Production start date

Dear Experts,
We have a finished material FMAT which is having two semi-finished material SMAT1 and SMAT2 . The lead time of SMAT1 is 30 days and SMAT2 is 60 days . We want the the production to be start once the  SMAT2 is available . We run MRP today ( 22/01/2009 ) and the material SMAT1 will be available on 22/02/2009 and SMAT2 will be available on 22/03/2009 and so we want the production start date to be on 22/03/2009 . How to achieve this . Please suggest.
Thanks.

Hi,
   You have to give the requirement for the finished material FMAT accordingly i.e after 2 months,end of March 2009. System will plan by taking the lead time of the dependant semi finished materials plus the lead time of the finished material.
  If the lead time for the Finished material= 7 days, you give the requirement on 30.03.2009. After MRP run, system will propose dates: Finish Dates for SMAT1  and SMAT2 is 23.03.09. So SMAT1 will start 30 days before 23.03.09 and SMAT2 will start 60days before 23.03.09 thus produce the semifinished material on the start date of the Finished material.
  Hope this is clear..
-Thaila Shree

Similar Messages

  • Maintain production start date in sales order

    Hi,
    Is it possible to maintain the production start date in the sales order? Is there a field that can be used??
    Thanks
    Keshi

    Hi,
    There is no standard field which is available to enter the production start date but you can use the field GUARANTEE in the header of the sales order for your reference but this is at header level or you can use in item level text if this is only for your reference.
    Regards
    Goutham

  • Start date in past

    Hi all ,
    What for the need / concept of  the Stat date in past has been given in Scheduling paramters ?
    or why i have to create the order in past date when practically i can not mfg the prodcut in past ?
    Thanks in adv .
    Regards

    Hi,
      For every production order we are scheduling with some cushion time because of many interruptions. These cushion timings given in schedule margin key.
    As per system schedule , production start date in the past. We can not start production from the past date.
    But with these cushion timings float before production, opening  period we can eleminate & possible to start production from today.
    So no need to reschedule the order.
    Hope this helps you.
    Regards,
    Dharma

  • Production finish date differs from basic finish date in backward schedulin

    Hi, experts.
    When i do scheduling the planned order,
    production finish date differs from basic finish date in backward scheduling as below.
    Scheduling: Backward
    Basic finish date : 2010.01.22
    Basic start date : 2010.01.21
    Production finish date : 2010.01.23  09:00:00
    Production start date ; 2010.01.22 03:57:09
    *GR time : 0.
    *Scheduling Margin key : 0.
    I don't know why production finish date set in 2010.01.23 09:00. ( Basic finish date +1 day)
    Please reply me.
    Thanks.

    Dear Jong,
    1) what is the parameter used in MRP run, Basic scheduling or lead time scheduling
    2) you must find a exception Mssg for that plan order in MD04
    3) basic scheduling take the time from material master & lead time scheduling will take time
    from Routing
    Regards
    Madhu

  • Process/Production Order WIP Reverse on Month starting date with postiing d

    Hi Experts,
    Is it possible to reverse the WIP of Production/Process Order at month starting date eg. 01/07/09. Posting date & Document date should be: 01/070/09.
    In my current project production is batch management system. Some of the batches start at month ending days (Eg. 29/06/09) for we calculated WIP at dated: 30/06/09.
    My Client wants to reverse that WIP next day, month starting hours Eg. 01/07/09 but while reversing the WIP system is posting the WIP reversing doc. posting date is 31/07/09.
    Same batch which started production on 29/06/06 is closed at 03/07/09 as well as goods received same date. FG Stock A/c updated in accounting books.
    At the same day If I print my trail balance system showing the Stock value double (WIP stock as well as FG stock)
    First Month
    Eg. Process Order WIP at 30/06/09                              : 50000/-INR
    Second Month
          WIP Reversal Posting date:31/07/09 by system     : 50000/-INR
          FG Stock received at 03/07/09                               : 50000/-INR
    If I Print Trail Balance on 03/07/09 system shows        : 1, 00, 000/-INR (based on Posting date)
    Which is wrong..
    Please tell me the way for Change the Posting date of WIP reverse document. OSS guys are replying as consulting issue. 
    I am waiting for your valuable reply.
    Thanks & regards
    Bhagiradha

    In KO88, CO88 Select Menu bar Extras-> Posting date
    Enter Posting and execute
    Thanks for Rajesh (SAP Labs)
    Thnaks & Regards
    Bhagiradh

