Production order schedulling

Dear PP Gurus,
My order is 30000 qty. I used operation splits & overlaping. In first work center out of 6 splits used 1 split & 2500 qty. overlaping, in second work center out of 370 splits used 30 splits & 6000. In third work center no splits & no overlaping.
When I am creating production order with forward schedulling ( forward is the requirement), how many times I am clicking on schedulling that much times dates are changing. I don't know why? please please explain
Jayesh Narvankar
SAP PP

until unless you firm the order or if the order is not in planning time fence, scheduling dates will be automatically changed depending on the new requirements coming.

Similar Messages

  • Daily production order scheduling

    Hi Experts,
    i am using maximum lot size procedure  for the MRP Run and after MRP ,planned orders are generated based on the maximum lot size and these planned orders are further converted in to production orders.
    my requirement is how to schedule the production order on daily basis,please suggest me an appropriate solution.
    Thaks in advance.
    Regards
    Srinivas

    Hi,
    Production orders scheduled start dates are generating for the whole month for a material as same date like first working day of the month (Here i am using maximum lot size) and the orders can be only scheduled for the particular date in order dispatching transaction.
    Example,
    Material : X
    Maximum lot size : 1000 in MRP 1 view
    PIR Qty : 01.08.2008  1000 Pcs
    after MRP,
    10 Planned orders are generating with schedlued start date as 01.08.2008.
    after converting all the 10 planned orders in to production orders , then all the 10 production order are generated with scheduled stat date as 01.08.2008.
    While dispatching the production orders in CM25, the system is showing all the work centres are overloaded on 01.08.2008, because system is considering all the production order are start date as 01.08.2008.
    But  i want get the production order scheduled start dates based on the capacity availability  ,so please suggest me the appropriate solution.
    Thanks in advance.
    Regards
    Srinivas

  • Production Orders - Scheduled Finished Date Basic Finish Date

    In production orders, it is being noticed scheduled finished date lies further than basic finish date, what could be the
    reason? what configuration should we need to do in order to make scheduled finish date matches (or) lies before basic finish date

    Eshwer,
    Basic dates of production orders can be made to match scheduled date.
    Config is at OPU3.  Under the "adjust scheduling" section, select either 1 or 'blank'.
    Best Regards,
    DB49

  • Production Orders: Scheduling Problem

    Hello
    I have a scheduling problem.  I want the system to calculate the production order dates.
    I have maintained the following
    1.      Work Center:  A formula to calculate the duration.  I have marked the u201Crelevant to finite indicatoru201D in the Capacity Header Tab.  I have also maintained the available capacity as 24 Hrs.
    2.     Routing:  I have maintained the values for the standard value keys
    3.     SPRO:  In scheduling parameters for the order type, I have marked u201CGenerate cap requirementsu201D and u201CSchedulingu201D;  In the production scheduling profile, I have marked u201CSchedule orderu201D (on release) & u201CFinite Schedulingu201D (Availability check).
    But the production order is not getting scheduled & the start & end times are the same.  I get the error u201CNo req/capacity exists or not relevant for finite schedulingu201D.
    Can anyone guide me as to what I am missing?
    Best regards
    Tom

    Dear Tom,
    Please check following;
    1. Your operation contol key; whether it allows scheduling.
    2. scheduling parameters for production order on OPU3: Please select proper combination of plant and order type and tick scheduling and generate capacity requts indicators in detailed scheduling tab.
    Please revert back if problem persist.
    Best Regards
    Uday

  • Production order scheduled start/finish dates

    Hello experts!
    I have a problem with prod. order scheduling. I set the date '07.05.2007' as order start/finish date. If I run <i>Functions -> Schedule -> Order</i> (or save the order) SAP set these dates to '02.01.2008', and scheduling also to '02.01.2008'. The scheduling type is <b>Forwards in time</b>. Scheduling margin: everything is 0.
    I have checked the <b>work center capacity</b>:
    from 20.04.2007 to 31.12.2007
    Lenght of cycle: 1 Start: 06:00:00 End: 23:00:00 Break: 00:00:00 Cap. util.: 100
    from 01.01.2008 to 31.12.9999
    Standard avail. capacity
    (01.01.2008 is non-working day)
    Routing exists for this material (valid from 02.03.2007).
    Based on what does SAP calculates these dates?
    (SAP 46B)

