Production confirmations for Production order
Hi all
I am using ECC 6.0 and Production orders. When I do a final confirmation to the order the order is in a 'CNF' status. Now after it is in a CNF status if I try to perform another confirmation using a CO15 then it allows me to do a confirmation with a 'warning'. If I am using a CO11 or CO11N then its a hard error. Is there a way I can get a warning message on a already Final confirmed order in tcode CO11 or CO11N?
thanks
Hi John,
You want the system to allow to confirm operation wise even though you have already confirmed with respect to order
I dont think its possible,because if you see logically -once we do the confirmation for the order system will complete the confirmation for operations too ie it will book the time,cost to the respective cost center
So logically it will not be possible to confirm the operations which are already confirmed when doing the order confirmation
If you want to do order wise confirmation then you have to cancel the order confirmation & then you will be able to do operation wise confirmation
Hope the above explantion is understandable
Revert back if you have further query
Reward points if useful
Regards,
SVP
Similar Messages
-
Product valuation for Sales order with itemizations
Hi experts,
I'm trying to find a data source which extracts Product valuation for sales order, and which is important, with itemizations. This is for the KMAT material. I tried 0CO_ACT_* and 0CO_PC_PCP_* but found no proper one.
The closest one is 0CO_PC_PCP_03 but which only extracts normal material instead of KMAT.
Points will awarded.
B'R
AaronI found it.
0CO_PC_01
Cost Object Controlling: Plan/Actual Data -
Progress confirmation for process order
Hello to all,
I want to use the progress confirmation functionality for process order. I know that it is possible for production orders, but I couldn't find respective transaction for process order. Do you know if it is possible to use progress confirmation for process orders.
BR,
NikolayThanks for your inputs, but they are not useful!
COR6 - it cannot be used once the order is confirmed at phase level;
COOISPI - it's a report
COR6N -it is the standard transaction for process order confirmation
I want to do so-called "unplanned milestone" for process orders, something similar to CO1F for production orders.
BR,
Nikolay -
Restricing CO11N confirmations for TECO orders
For production orders with partial confirmations and TECOed say TECO & PCNF, PDLV how to restrict further confirmation happening in CO11N
Thanks & Regards
Manikandan .JHi Mani,
You can restrict it the confirmations for TECO order by following ways.
1) Using User Status (T.Code BS02) - You can set both Production order and / or Prod. Cofirmation
2) User Exit
- CONFPP05 PP order confirmation.: Customer enhancements during saving
- CONFPP04 PP order confirmation: Customer-specific input checks 2
- CONFPP02 PP Order confirmation: Customer-specific input checks 1
Regards,
Dhaval -
Confirmations for Limit Orders in ECS
In extended classic scenario when creating a limit order, there is an error in process in the local PO related to the follow-on documents for goods receipt with the following error message:
'Combination of GR/IR control not allowed for external services'
It is only possible to create the order in the backend if the Invoice Only option is selected in the Limit Order, but then this means it is not possible to create a confirmation for Limit Orders!
Has anyone else come across this problem in ECS for limit orders? As far as I am aware the functionality should work with GR-based invoice verification. In the backend PO it is possible to create the same order without any errors!Monica,
My analysis till now is:
1) It is true that limit oders are not going with "Confirmation & Invoice" flag. We need to raise OSS.
(There is one additional problem with this is "The vendor master flags don't get transferred to PO" for this you will have to implement the OSS notes 956083.)
Now after applying this notes you see the standard functionality:
2) If we are creating PO with "Invoice Only" flag then there are follwoing options:
a) If the "GR based invoice" flag in vendor master is checked then the POs goes into D item category and you can enter a service sheet for them.
b) If the "GR based invoice" flag in vendor master is NOT checked then the POs goes into B item category and you can enter invoice just after PO.
I made change in V_T163Y for B item category and checked the flag for GR but then too I am not able to enter GR for item category B.
Please assign points for useful answer as applicable. -
No corresponding product found for product ID
Hi,
Trying to replicate ISU Contract to CRM, using dummy product only and did the following config:
Define DUMMY01 Product as Service product and defined as default product in ISU.
Tried to replicate ISU contract but getting error in CRM in SMQ2 as "No corresponding product found for product ID DUMM.", but product do exist in CRM.
Please suggest.
Thanks & Regards,
RaviHi Ravi,
From the error message it seems it is an issue with the numbering scheme of hierarchy. Just try to create a product with 4 char. only like DUM1 .
Regards,
Manjeet. -
Hi PM Expert,
When i am creating confirmation for PM order, system do a goods movement as a automatic without ticking goods movement button. How to set consumption after ticking goods movement and save button.
Regards,
AktolgaHi,
Please ensure you have not enabled back flushing in component tab,by which material would be issued automatically.
Regards,
Sudhakar -
Product seelection for product registration in ICSS
Hi All,
IN product selection for product registration, all the products are displayed as a column. How to make the products serachable instead of displaying all at a time.
Thanks,
Priyathanks
-
Is there any soln to display production line for process order in COOISPI?
HI,
When we run COOISPI for planned orders, the field MDV01 "Production Line" populates correctly (based on the value in the production version associated with the planned order). However, you run COOISPI for process orders, that same field is now blank.
Any pointer on how to display MDV01 in case of Process order.
Thanks in advanceThanks for your reply. my requirement is to populate the field value of production line in the CIOISPI report. I have production line assigned to production version. It does display if you see the results for Planned order but not for process order and the 'production line' field remains blank. More importantly i am trying to display the results for the same production version in case of process order,
Can you plz provide me any pointers or the way we can have production line value if want to display COOISPI for process order.
