Production lead time report
Hi,
Given below mateiral with their lead time activity
Material A- Finish (in house prodn)
100 qty = 10 days
Low level in BOM
X- Halb (2 days)
Y-Roh (10 days)
Z-Traded goods (2 days)
Is there any report available which provide the information, if i want to plan mateiral (finish) with what period it is possible to fulfill the customer requirement. Considering all procurement and production activity.
Regards,
Rajesh
Hi Rajesh,
There is no standard report available for the leading time of FG with BOM multi levels. You can go for a Z report.
thanks and regards
Murugesan
Similar Messages
-
Hi Gurus
What report can be run to provide the average time taken from PO creation to Goods reciept? IE how do we measure actual delivery lead time
Thanks in advance
BRHello
Thanks for reply.
IF this is not , could you pl let me know the correct procedure and any standard report for measuring the Delivery time for Purcsase Order based on materials.
As per your exnample , why a person should enter the delivery date manually , it should should come by system based on PDLT maintained ..
for tht reason only we are looking to review our materials to update correct PDLT.
thanks.. -
Hi,
Would like to have a report on Lead time between PO Date & GR date.
Ideally the report should show the PO Number, Date,Material, Mat. Doc Number & GR Date.
Though ME80FN shows by clicking the PO history, But our user would like to have in a single line item.
Is there any other Standard Report to get the above data?
Regards,
VengatHi,
There is a standard report that shows the actual average LT compared to the master data definitions. You can also see the details, and even update master data automatically if you want; WPDTC.
Regards,
Mario -
View of lead time of product in APO
In R/3 under transaction C203 we view the time required for different operations to manufacture a product.
Where in APO does the inidividual operations time appear in APO. Specially the leadtime.
Regards,
ChetanHi Siva,
Thanks for your reply. but that data is maintained in R/3 Material master in MRP2 view.
my question is related to production lead time maintained in transation C202 in R/3
Regards,
Chetan -
Lead time values are not appearing in the report for current year.
Hi friends,
Iam checking a report in production. where lead time values are displayed as 0 for 1 key figure lead time3 (w/0 dim) . i found there is a formula for this it shows like NODIM ( 'Lead Time 3' ).and there is a value for cal.lead time
how can i get values in the report.
Thanks ,
VRV.Hi,
Although your question is not clear, I understood that the formula built on that KF is NODIM. Basically it means, units of measurement is not considered when calculating.
Eg: 5 Minutes + 5 Kilograms = 10
You please try to analyze your KF by the above logic. Then you would be able to figure out why the data is not appearing in the report..
Assign if helps...
Regards,
Suman -
Target and Actual Lead time in MCP1 report
Dear Experts,
In MCP1 report, what is Target Lead Time and Actual Lead Time. How it is calculated?
Thanks in advance for your valuable replies.
Regards,
JejeshHi,
Target lead time
On the operation level, it is the time period between the scheduled
input date at the work center (target input) and the latest scheduled
finish of the operation.
The target input date is calculated through the scheduled execution
finish of the previous operation.
On the order level it is the time period between the scheduled start and
the scheduled finish.
and
Actual lead time
At operation level, the time between the input date at the work center
and the completion confirmation date (the total from queue time,
execution time and move time).
When calculating, the input date is determined via the completion
confirmation date of the preceding operation. The process-dependent
wait time of the preceeding operation is subtracted.
At order level, the time between the reported start date and the finish
date (the total from execution times and transit times of the operations
as well as the order floats before and after production).
Regards,
Rajesh -
MM Report for Reorder and lead time
Hi,
Can anyone suggest me a report that can show information by materail such as min./max. quantity, re-order or safety stock, and replensihment lead time.
Thanks
Atifyou can create the query using MARC or just go se16 adn enter the MARC table and pull the data.\
Displayed Fields: 8 of 8 Fixed Columns: 2 List Width 0900
Material Plant Reorder Point Safety stock Min. lot size Max. lot size Total RL time Min SafetyStock
MATERIAL Z001 0.000 0.000 5,000.000 350,000.000 0 0.000 -
Lead Time Demand on REORDER POINT REPORT ??
Hi ALL,
Hope you all doing greate , I am very new in Re order point Inventory Planning Method. I have done all the configuration as;
i - Creates an Item and assign it to the specific IO where I am selection the Planning method as Reorder point and enter the other paramters under the lead time tab I am seleting the total lead time as 5.
I have define safty stock as 100 quantity.
I have configure the Forecast Set and forcast under it which contain an Item with Current Quantity is 1000 now I have call the Report to run so I am getting the rest of the thing except value Lead Time Demand ??
kindly help me in this regards, I would be so kind of you.
Thanks
Mohammad YounusHi,
There is a standard report that shows the actual average LT compared to the master data definitions. You can also see the details, and even update master data automatically if you want; WPDTC.