    Hello guys!
    I have found the reason and also the solution. It's a bug in SAP (46B). When it happens?
    1) Open work center
    2) Create interval with minimum 2 shifts and save
    3) Delete first shift of the interval
    4) Check table kapa -> field SCHNR (shift sequence number) for the 1st shift in this interval will contain number 2.
    If SAP calculates the scheduled date for order it excludes this interval from calculation. We had an interval 20.04.2007 to 31.12.2007 with deleted first shift, so the next workday for SAP was 02.01.2008.
    I have created a function, which can solve this problem:
    FUNCTION z_pp_fix_capacity_data.
    *"*"Local interface:
    *"  IMPORTING
    *"     VALUE(I_WERKS) TYPE  WERKS_D
    *"     VALUE(I_ARBPL) TYPE  ARBPL
    *"  EXPORTING
    *"     VALUE(E_CHANG) TYPE  INT4
    *"  EXCEPTIONS
    *"      FOREIGN_LOCK
    *"      SYSTEM_FAILURE
    *"      NOT_VALID_WORK_CENTER
    *"      DATABASE_UPDATE_FAILED
      DATA: l_kapid LIKE crhd-kapid,
            l_schnr LIKE kapa-schnr,
            l_error TYPE c.
      DATA: ikap LIKE kapa OCCURS 200 WITH HEADER LINE.
      CLEAR: e_chang.
      COMMIT WORK.
    *- Get the Capacity ID of the work center
      SELECT SINGLE kapid
               INTO l_kapid
               FROM crhd
              WHERE werks = i_werks
                AND arbpl = i_arbpl.
      IF sy-subrc <> 0.
        RAISE not_valid_work_center.
      ENDIF.
    *- Lock the work center
      CALL FUNCTION 'ENQUEUE_ECARPL'
           EXPORTING
                arbpl          = i_arbpl
                werks          = i_werks
           EXCEPTIONS
                foreign_lock   = 1
                system_failure = 2
                OTHERS         = 3.
      IF sy-subrc <> 0.
        CASE sy-subrc.
          WHEN 1.
            RAISE foreign_lock.
          WHEN 2.
            RAISE system_failure.
        ENDCASE.
      ENDIF.
    *- Select the whole capacity into internal table
      SELECT *
        FROM kapa
        INTO TABLE ikap
       WHERE kapid = l_kapid.
    *- Sort
      SORT ikap BY versn datub tagnr schnr.
    *- Set the correct sequence number
      LOOP AT ikap.
        ON CHANGE OF ikap-versn
                  OR ikap-datub
                  OR ikap-tagnr.
          l_schnr = 1.
        ENDON.
        IF ikap-schnr NE l_schnr.
          ikap-schnr = l_schnr.
          e_chang = e_chang + 1.
          MODIFY ikap.
        ENDIF.
        l_schnr = l_schnr + 1.
      ENDLOOP.
      IF e_chang NE 0.  " If change found, recreate data
    *- Clear error indicator
        CLEAR l_error.
    *- Delete old data
        DELETE FROM kapa WHERE kapid = l_kapid.
    *- Insert data
        IF sy-subrc EQ 0.              " Delete OK, insert
          INSERT kapa FROM TABLE ikap.
          IF sy-subrc EQ 0.            " Insert OK, commit
            COMMIT WORK AND WAIT.
            clear: l_error.
          ELSE.                        " Insert failed, rollback
            ROLLBACK WORK.
            l_error = 'X'.
          ENDIF.
        ELSE.                          " Delete failed, rollback
          ROLLBACK WORK.
          l_error = 'X'.
        ENDIF.
      ENDIF.
    *- Unlock the work center
      CALL FUNCTION 'DEQUEUE_ECARPL'
           EXPORTING
                arbpl = i_arbpl
                werks = i_werks.
      IF l_error NE space.
    *- Raise exception
        RAISE database_update_failed.
      ENDIF.
    ENDFUNCTION.
    I hope this helps someone! Anyway! Thank you for your answers!

