We create a production order without materials using CO07 and everything is ok except that the cost is now sitting in cost element. Although the settlement parameter of the order goes to cost center, finance wants it to expense off to another GL account automatically. Status of prod order is REL  PRC  NMAT SETC. Settlement rule is created with cost center as one of the settlement receiver.
I went to t-code OBYC and found the PRD  - General Modifications PRF pointing to the GL account I wanted.
I went to t-code FS00 (edit G/L account centrally) edit cost element, default acct assignment and was tempted to update the cost center to default the GL account to the cost center but was unsure what is the impact.
Is there anything else that i am missing here ?
Any help with t-codes guidance will be greatly appreciated

In OK07 select the settlement profile, change default object type to CTR. So the settlement receiver will be cost center.
Who is the receiver you can check in production order itself.

Similar Messages

  • Production order settlement in case of non valuated material

    Hello guys,
        Our client wants some of the materials have to be non valuated. These materials are raw materials and SFG also. We can assign UNBW material types to those materials.
       I have created one material for test purpose. It doesn't contain the accounting view so as no valuation class. BOM of it , doesn't contain any component as client doesn't want to show any consumption on production order.While creating the order for that material system asks for the settlement rule. I skip that step and create the order. I do GR for the same.
      My question is, is production order settlement essential for these orders? What if we don't settle the order. No activity type has been assign to the work center.
      Kindly give ur valuable inputs.

    Hi,
    No need to create material as UNBW type.
    Normal ROH, HALB, FERT material type we can achieve this.
    In the BOM of FG or SFG goto  item detail screen there is a tick mark in costing.
    Remove the tick by OS23 - BOM status.
    Now you can do your production as regular. But cost will not get update.You can do regular settlement also.
    Regards,
    Dharma

  • Production Order Settlement

    Dear All,
    When I am trying to settle production order ( T.code: KO88 ) I am getting the error as
    Moving average price for material is negative: 100504 2300
    Message no. M8783
    Kindly suggest remedies for this.
    Rgds
    Srini

    Normally what happens is that when you have a material with price control as moving average instead of standard price. The moving average is updated when you do production order settlement
    In your case, the settlement is trying to bring down the price to negative. Check this would resolve yr error.
    You might want to change the materials from moving average to standard or check why the settlement is taking your moving average to negative.

  • Production order settlement accounting entry

    Hi,
       Can u gibve some link what is production order settlement ,  and how the accounting entry is generated,  our PP person have done the settlement in april 2010  but accounting entry are not updated in the corresponding g/l account how to check this.
    regards,
      zafar

    Production order settlement is just a process of closing the order after goods recipt (production) is being booked in system
    Production order settle the costs to CCNs from the orders. It doesnt have any entry unless under / over absorption. In that case following entry will be generated (i.e. of difference amount)
    Inventory Change Dr. To Inventory & vice a versa as the case may be of under/over absorption.
    If you go thru MB5B for the material, you will find the same without any Mvt. type.
    Hope it is clear.
    R/s

  • Production order settlement posting

    Hi all,
    For our production order settlement now, it is posting to:
    Debit u2013  Production Order settlement (OBYC --> GBB --> AUA )
    Credit u2013 inventory
    For the credit posting though, in OBYC --> PRD --> PRF it is set to hit the 'cost of goods sold' account instead of the 'inventory' account. What can be causing it to hit inventory?

    Dear,
            In production order, there are 3 elements. 1 Material consumption 2 inventory change and 3 is confirmation on which planned cost and actual cost is determined.
    Material consumption and inventory change is directly relevant to stock of materials but confirmation is only relevant to activities e.g. labor, machine, FOH and setup.
    Settlement is difference of plan and actual cost on production order. This difference can be due to either first 2 elements or 3rd element i.e. activity. That's why it can not be "inventory' account".
    Thanks
    Muhammad Ashfaq

  • After production order settlement, where does the cost go?

