Production order finish date

While creating a production order  I  am using forward scheduling order start date is today and finish date proposed by the system is 07.02.2011 but the problem is in house production time is 10 days. then why the system has proposed finish date as 07.02.2011 instead of 14th or 15th or 16th

Dear Kumar,
Always system picks the timings from routing when you create production order manually
System will not check the filed in house production time from material master while creation of production order
So check in routing, for the timings that you have given
It will solve your issue
Regards
Madhu

Similar Messages

  • How Production Order finish date and time is being comptued by SAP?

    Hello Expert,
    How Production Order finish date and time is being comptued by SAP? for example, we create a Production Order via CO01, the basic start date is 29.09.2008 and time is 04:00 it gives us basic finish date is 29.09.2008 and time is 13:28.
    how does SAP compute the time 13:28 as it finished time
    Please explain me briefly.
    Thanks
    Ryan

    Hello Guys,
    When we create Production Order in R/3 the time is calculated by routing but it is extended at SetUp machine time. It is not correct?. SetUp imachines time used only for first Production Order for the same product and it is plan manually, for others Production Order we need calculate time for production without SetUp machine time being pick up to compute finish time. how could we achieve this? only those Machine time will be check.
    thanks

  • Can GATP confimed date come from production order finishing date??

    Hi Expert,
    I have one question to ask.
    in the GATP , I want to the APO system can consider the production ability , that is, when I create a sales order, the system will make  a GATP check in APO, if there is no enough stock, the system will create a PPDS planned order and return the planner order finsihed date as the schedule line confirmed date.
    I do not know this is possible or not??
    I hope some expert can help me to solve this problem
    thank you in advance!

    Hi Liu,
    Why Planned order date.. It could be Production order date (planned order release date) + inhouse production time + Transporation lead time + GR processing time (at the original location where the order is placed) ..that should determine the material availability date. CTP exactly does this. Make sure that the "replenishment lead time is switched off" in the product-location master (in fact this is location independent)- as this take precedene over everything else.
    Also ensure that that end of checking horizon is larger than the interval established above, else MAD could be much earlier. Also enure that transfer of requirements is set both at header and schudule line level for CTP to work.
    Regards,
    Loknath

  • Production finish date is later than order finish date?

    In my company, most of the plan orders in MD04 have an exception message "64 Production finish date is later than order finish date". The plan strategy of the materials are 40. The plan orders are created from Scheduling Agreements or Independent Requirements.  We set 'Scheduling' as 2(lead time) in the MD01/MD02. The self-production time in material master data is 0. The schedule margin code is 000 which all the parameters are 0.
    For a example, we create a requirement on 2007.04.24. After MRP run, plan order generate. It's basic date will be 2007.04.24, but the production date IS 2007.04.25. All the plan order like that, the production date are always later than the basic date for one day.
    Could someone tell me why? and how to settle this problem?
    Thank you in advance!

    Hi,
    check scheduling parameters for planned orders and scheduling parameters
    for production orders.In that set the various indicators like
    adjust basic dates to order start date
    do not adjust basic dates to order start dates and try.
    Tcode opu3 / opu5
    Thanks,
    s.nandhakumar

  • Set Order finish date in planned order on Production order creation CO41

    Hi experts,
    I'm trying to set the order finish date, field SFC_POCO-PEDTR on transaction CO41, into Scheduled finish, field CAUFVD-GLTRS, of production order transaction.
    The issue is get the value of PEDTR. For change the value GLTRS i'm using the exit PPCO0007 and it works, but i haven't the value of field PEDTR.
    I hope to have been clear.
    anybody can help me??
    Thanks in advance
    Marco
    Edited by: Menegazzo Marco on Aug 3, 2010 5:20 PM