  • Process order scheduling based on in-house production time.

    Hello!
    I have following problem. My SAP system is configured in that way that process oedrs are schedulled based on times saved in master recipies. When I input data to in-house production time in master data for materials and make new process order, this time is not
    taken into account.
    Where I have to change configuration to use in-house production time from material master data to make scheduling process orders.
    Regards
    Bogdan

    Dear
    Process Order /Production Order scheduling ( Lead Time Scheduling )  based on the Operation timings in the routing not based on the Material Master In house Production Time in Work Scheduling View .
    If you are loking for Basic Date Scheduling then it will happend based on material master , scheduling margin key  at material master level .
    It depends the selection of Schedueling indicator while excetion of MRP in MD02 .
    In case of Process order specifically , you need  to schedule the Master Recipe and check whether operations are getting scheduled, if it is not then you need to first the problem, which may be because of wrong "Forumla" or paramater assigned in resource or the resource is not maintained for Finite scheduling (capacity header).
    Master reciepe can be schedule in the change transaction C202, and from menu you would find the option to schedule the recipe .
    Also  check the OPU3/OPU5-Define scheduling parametres wether scheuling , adjust scheduling , scheuling type , logs all are in place .
    Check and revert
    Regards
    JH

  • Scheduling type for production order.

    Hi Gurus,
    i have some doubts about production order scheduling. i have run a scenario OF MTO to Understand The Scheduling. i had created a BOM with  two components. The inhouse production Time of header Material is 3 days.and the scheduling Margin key is op2   flt aft1  flt bfr 1    rl per 2
    after creating a sales order i had run MRP in MD50 by selecting scheduling 1 Basic Date Determination. it has taken the 3 days of in house production time and praposed dates.18th as starting date and 20th as finish date.and planed opening period is in past. and it has not praposed any scheduled dates in planned orders.
    if i convert the planned order in to production order it is praposing the scheduled dates.
    scenario 2.
    if i run the mrp for the same order by taking scheduling type as 2 lead time scheduling.       in planned order itself it is showing sheduled start date and scheduled finsh date. (which not shown in basic date run).
    1.so is it mean that what ever the scheduling type we are using in MRP run is only applicable to create Planned orders only while convrting the planned orders in to production order dates will be re detemind. is this currect or wrong?
    2.in which scheduling type system will not consider the scheduling margin key?
    please help me to understand these questions.
    Thanks&regards,
    Venkat Bolla.

    Hi Venkat,
    When MRP is run with '1' Basic Scheduling - Schedule Margin Key is not considered. As you rightly observed it considers the Inhouse Production days mentioned in materials master for fixing the start date. This is exactly to days.
    When MRP is run with '2' Lead Time Scheduling - Schedule Margin Key is considered. Dates are calculated from Routing and Capacity requirement calculations are also done. Here calculation are exact to the seconds.
    Schedule Margin Key takes effect only for lead time scheduling. Production dates are calculated from the float times of the SMK in the material master and times from the individual operations maintained in routing.
    When planned order derived from Basic scheduling is converted to production order it is subjected to lead time scheduling and thus production dates are calculated
    Refer to the below discussions on the same topic.
    http://scn.sap.com/thread/1535577
    http://scn.sap.com/thread/1554548
    Thanks & Regards,
    Ramagiri