    Dear Experts,
    I understand after we did the "order settlement" for production order, the cost will be settled to material manufactured from the said production order.  Say, the total cost is $10,000 to produce 1000 units of finished goods (FG), then the cost settled to each individual FG at $10 each, am I right?  Where can I see the settled cost in the material master?..
    I checked in the cost center report, S_ALR_87013611, I can see the cost Credited from "production" cost center with a breakdown in settlement cost element such as machine hour, setup and personnel hour.  I understand the other side of Debit was to the production order, and only after order settlement, I'm not sure which cost center will be Debited.
    That would be the CO side, how about the FI, would there be any cost posted to the GL side after production order settlement to the material?
    Please advise..
    regards,
    Abraham

    Hi Abraham,
    It's not the button i mentioned. I was just trying to take u to the accounting document from the settlement screen. well just drill down the settlement screen and u'll get it. No big deal.
    But more important is the concept. I'll share my understanding here. (cost by production order)
    Any value that flow into controlling module should have a cost object. Here production order is the cost object.
    First u create a production order (cost object) for say 1 unit of X with a std price of Rs. 10
    Std price comes frm material master as a result of std cost estimate
    U start production - Raw materials are consumed - 2 qty x Rs.3.
    Entry RM Consumption Dr Rs. 6    Inventory Cr Rs.6 (Prod order is debited with Rs.6)
    Activity (Let's say machine hours - 3 Hrs x Rs.2) According to the routing it was  2 hrs but actual production took 3 hrs.
    Entry - None - But production order is debited with Rs. 6.
    When production is complete for 1 qty of X, entry flows
    Finished Goods Dr Rs.10    Change in Stock  Cr. Rs.10  (Production order is credited with Rs.100
    Abraham, now visualise both sides of the production order. It will have debit of Rs.12 and credit of Rs.10.
    Now accountant sees the production order and confirms the values are ok and puts the status of TECO to the order. which means the order is technically complete.
    Now when u run the order settlement, this production order is picked up by the system (due to it's status). System sees difference between debit and credit of Rs 2.
    So it cedits the production order with Rs. 2. Now both debit and credit of production order is equal (Rs.12)
    Entry Price diff A/c Rs,2     Change is stock A/c Rs.2
    Now this rs. 2 is settled to COPA. It does not flow to material.
    Reason:  in a std costing system materials are valued at standard cost and
    Hope this helps. Do revert in case of doubts.
    Best Regards
    Vimal

  • Error while doing production order settlement

    Hi frds,
    When I am doing the production order settlement, I am getting the following error
    " There are no accrued amounts; settlement is not possible".
    The status of the order is TECO CNF DLV PRC BASC BCRQ GMPS MANC.
    Rajnish

    Rajnish,
    Please check if there is cost balance for the order, to me it looks like the order is already settled. In the order display mode (CO03) menu bar Goto->Costs->Balance.
    If balance exists then the problem may be related to the settlement period used in the Intial screen of transaction KO88. Please check the cost incured period and use the same period as settlement period.
    Regards,
    Prasobh

  • Production Order Settlement Process with respect to  a Project

    Hello All,
    I know about normal Production Order Settlement Process in discrete industries.
    Can anyone give me the steps for the Production Order Settlement Process if the Production Order is created with respect to a Project in SAP PP- PS Integration Scenario.
    Thanks in advance for your support.

    Hi Experts,
    Can anyone clarify my above queries.
    Thanks in advance for your support

  • Auto Production Order Settlement

    Dear experts,
    Please advise how to implement the auto production order settlement (configuration, exit)?
    i need to automatically carry out the settlement procedures (in the background?) as soon as the production order gets the 'TECO' status.
    I searched for similar question but not answered
    http://scn.sap.com/thread/463939
    Thanks for your kind suggestions in advance.
    Best Regards,
    Gary

    Hi Gary,
    What I meant here was, let's assume you have 10 plants where TECO would be done for Prod. Orders
    Assuming that you split the batch jobs based on the number of the open Prod. Orders in a plant and then have them run once a day to avoid excessive use of system resources.
    The program can be found with search string *CO88* in SE38.
    The settlement would happen for the Orders which has the TECO status as per the standard SAP design, only difference would be that the once having no changes would be ignored and with the newly TECOed Prod. orders would be considered for the settlement.
    Hope that helps!
    Varshal Kachole
    The SCN Rules of Engagement