    Hi  DwarakanathS         
    Thanks for you reply....
    But if in the exit i try with the code you suggest, when i do the assign:
    FIELD-SYMBOLS <my_fs> TYPE SFC_POCO.
    ASSIGN SAPLCOUP(SFC_POCO) TO <my_fs>.        
    the program give me an error "Field "SAPLCOUP" is unknown. It is neither in one of the specified"...
    and if i try with this:
    FIELD-SYMBOLS <my_fs> TYPE SFC_POCO.
    ASSIGN 'SAPLCOUP(SFC_POCO)' TO <my_fs>.        
    the error is "SAPLCOUP(SFC_POCO)'" and "<MY_FS>" are type-incompatible."
    what's wrong?
    thanks
    Marco
    Edited by: Menegazzo Marco on Aug 4, 2010 10:16 AM
    Edited by: Menegazzo Marco on Aug 4, 2010 10:53 AM

  • BOM Explosion with order finish date

    Hi,
    In transaction OPPQ it is possible to configure the BOM explosion date used by MRP and creation of a process order (see SAP NOTE 506345).
    I suppose this setting is also considered when re-reading master data during release of an order.
    The field BESAL can have the following values:
                BOM explosion number/order start date
    1     Order start date
    2     Order finish date
    3     BOM explosion number/order start date
    4     BOM explosion number/order finish date
    What I do not understand is that value 4 also end up in using the order start date when re-reading master data. Here the function module CO_ZF_VALIDATIONDATE_DET is called which contains the following coding:
    + Festwerte Feld BESAL:+*
    * ' ' Seriennummer/Eckstarttermin
    * 1   Eckstarttermin
    * 2   Eckendtermin
    * 3   Seriennummer
    IF T399D-BESAL <> CHAR2.
    * Auflösung mit Starttermin
    u2026
    ELSE.
    * Auflösung mit Endtermin
    u2026
    ENDIF.
    which says only use the Order finish date if BESAL has the value 2. The comment showing the possible values gives me the impression that SAP simply forgot to adapt this coding when splitting the value 3 (prev. only BOM explosion number) into 3 BOM explosion number/order start date and 4 BOM exlosion number/order finish date.
    On the other hand the SAP Note mentioned above documents this behaviour.
    Does anyone know the reason why value 4 (BOM exlosion number/order finish date) results in using the order start date ?

    hi,
    The defination in OPPQ is only working for the MRP, when the planned order is created.
    Then the explosion date will be copied from planned order to production/process order when you convert the planned order.
    However, when the production or process order is created manually, or when you do a re-read master data process, then a different BOM explosion date process will be carried out as described in the SAP note 506345, it has explained the behavior clearly base on the different value of paramter:
    V_T399D_S-BESAL = initial, 1, 3 or 4
    V_T399D_S-BESAL = 2 (Explosion with order finish date)
    So there is no problem to have different behavior of planned order and production/process order.
    Regards,
    Rachel

  • Req. delivery date and plan order finish date relationship

    Dear Experts,
    I have a question on setting the req. delivery date and plan order finish date relationship. Now, I want the plan order finish date is one day before the req. delivery date, is it possible to set it in configuration? Please advised! Many thanks!
    Regards,
    Matt Yim

    Matt,
    Please use a schedule margin key(SMK) in the material master MPR2 view which has float after production defined as 1day.
    If there are no SMK with that defination then you can define you own in customisation and assign the same in the material master. (SPRO--->Production ->MRP->Planning ->Scheduling and Capacity Parameters->Define Floats).
    Regards,
    Prasobh

  • Production order - Master data explosion date

    Dear Team,
    I am creating the production order in CO01. While creating the production order, i am choosing the backward scheduling. Since i have selected the backward scheduling, i have given the finish date as "27.02.2012". And in the tab "Master Data", i was refering the field "Explosion Date". The explosion date is been displayed as 20.02.2012 (Routing and BOM explosion date).
    How this explosion date been determined based on the scheduling types (forward scheduling, backward scheduling)?. Is any configuration to be done to calculate this explosion date?
    What is the importance of explosion date in production order? will it affect the production order? Because in my production order the explosion date occurs in future ie, 20.02.2012. (as mentioned above).
    thank you
    psk