Regards,
Mario -
Report Supplier Lead Time - Days
Hi All,
Can anybody give me the characters, key figures, CKF's, RKF's and other fields that are usually used in Supplier Lead Time - Days Report in general irrespective of the requirement.....come up what ever you remember from your side.
Thanks All,Nevermind
-
Hi Experts,
Do we have Standard report to monitor PO Lead time. (Time taken by Vendor to fulfill the Order)
Regards,
JackieHi,
You can use the report MC$K to check the delivery date vairance for the vendor with respect to material delivery.
The delivery date variance is calculated with respect to PO Delivery Date and GR Posting Date.
To execute the report, the delivery date variance needs to be defined in transaction code MCFC at Purchasing Org. level.
Regards,
Bijoy Kumar -
Material report showing lead time & min order quantity?
Hi,
Is there a report which I can download which shows by material, the lead time and minimum order quantity?
Thanks
KeeleyWe don't have access to any query writing so if it's not possible to get both fields on one table, can I run two reports?
OR...
is it possible to change the ME1M report to display/export horizontally in a table type format rather than wrapped?
Edited by: Keeley B on Sep 23, 2009 7:58 AM -
Re: report for lead time of material
Dear Gurus,
I just want to know is there report to see the lead time of material. Kindly suggest me which is the t-code available
Regards,
RajashekarHi,
You can see the lead time in Report- MCE7 (T Code) for material analysis, here yo will get lead time delivery time of material as per Material group, Vendor,purchase Org. If you want to get material number ,after results displayed choose from menu settings > characteristic display > key & description (or just key) , then
choose from menu settings > column width and extend the length to e.g. 59 (18 material number + space + 40 description)An alternative way is building query taking into consideration Table MARC. Thanking you. -
Report of List FERT goods' standard production labor time
Hi Expert,
Is there a standard report can list all FERT goods' standard production labor time?Bean,
you mean the labor time in routings or recipes ? There are some reports as CA51 that list the routings for a plant but it is not specific, as the labor time is not a fixed parameter but depend the way you define the work center. The labor time can be the first , second, etc. standard value in the operation.
Regards -
Product Specific Transportation lead time
We need to maintain different sourcing lead times for different products in the "Transport duration" field of the "Means of Transport" of the transportation lane. The transportation lane exists between the Supplier and the DC. A single vendor would supply different products which may have different lead times.
Could anyone kindly give us pointers as to how this could done in the TL ?
Best Regards,
MukundanHi
as well as Sanjog's answer another option is to keep just one TL MOT record and instead use the Goods Issuing time on the product Location record to account for the different leadtimes of product from a supplier. This time is added to the transportation time on the TL. It is the "GI Processing Time" field on the GR/GI tab.
Which method you use depends on the amount of different leadtimes you have from a supplier (a few and I would use Sanjog's method, more and I would use the GI time). The GI time can also be integrated in with the transportation planning of deliveries in the ERP system as well to give better visibility of milestones in the delivery tracking. (e.g. you have a planning point when the goods should be ready to ship as well as when they are due).
Regards
Ian -
Contract renewal lead time in standard sap?
Hi,
I need a report which can tell me per material (contract based), what is the lead time to renew the contract? Average consumption in production taken into account!! Case:
contract quantity 1000 PC
average consumption in factory over the past 4 months : 50 PC.
contracl renewal lead time 4 months.
Actual stock level is 400.
I assume a lot of purchasing people like to have such a report, but does it exists in SAP or does any body have a clue where to look?
Does anybody have the same experience, that this report is missing in SAP? Or do I really need (as proposed solution) work with queries?
Best Regards,
Eric.Dera Eric,
It seems like you combine between Purchasing data and inventory data, so you need to custom a report that meet your detail requirement for 1 preview.Or you can run several SAp standard report and combine it in excell or you can use SQVI.
Maybe you are looking for
-
Adobe Bridge CS5.1 - Edit Export Preset Crash
I have successfully duplicated this issue on multiple machines, multiple user accounts running variations of 10.7 - 10.7.2. All Adobe updates applied. Open Bridge CS5.1 > Click on EXPORT Panel tab > Save to Hard Drive (double click to edit) > choose
-
How do I make my workhorse Samsung ML-1740 printer work with Yosemite 10.10.3?
How do I make my workhorse Samsung ML-1740 printer work with Yosemite 10.10.3?
-
Profit Centre Hierarchy Change and Profit Centre Budget
Hello Friends For better view of Profit Centre Reports we are planing to change the Profit Centre Hierarchy. I wanted to know that, are there some Specific Points which we have to take care of, before changing the Hierarchy? Will some other settings
-
Wish: File::Save As instead of Export
I wished Apple would improve the usability of the entire iWork'08 suite by elminating the File::Export menu item and instead put a combo box containing all available formats in the File::Save As dialog. File::Export doesn't even have a keyboard short
-
Hi, when I add a DVD cover to a movie, this changes the permissions in leopard. I have to chmod the dir again to edit the info. Very irritating. Anybody any tip or is this a bug?