) for this field which table it is coming and i required particular strategy profile for that process order .
Please help me the table in apo.Hi Venkat,
This value is stored in structure /SAPAPO/RRP_ORDREQ_STR
under the field name EXTRA.
You can check the details of the same in transaction se11
Regards
R. Senthil Mareeswaran.
Maybe you are looking for
-
Someone has stolen my ipod. I do not have it with me, but is there another way to find the cerial number or another piece of information i could turn into the police? is there anyway of getting it back, Becuase i hav a good idea of who stole it, and
-
Previous iPad allowed me to use an adapter to download pics from an sd card. I can't find one for the new IPad. Is there one available? Any other way to do this?
-
Simple Library Import question
I have a simple question pertaining to importing. I am used to iPhoto where you import all pictures into your "Library" folder. However in Aperture I find that I can import into the "Library" (which in turn also puts the picture in a "Project") and a
-
HT201302 How save photos from iPad to a USB
How can I save the photos from my IPad into USB
-
Flashback OS X 10.5.8
Have been having some issues lately and just read about flashback. I saw a patch was available, but only for more recent OS, not 10.5.8. I do keep getting an Adobe pop up, so that is why I am suspecting flashback. I'm computer illiterate. I use m