    Dear PSK,
    The explosion date refers to the date when the BOM & Routings are exploded on the orders i.e. applied. The explosion date can be controlled based on the settings in the SPRO.
    Go to SPRO - Production - MRP - Plant parameters - Carryout overall maintenance for plant parameters  (Transaction: OPPQ).
    In the plant pameters for a particular plant and in the tab 'BOM Explosion' we can determine how the system should can calculate the explosion date.
    Explosion date is controlled based on the order start date or finish date. If  the production order is added manually the system determines the explosion date as follows:
    Case 1:
    If you have specified the order start date on order creation the system takes this date as the explosion date for the bill of material.
    Case 2:
    If you have specified the order finish date on order creation the system calculates the explosion date from the order finish date minus the in-house production time defined in the material master.
    As per your example it looks like in your system the explosion date is controlled by the 'Start Date' due to which the explosion date equals the order start date.
    Hope this is helpful. Pl let me know if you need further help.
    Thanks,
    Satya

  • BOM explosion date after order finish date

    Hi
    We have issue with BOM explosion date. In process order, BOM explosion date is geting calculated after order finish date.
    Any idea why this is happening.

    Hi,
    Just to understand the issue better, can you list the scheduled and basic dates on the order.
    Anup.

  • Profit center field in production order master data in KKF3

    Hi GUrus,
    is there any way of mass updating the profit center field in production order master data in KKF3 transaction. PLease help
    Anusha

    HI charlie,
    When i try to change the profit center, the system gave this message. We already have a profit center for a production order and we need to change the profit center, That is when we are getting the errror message.
    You have changed the profit center from AR00620800 to AR00620301. This is only allowed when the corresponding configuration was made in Customizing. Then this message is only a warning, which you can ignore.  PLease help
    Thanks
    Anusha

  • Production Order Completion date

    Hi All,
       Can I know from which table can I get the production order completion date.

    Priya,
    There are different thoughts as you did not clearly explain what you meant by Order Completion date.
    If you are looking at based on,
    Confirmation then AFKO-GETRI
    Goods Delivery then AFPO-LTRMI
    If you are looking at Based on Status CLSD then you need to find the status change document using table JCDS-TJ02 with referance to the Object Number of the Production order from AUFK table.
    Regards,
    Prasobh

  • Production Order  Start Date

    Hello All,
    I am facing a problem in a Production order.When I am trying to change the  Production order Start date  and saving the changes I am getting a termination error (program termination).
    The error message is as below
    Nested call of PERFORM ON COMMIT: NESTED_PERFORM_ON_COMMIT caller: SAPLMCEX program: SAPLMCEX form: MCEXLOG_WRITE_04_DIA
    Regards
    Dhananjay

    Hi
    Check for the order scheduling parameters and confirm that the order in past are also allowed.
    Krishna

  • MRP Planned order finish Date calculation (Planned delivery + GR Proc.time)

    Dear Gurus,
    Currently in our system, when MRP runs, Planned orders are created and the order finish date is calculate based on Purchasing processing time OMEW + Planned Delivery time from Material Master + GR processing time from material Master.
    My business requirement is that,  system has to take only Planned Delivery time + GR Processing time and exculde Purchasing PRocessing time.
    I cant make it Purchasing Processing time as ZERO - because this is used for other Purchase orders and KPI will be affected for procurement department
    Now we are going to Automate the Purchase orders for Materials - if outline agreement exist.
    How to make system settings for a MRP run, the Planned order finish date - should consider only Planned delivery time from Material master + GR Processing Time ( it should exculed Purchasing PRocessing time). Is it posssible? if not by any user exit, ABAP coding should be done?
    gurus please advice!
    BADI : MD_PLDORD_CHANGE - is this can be used?
    Please advice
    Regards
    RS
    Edited by: RS on May 18, 2010 10:22 AM
    Edited by: RS on May 18, 2010 10:33 AM
    Edited by: RS on May 18, 2010 1:34 PM