  • Production order Basic start date calculation

    Hello PP Sapperu2019s,
    I have an production order for total qty - 865,00.This production order created on 11.08.2011 and I could able to see the Basic start date as 26.06.2011.Please let me know how this basic start date gets calculated. I mean what are all the parameters included for calculating this basic start date.
    My Observation:
    I have checked in OPU3 for the respective plant and order type the scheduling type mentioned as Backward.
    SMK u2013 903 (ie, opening period for planned order u2013 3 days)
    In Routing we have two operations.
    Requesting from forum people to give me the detailed calculation part on how this basic start date gets calculated / arrived.
    Please let me know if you need any more inputs.
    Cheers,
    Kumar.S

    Hi Kumar,
                     As per my understanding this is all decided/maintained through scheduling parameters which are defined in Customizing per order type, plant and production scheduler (from the material master) (Customizing for Shop Floor Control, by choosing Operations > Scheduling > Define Scheduling Parameters). In what follows the parameters are described that affect the scheduling of a production order. Further control parameters are described in the course of this section.
    According to your query I suggests ,In Customizing you can specify that an order is rescheduled as soon as it is a certain number of days late (Start in the past indicator). The system then automatically carries out today scheduling when the basic start date of the order is more than the given number of days in the past. This scheduling is a type of forward scheduling starting from todayu2019s date and where the necessary reduction measures are applied .
    Else you can also specify  that a production order is to be rescheduled automatically whenever it is saved (indicator Automatic scheduling). If changes relevant to scheduling are made in the order and this indicator is not set then the order is given the status NTER (dates not current).
    Hope this would be useful for you at some extent.
    Please revert if required .
    Regards
    Chandra

  • Production order start date gets incremented by 1 day

    Hi,
    I have a scenario where in when the Planned Order gets converted to Production Order the Start date gets incremented by 1 day.
    If the planned order date is 11.02.2009 after converting to Prod Order it shows the start date as 12.02.2009.
    Can any please help me in resolving this issue,
    with rgds
    Ranjith Singh

    Dear,,
    Please run the MRP MD02 with Scheduling- 2 Lead time scheduling.
    Planeed order date may be from in house production time which is lot size independent.
    But production order date is from routing time which are lot size depnendent.
    Hope clear to you or come back if any problem.
    Regards,
    R.Brahmankar

  • What parameters determine Planned order production start and end dates?

    Greetings
    We are using the graphical planning table @ MF50 to firm Planned Orders (Basically checking off "Firm Order" field within the Planned Order). We are on ECC 6.0
    Whenever I backflush, the production start and end dates get overwritten (The Basic dates do not change).
    I would like to prevent this. Can someone advise me on what parameter controls how the production start and end dates getting changed?
    Thank you
    Hanarin

    Hi,
    Calculating production dates ( Lead time scheduling) are explained in detail in the SAP help URL as below:
    If "Automatci Scheduling indicator" is set in the customizing for scheduling parameters then after every change relevant to scheduling, the production order is also automatically rescheduled before saving.
    You need to check these settings.
    regards
    Datta

  • INHOUSDE PRODUCTION TIME AND BASIC START DATE

    WHAT IS THE RELATION BETWEEN INHOUSE PRODUCTION TIME AND BASIC START DATES

    Hi,
    Inhouse production Time : This is the field avl in material master, where we provide No. of days required to producce a Product / Assembly. While running MRP if you use the Scheduling as " Basic Scheduling" in MRP parameters system will take the value from Material master and do the backward scheduling and find the Basic Start and Finish dates for a Order. i.e. From the Finsh Date system subtract the Inhouse Prod time and arrive at the Baic Start Date.
    If you select the Lead time scheduling in MRP parameters then system will ignore the Inhouse prod time mentioned in Mat master and consider the Routing Timings for scheduling the Order.
    Hope this will help you.
    Regards
    radhak mk

  • Production Order  Start Date

    Hello All,
    I am facing a problem in a Production order.When I am trying to change the  Production order Start date  and saving the changes I am getting a termination error (program termination).
    The error message is as below
    Nested call of PERFORM ON COMMIT: NESTED_PERFORM_ON_COMMIT caller: SAPLMCEX program: SAPLMCEX form: MCEXLOG_WRITE_04_DIA
    Regards
    Dhananjay

    Hi
    Check for the order scheduling parameters and confirm that the order in past are also allowed.
    Krishna

  • SVC Contract start date different than Product Shipped date

    Hi
    "SVC Contract start date different than Product Shipped date"
    Why this is an issue, what could be the reason, how can I fix this ?
    Appreciate your input.
    thanks
    s

    Hi Siva
    Can you give more details about what you are trying when you see this message? What is the apps version? Are you creating contract from OM or from service contract module? At which stage are you getting this message / error?
    Thanks
    Sid.