  • How to change operation dates in Production Order /Capacity Leveling

    Dear Experts ,
    We are using ECC 5.0 .In production order , scheduling happing as Backward  based on the Sales Order Delivery Date .I am doing the following :
    1.Demand as Sales Order with Delievery date : 20.03.2010
    2.Running MRP with Lead Time Scheduling -2  in md02 and converting the Planned Order to Production Order .
    4.Production Order have following dates :
             Basic Finsish Date : 21.03.2010
             Basic Start : the day Pl.Or--Pr.Ord
             Schedule Start : 15.03.2010
             Schedule Finsish : 17.03.2010
            Schedule Release : 13.03.2010
    5.In schedueling margin key :  Float Before Production : 3    , FAP : 3 , Release Period : 2
    6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
    7.In operation : Op1  : Start Date  : 15.03.2010    Finish Date: 15.03.2010
                             Op2 : Start Date : 16.03.2010      Finish Date : 17.03.2010
                             Op2 : Start Date : 17.03.2010      FD : 17.03.2010
    Question :
    1.How to change the Operation dates  in Production Order Operation over view screen ? Today,  operation over view screen , Start date and Finsih Date  of individual operation are not changable with in Production Basic Start /BF date  or beyond .It is only changing based on the Standard Value : Labor
    2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per   Production Order and Operation combination ) based on capacity availale in advance dates? I am using  Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning  ,
    How to solve this above issue in scheduling operation and capacity distribution .
    Regards
    JH

    Closing the thread

  • Material requisition against production order

    Dear all,
    How do i put material requisition against production order. Kindly give me the t-code and total path till material issue from a particular storage location. i.e
    --> requisition against Production order for a storage location
    --> Transfer posting by movement type
    Thanks

    Hi,
    Procurement of RM: -
    1. MM01 - First of all create materials (RM, SF, FG)
    2. CS01 - Create BOM (FG > SF > RM)
    3. MD61 - Planned Independent Requirement for FG
    4. MD02 - MRP Run for FG (System will create Planned orders and PRs automatically as per procurement key - E, F and X in Material Master)
    5. MD04 - Stock / Requirement List OR ME5A - PR List
    6. ME21N - Create PR w.r.t. PO
    7. MIGO - GR w.r.t. PO (Movement Type - 101, Capture Excise invoice here)
    8. J1IEX - Post Excise Invoice
    9. MIRO - LIV for PO
    Goods Issue of RM: -
    1. CO40 - Convert Planned Order to Production Order (Schedule, Release Order)
    2. MIGO - Goods Issue > w.r.t. Production Order (Movement Type - 261) - You can also use MB1A for GI against Order
    3. CO11N - Confirm Production Order
    4 MIGO - Goods Receipt > Order (Movement Type - 101)
    5. KO88 - Order Settlement

  • Change Log for Production Order

    Hello Gurus,
    I have a requirement where the production order scheduled finish date should not be changed in the BW reporting though it changes in the R/3.
    For the same. I need to know if there is any way i can get to know if there were any changes to the scheduled finish date (GLTRS). I checked the CDPOS and CDHDR, but did not find any entries for these changes..
    Please let me know if you have any details on where the change documents history would be maintained.
    Best Regards
    Avinash

    Please check the Order and Click on the Status, then go to extras and check the change documents for all.
    this will display all the changes against the order, with dates and user names.
    From this try to get the report developed.
    Or get the status of Order status from JEST table.
    Hope this helps you.

  • Production Order Function Module details

    Hi Team,
    I am would like to get the following production order informations using function module. Which function module will provide the following information?
    1. Production order status
    2. Production order scheduled start date and scheduled end date
    3. The operation at which the production order being currently processed (current operation of routing being processed)
    4. All the dependent production order details for given finished goods production order
    Your information will be very much appreciated
    Thanks
    Kumar
    Edited by: psk.psg on Jul 13, 2011 10:12 AM

    Hi,
    I had the same problem this morning and I found out a FM you have to run to fix this problem.
    FM: CO_IT_SET_FLG_ITAB_NEW
    Rgds,
    Parise

  • Schedule line delivery date of sales ordere in production order-MTO

    We have a Make to order scenario where item in sales order can have mutliple scheule lines on different delviery dates.
    Ex : sales order 100020  and item no 0010
    has schedules with schedule line dates as
    10.04.2010----1pcs
    20.04.2010---1pcs
    03.05.2010----1pcs
    When the planned orders are converted to production orders, the 1 del date (EDATU) in the all the three production orders is the same ie the earliest delivery date (10.04.2010), even though the delviery dates are different for three as shown above.
    Is there a way we can show the indivdual delivery dates on all the three production orders.
    production order 1----- 1 del date as 10.04.2010
    production order 2 -
    1 del date as 20.04.2010
    production order 3 ---1 del date as 03.05.2010
    Thanks in advance.
    When a planned order is converted toproduction order