    Let me check, if I can find a way to paste /afs/md04 (AFS Envirnoment) screen shot . But in the mean time following are the
    details
    IHPT  - 12 days
    GRPT - 0 days
    SMK  - 000 (Op Period, Float After Prod., Float Before Prod.,Release Per. - 0 days)
    Thanks,

  • Production order basic dates (start and finish) in past

    Hi,
    My clinet has got one requirement where in they want to create an production order with past date (Basic start and finish). I found one way to achieve this by selecting the scheduling type as "Only Capacity requirement", but the disadvantage is that the order will not get scheduled.
    Do you know any other method to achieve this functionality?
    Thanks and Regards
    Purushothaman Nagarajan

    Dear Friend,
    As i said, in Production order, under Production order - Setting - Scheduling maintain the number of days in past (says 100 days).
    Now in below select the scheduling type as backward scheduling and in Finish date give the date which is in past and now enter (or schedule the order). Because of this system will propose the start date which will also be in past.
    Regards,
    JItendra

  • Production order - post date - cannot change

    Hi,
    could anybody, especially from SAP, explain me the background and reason, why user cannot change the PostDate field in OWOR table of production order after the order is created?
    And seccond related question is, why item gen. entry and exit are with date, which is in production order as PostDate and user cannot change it as well?
    Real situation:
    User creates production order and sets as postdate April 2008. PM will order the material necessary for this production order and the material will arive to the stock at the end of May. At the end of May is posting period for April blocked already.
    So now user has no chance without opening the posting period to finish the production order.
    Opening and blocking posting period isnt solution for user. Im asking, because now we are implementing new customer and I know, that there will be the same problem and I would like to solve it before he will start.
    Thanks a lot for make it clear for me.
    Petr
    Edited by: Rui Pereira on Aug 6, 2008 4:03 PM

    Dear Petr Verner,
    1st to clarify your question currently It is not possible to change the Order Date ( Posting Date) for the production order ( to set as "Yes" in OWOR).
    2nd, For any change you need in the system behavior, you need to go through Note: 1028874, and post the message accordingly.
    3rd on UDF ( User Defined Field), I suggested you to attach and UDF for the Production order (UDF as Date format), and you can record the changes ( date when you want the order to be changed).
    Note:- UDF will not effect accounting, but only for record and information purpose.
    4th As I understand form your example, you say that An Production order A created in April, its Child Items comes in May.
    Later you make Issue for Production. Which you say the JE for Issue for production will happen in April ( though the goods have come in May).
    And Receipt for Production will happen in May, which is ok.
    Please clarify the 4th point.
    Regards,
    Raghu N
    SAP Business One Forums Team

Maybe you are looking for

  • Error Message when Starting Windows 7

    Whenever I start or restart my computer I receive an error message that says: "the procedure entry point sqlite3_wal_checkpoint could not be located in the dynamic link library SQLite3.dll" There is a button that says "ok" under it. How do I fix this

  • Is there a way to save an image file as a jpeg and add -web or -print to the file name?

    I am trying to find a way to save my image file as a jpeg and add -web or -print to the existing file name.  This way I can easily see which files are lower resolution for web posting or high resolution for printing.

  • Cannot create 'download' page for inline PDF viewing with IE

    Description of Problem: Typically, when you want to transfer a file to the client via code (cuz the file is in a db, for example), you create a page that will change the response headers and then spit out the file for them to download. This works, ho

  • Cloud mail not appearing on my computer

    Some mail messages are appearing on my iPhone but not onto my laptop, I'm fully clouded up and need to work on the emails on my mac, any ideas as to why this would suddenly happen? All has worked well up to now.

  • FI Invoices -Invoice Amount and Invoice PaymentAmount

    Hi, Where can I find these values Invoice Amount and Invoice Payment Amount for an AP invoice.I need table name and column name ex:BSIK-WRBTR. (Payment amount  apart from PAYR/REGUP tables) If some one could point me to links to throw some light on t