  • Planned order creation with PDS valid on only order start date and not finish date

    Hi All,
    We have requirement to allow creation of planned order manually if production version is valid on order start date and not finish date.  This is because lead time of order is longer. I refered OSS notes 385602. I could find out solution for this is implementation of OSS note 694140 to change validity mode at activity level to consider start date of first produce activity  in validity interval. Problem is even If I create order in APO by implementiong this note planned order is not transfered to ECC and it gets stuck with error production version not valid.
    Is there any way in ECC to control this? Any config or customization?
    Regards,
    Santosh

    Nilesh,
    I think there is a simple procedural skip happening in your business process. You are right when a planned order is created after MRP it would default assign it to the first available production version. 2options available for us,
    1. First use transaction MF50 and do the line loading and assign the quantites to the production versions/Production lines, so that the actual capacity planning is getting completed. This way you can have planned orders with both the production versions and matching to your actual line capacity.
    2. Use Quota arrangement concept, to automatically split the Planned orders during MRP for a percentage based on individual production versions.
    Now when backflush is performed S225 table is updated and Planned order qty also gets reduced.
    Hope this helps....
    Regards,
    Prasobh

  • SNP Planned order START date should be displayed in DATA VIEW

    Hello Guru's
    I have a very complex requirement. It is as follows
    We are using heuristics and capacity leveling for our requirement. We generally see the planned orders in the SNP view but here additional requirement is that we have to see the start date of the production planned in the date view, ie the client would like to know when the actual production starts and wants to see the quantity produced on the first day in the date view.
    In capacity view,we can observe the resource load which is the start date of the production planned, this load is in percentage now do i related that into quanitity and even if we do related that percentage in quantity then how do i see it the SNP data view plan.

    Hi Sriuppa,
    you can use receipts view /sapapo/rrp4 transaction where you can see receipts. This transactions offers you the selection based on  product,source,target,dates,resource and you will get the list of orders.
    Secondly ,if you right click in the receipts cell,select display details,it will show you order details at the bottom of the data view.
    Please let me know if it helps
    Thanks
    Amit

  • BAPI to create SNP planned order based on start date

    Hi,
    I am looking for a BAPI to create SNP planned order based on the order start date. There is BAPI BAPI_MOSRVAPS_CREATESNPORDER which can be used to create SNP planned order based on the end date but not based on the start date.
    Also would be great if some one can share how do they create SNP Planned orders using BAPI BAPI_MOSRVAPS_CREATESNPORDER in case if GR processing time is defined in the product master and workdays for GR to be respected according to the calendar.
    Regards,
    Venkat

    Hello Mr.Venkat,
    Hope you recognize me.
    Please check out the BAdi below.
    BAdi - APO_BAPI_BUS10503 (this is the BAdi for ManufactOrderAPS  BAPI which contains the SNPorder BAPI)
    Method - CHANGE_SAVEMULTIPLE2
    In this method parameter IT_ORDER_HEAD contains Order start date input option.
    For GR time please check this (not sure if it will help).
    Same BAdi/ same method
    Parameter IV_PLANNING_MODE_USAGE contains field PLANNING_MODE.
    Value 1 for PLANNING_MODE corresponds to "Observance of parameters from the product master".
    This may make it respect the GR time in product master
    Good luck with the above
    Regards,
    Ashok

  • Problem-planned order start date in the past

    I use PP-PI - After MRP run, planned order was created and has exception message "06-start date in the past" its make me wonder because before this problem occur we already tested many time and never found this message(06). then i check in OPPR- field "start in past" is blank, OPPQ- field "Start in past" are not check, OPUZ-Scheduling Type is backwards and field "Start in the Past" is blank, OPU5-Scheduling Type is backwards and field "Start in the Past" is blank.
    do any guru know why system not use forward scheduling when found that start date in the past? or have any config of other module which may lead to this issue?
    thank in advance.

    In OPU5,
    Check the setting for correct MRP group which is assigned in  material master or in the SPRO node
    Production >Material Requirements Planning>MRP Groups-->Define MRP Group for Each Material Type.
    check and come back