  • CO - Production order settlement(KO88)

    Dear SAPns
    1.Explain why the production order  actual settlement have to do.
    2. What is the financial impact (P&L and B/s) due to settlement of  production order
    3. Where/How  the actual cost is calculated?
    4.What is the benefit to do the settlement of production order.
    Anybody have document regarding above pls send me.
    My Id : [email protected]
    Regds
    Tamil

    Hi,
      Production order settlement is done to capture the variance and the WIP to the header material of production order. On execution of the settlement the entries for FI will be posted with respect to variance and WIP
    Regards
    Kaarthik.D
    Assign points if useful

  • Production Order Settlement Function Module

    HI,
    Trying to find a BAPI or Function Module to used that will perform a transaction K088  Production order Settlement. Can anyone tell me is one exists?
    Thanks,
    Chris

    Dear friend,
    I had the same requirement as you have defined, Did you get any function module for PP production order settlement (KO88). If there please mail me on [email protected]
    Thanks in advance,
    Regards,
    Mubashir

  • Lock the production order creating without material for order type zp01

    Hi all,
    Good morning.My client wants to lock the production order creating without material for order type zp01.He does not want to create production order without material.Its very urgent.Please guide me the settings if any.
    Thanks and Regards
    Sukumar

    Hi Sukumar,
    You can do by applying user exit.
    Use PPCO0007 - Exit when saving production order.
    Function module - EXIT_SAPLCOZV_001.
    Include Program - ZXCO1U06
    Write your Code:
    *&  Include           ZXCO1U06
    Regards,
    Sankaran

  • Production order settlement period

    Dear Friends,
      I have settled my production order in period 4 (Let us assume). After some time ( let us assume 15 days) i wants to reverse my order. But by the time of 15 days my period has been changed from 4 to 5. I have forgotten on which period that particular order has been settled, so that i can reverse the order on the same period.
    Could anybody guide me , How to display production order settlement period?
    Thanks
    Senthil

    Hi Mahesh,
      I could not find any period related information under change management option.
    But i have found the information under "Header----Settlement rule". Here we can find the details about settlement period (First used and last used).
    Thanks
    Senthil

  • Production order settlement info

    Hi,
    In production order settlement category  is MAT.Some times it is CTR .But costing varient is PPP2.In settlement configuration i check that Allocation structure is A1 ,PA transfer sture is A1 butdefault object trype  is blank . So how system take it MAT some times CTR sometimes and wt is the impact and wt is the meaning of this thing when production settlement i is happened  ?
    Thanks &  Regards,
    Debashis

    HI,
    You can check order type in the Production or Maintenance order as Type.
    Check the Order Type in T.code KOT2 and view details for your order type in which you can see the settlement profile. The settlement profile(T.Code OKO7) will have the Default object MAT or CTR etc.
    Costing variant doesn't have any relevance.
    Generally all maintainence order will be settled to cost Center.
    And Production Order will be settled to Material.
    At the settlement all the costs incurred for the production order will be settled (Moved) to respective Finished product if it is MAT and for Cost center if it is CTR.
    The accounting entries for production order will be
    Price Difference F.G A/c DR
          To Change in Stock A/c Cr
    or Vice versa.
    Regards,
    Raj

  • Single production order for many materials

    Dear Experts,
    We can create a single purchase order for many materials. Like wise can we create a single production order  for many materials which is produced from single raw material in same operation?
    Thnaks,
    Chetan

    Chetan,
    You can not create a single production order for multiple materials.
    However, the workaround would be create one material as BOM header and and assign the remaining materials (for which you want to have production order) as BOM components with by-product or co-product. With this you can receive all the materials against one single production order.
    This will have implication in many areas like planning and costing.
    Evaluate the option with your FICO consultant also, before going ahead.
    Regards,
    Himanshu