Regards,
Nitin -
Goods Receipt after Completion Confirmation for Service Order
Hi,
We have a scenario in which a Notification is used to create a Sales Order & a Service Order using the action button.
The Sales Order has a old/used product as a line item which we will consume along with some other new parts(added in the components tab in Service Order) to make a remanufactured product which we will obtain after using IW42 for Completion Confirmation. (The Service order is to carry the cost of refabrication/refurburishment & additional parts as well)
We need to do Goods receipt of this remanufactured product to bring it into stock so that we can deliver the same using the same sales order.
Is this possible? We have tried using Refurbishment order both CS/PM but have not been successful in inwarding the remanufactured product using IW8W.
Kindly do suggest possibility of using a Service Order(created through a notification) with a GR feature for the above process of inwarding. Any alternate suggestions would also be very helpful.
If this functionality can be achieved with some enhancement(custom exit, BADI etc) & some amongst you have worked on something similar , please do share your valuable inputs
Thanks & Best Wishes
VishalHi
I dont think you will be able to do Goods receipt against prodcution order using inbound delivery VL31N. Inbound deliveries are normally created for Purchase orders and then GR can be posted wrt to the inbound delivery.
Prod order is normally within warehouse only so you can use MB31 and post GR directly against Prod order.
If you can explain more about your scenario hope we may help
Please let us know
thanks -
Auto Confirmation for combined order with quantity distribution
Dear All,
we need your help that we have using the auto-confirmation for normal production order , but got the problem in combined order confirmation for final operation , in final operation we are not getting quantity distribution with respect to child order.
please suggest any BAPI is there?Not possible in standard system.
-
Confirmation for Service Order
Hi Gurus,
How to create follow-up document of Confirmation for a service order in IC Agent role
Thanks,SaratYou could use the left navigation bar to go to service confirmation tab and just click create on service confirmations, the prerequisite is you must be on the service order from which u want to create Confirmation, this will link up all the transactions your interaction record
Second way of doing it, is click on followup document from service order to create service confirmation prerequisite here is that you must have the configuration ready for creating follow up documents
Thanks
Raj -
Generating Inbound delivery based on Vendor Confirmation for Purchase order
Is there a way to create Inbound deliveries based on Vendor confirmation for a purchase order.
Here is the complete scenario.
Buyer Creates the PO for qty 100 and Date August 29
Vendor Confirms that he can supply a qty of 50 for August 29 and remaining 50 for Sep15th
Based on vendor confirmation, Buyer creates 2 vendor confirmations (AB) to match with the data received from Buyer, without modifing the PO.
Requirement:
Inbound deliveries should get created based on the vendor confirmation.
As MRP looks at Inbound delivery for Planning purposes once they are available, Inbound delivery should match with vendor confirmation data.
Is it possible to get this requirement met with standard config available in SAP.could you eventually get the answer from the docu Set Up Confirmation Control
-
EDI Confirmation for Purchase Order
Hi All,
Scenario : Our vendor is located abroad. The Purchase order is transmitted to the vendor via EDI. The vendor sends a confirmation for the PO as an IDOC via EDI. The suitation we have is that there are instances where there is a miss match( Requested item doesn't match the confirmed item) between the item in the PO and the IDOC received from the vendor as confirmation. But the PO is still confirmed. Is there a method where we identify when there is a miss match in the item.
Any input on the above would be appreciated.
Thanks
NigelHi Nigel,
You could control this via customizing purchasing->Confimrations->Setup confirmation using SPRO.
here ,you can specify the tolerance for price quantity and material.
The tolerances you define apply to all vendors. Using the enhancement MM06E001 provided by SAP, you can specify that the tolerances do not apply to certain vendors.
If the acknowledged quantities, prices, and dates vary from those set out in the PO or purchase agreement, the system issues a warning message. In this case, the purchasing document is not updated.
Regards,
Karuna -
Production cost for product preference dermination
Hi Gurus,
I have a question about preference determination for a finished product. As you can see from below screen shot, there is a value for production costs, which is used to calculate RVC. Could you shed lights where this production costs value is from?
Thanks,
RyanHi Dave,
Thanks for your reply.
Actually I checked related tables mentioned by you. However, the logic does not explain well in my case. Value from table /SAPSLL/PRVAL for value type PROD_PRICE is not equal to productions costs showed during performing material preference determination.
One more thing, I got an odd case which has production costs as minus value( -3095.21 CAD). while doing preference determination. Any idea why prodduction costs is minus? (see attached screen shot)
Regards,
Ryan
Maybe you are looking for
-
Microsoft Word Freezing Repeatedly, Application Not Responding
Just wondering if anyone else was having issues with Microsoft Word from MS Office 2008, where you open the application, you type a few sentences, and the application freezes with the spinning circle of death that won't go away until you click the do
-
I only walk because of back surgery and knee issues and I really want to track my progress on Nike Plus to encourage me to do better and it only syncs runs. If someone knows if im doing something wrong other than going to site from my ipod and trying
-
Apple configurater won't restore backup since updating to version 1.2
Since updating Apple Configurator to version 1.2, I am unable to restore from a backup. I have supervised iPad 2s. Set one up the way we want and backup. Connect another supervised iPad 2 and try to restore. Fails everytime. If I restore from a backu
-
Do we have an option to create leads directly from ELM?
Hi Experts, I have a requirement that I need to create leads directly from ELM. Is there any such option could you please any one respond and guide me. Thanks Bharath
-
CRM - "closed date" versus "last changed on"
Hello , There are Service tickets in CRM . So the user just wanst a track of the "closed date" and "last changed on" for the Service tickets . I am able to locate the field the "last changed on" in the Infoprovider 0CSRVMP08 but I am not able to loca