    We have a Make to order scenario where item in sales order can have mutliple scheule lines on different delivery dates.
    Ex : sales order 100020  and item no 0010
    has schedules with schedule line dates as
    10.04.2010----1pcs
    20.04.2010---1pcs
    03.05.2010----1pcs
    When the planned orders are converted to production orders, the 1 del date (EDATU) in the all the three production orders is the same ie the earliest delivery date (10.04.2010), even though the delviery dates are different for three as shown above.
    Is there a way we can show the indivdual delivery dates on all the three production orders.
    production order 1----- 1 del date as 10.04.2010
    production order 2 -
    1 del date as 20.04.2010
    production order 3 ---1 del date as 03.05.2010
    Thanks in advance.

  • Schedule lines for an external operation in a production order

    Hi All,
    I have an external operation defined in a production order and a scheduling agreement is assigned to it in the Routing operation details.  Now, i want to generate schedule lines when a production order created but the system always generating a purchase requisition.  Do we need something to be configured in the background?  Please help!
    The idea is to have the goods receipt done against the same agreement always.
    Regards,
    Sravan

    Hi Sravan,
    As per my view point, this is standard SAP behaviour. System will generate PR only in case of external operation.
    If you go to OPL8 (Order type dependent parameters) for your respective order type & plant combination you have option of maintaining setting related to PR only and there is no option of using scheduling agreement or generating schedule lines.
    I don't see any possibility to use scheduling agreement using to have schedule lines for external operation.
    Regards,
    Tejas

  • Sales Order Schedule line not populating in the Production order

    Queation: Is there a way to tell the system to look at the sales order, line item AND schedule line. It is displayed in MD04 but it doesn't carry over to the Production Order. We are a MTO and this information is relevant in a number of ways. 
    Please Help.

    Vickie,
    If you are using MTO scenario then when you run the MRP for the material, it will create a planned order for that sales order based on the dates calculated from the sales order schedule line (Shipping tab)...
    So now when you convert the planned order to production order, all the sales order details will get copied.
    try and revert back.
    Swapnil

  • Regarding the Delivery schedule item in Production order

    Hi Gurus,
    Kindly can you let me know what are the settings to be done for getting the delivery schedule line number in the production order along with the sales order and item number for a MTO scenario.
    Regards
    Anand

    If you're working with stg. grp 20, it should do what you're looking for.
    If you're not sure, do this in your sandbox -> assign the stg. grp in material master, create a SO for this material, run MRP, convert the planned order to production order & verify the results.
    To know more about this stg. grp you can go thru SAP help or just do a search in this forum or maybe wait for someone to paste the links for you.

Maybe you are looking for

  • Problems with DVD/CD optical drive

    Hi all, my HP notebook's optical DVD/CD drive no longer reads disks. I have tried several different disks. I insert the disk, close it, then it makes sounds like it is trying to read the disk for about one to two minutes. Then it stops. Nothing else

  • How do I break up a concatenated disk set?

    After spending the better part of a week trying to shoehorn in two 500Gb SATA drives into my G4, I coming around to the conclusion that the Sonnet Tech PCI to SATA (TSATA) controller firmware, is not up to the challenge of concatenated drives. The OS

  • HT4437 slow motion video to TV

    I have problems transmiting a video with slowe motion from my iphone 5s to my TV through apple tv. I just hear the sound. Do not see image. Any idea???

  • Again mplayer problem

    After recent system update all my movies are shown in black/white and i don't know where could be the problem? EDIT: It happens only with xv video output.. Last edited by Insane-Boy (2009-09-03 08:08:16)

  • Universal dock differences - MB125G/A B & C

    Hi All/Apple Can anyone tell me the differences between the Universal Dock models? Having read through it initially looks like the only differences are in a change to the remote window on the dock and the selection of adaptors available. I have just