Profit Center Mandatory in Cost Center Master

Hi Expert!
I would like to know the configuration path to make the option Profit Center Mandatory in cost center master data.
Thanks
J

If you have activated profit center accounting and if you leave profit center blank in the cost center master, system issues a warning message at the time of saving. You can convert this message to error to make profit center mandatory.
The message number is KS096. It can be configured in transaction code OBA5. Choose application area KS. Insert message 096 and select the desired message type (E for error or W for warning).
Regards
Rakesh Pawaskar

Similar Messages

  • Profit Center Mandatory in Cost Center Master Data

    Hi guys,
    Can any one suggest,where can we make settings for profit center mandatory in the cost center master data?

    Hi Swapvik,
                    I was just surfing and came across the concept for the profit centre.Have a look at it , it might help you or even resolve the issue.
    Here is the Link: [Centre1|Re: Gl account is set to profit center mandatory;
    There is another link for configuration problem relating to the query.
    Link: [Centre2|Profit Center Column;
    I am sure this will resolve your query.
    Have a best day ahead.

  • Profit Center mandatory for Cost Center

    Hi,
    How do we make the profit center field in the cost center master data as optional instead of required.
    Thanks,
    Venkat

    If you have activated profit center accounting and if you leave profit center blank in the cost center master, system issues a warning message at the time of saving. You can convert this message to error to make profit center mandatory.
    Regards
    Rakesh Pawaskar

  • How to make the Profit Center Field Mandatory in Cost center Master Data

    Dear All,
    Please let me know how to make the Profit Center Field mandatory in Cost Center Master Data as well as my Internal Order Master Data?
    Thanks in advance!
    Regards,
    Rajeswari Shankar.

    Hi Rajeswari,
    You can modify message number KS096 to "Error" via OBA5. Thus, the users would no be able to save a cost center without entering a profit center. (Depending on your release you can make KS096 modifiable by implementing note 486781.) 
    Concerning the internal orders (transaction KO01), you can run KOT2 and set Profit center field as required entry in "change field selection" section.
    Regards,
    Greta

  • Profit Center deriviation from Cost Center

    Hi all,
    I have just configured CCA and PCA for one of our new company code.
    I have created 3 cost centers like A, B, C and subsequently same have been created as profit centers too.
    Maintained the profit center in the cost center master data.
    No other derivation rules has been configured so far.
    Now i am trying to do a expense posting with F-02, after entering cost center, system is updating profit center field with a dummy profit center only.
    Even i f a changed the dummy to normal profit center, again system replacing the normal PC with dummy PC.
    I want like...when i enter CC as A, then i need to derive PC also as A for the line item. ( For both expense items as well as revenue items).
    Please suggest.
    Regards,
    Srinu

    Hi Chintan,
    Thanks for your quick response.
    We have already implemented the said SAP note.
    Let me explain my requirement again.
    We have IOA, CCA, PCA active in our system.
    For every expense or revenue line item Internal order is mandatory.
    apart from we have 3 cost centers and 3 profit centers ( 1:1 )
    in cost center master , profit center is assigned.
    1) users are going to decide the cost center, while posting FI direct entries only. So while doing F-02, they will enter CC, and IO manually and at the same time PC should derive from cost center master data ( as it is 1:1 only).
    2) as specified above, we have IOA, CCA, PCA active. In this case IO, CC, PC are to be set as mandatory fields for Field Status Groups G004 and G029?
    Please advise...
    Regards,
    Srinu

  • Changes to Profit center assigned to cost center

    Hi
    We have a scnario in which the profit center assigned to the cost center master has to be changed. We have been advised also to  change the validity period of the same from the date of change of the profit center .However, the cost center has been used to for some data postings with the old profit center maintained in the cost center master. Now my query is:
    1. What is the impact of changing the profit center in cost center master? In our case, some data has been posted to the cost center when the old profit center was maintained.
    2. Why should we change the validity period of the cost center after changing the profit center assigned to the cost center?
    3. Also, what is the way to transfer the entries which have been posted to the old profit center to the new profit center?
    Regards
    Sanil Bhandari

    hi,
    1) The impact of profit center is more in the cost center. when ever we assign profit center to cost center. the cost will be updated automatically. so there is no direct posting in profit center only statstical posting are generated.
    2) second one when we want to create profit center first chek it out profit center valid and upto. if same is not maintained in creation of cost center . so u must have to change the validity periods
    3) i am not sure this one i thing 7KEH OR 1KEF TC is there any way tommorow i will give the answer this questions.
          if my answers are wrong plz correct and replay to my id [email protected]
    thank you

  • Profit center hierarchy and cost center hierarchy

    Hi
    What are the things we have to consider to create Profit center hierarchy and cost center hierarchy  and what is the need to assign profit center hierarchy to profit center and cost center hierarchy to cost center. What levels does this fall into? Can some one please guide me.
    Thanks.

    As you would for any other infoobject
    Activate the business content hierarchy datasources on R3 for cost centre and profit centre
    Go into BW - replicate the metadata
    Then just connect via transformations or transfer rules the datasources to yoru infosources or master data objects
    Create an infopackage per hierarchy!!!!! - press the button available hirachies from OLTP - click the one you want on the left - fire it off
    Then repeat new infopackages for all hierachies

  • How to make fields mandatory in cost center

    Hi Sap Experts,
    How to make fields mandatory in cost center.
    Please give me advise.
    Regards,
    Raj

    If you want to make "Profit Center" field as mandatory, then OBA5 transaction code
    Application Area - KS
    Number 096
    make this as error for online and batch input. Then profit center will become mandatory.

  • Profit center accounting and cost center relationship

    Experts, in the future as we look to tie the PCA cube with the CO cube, the referential integrity will be important.  What I see as being important is capturing the profit center, cost center and account that was used at the transactional level and not from an arbitrary hierarchy.  As such, in the PCA cube, it would be optimal to have the cost center assigned to the transaction be available.  This assumes that the PCA totals are by profit center, cost center and account.  Furthermore, I will want to build a jump target from the PCA cube to the CO cube where we can see this data by cost center and cost element or vice versa.  There seems to be some uncertainty on if the PCA cube has the cost center informaiton, so how would I do this?

    I don know if i understood it correctly but If you assign you profit center in your cost center you should be able to get all that you need.
    Assign points if helpful

  • Function module for Profit Center group and Cost Center group changes

    All,
    The requirement is to change the profit center group and cost center group from one node to another. Please remember it is trying to simulate the transactions KCH5 and OKEO programatically.
    I would like to know if somebody had this requirement previously and had made use of some function module or some other technique which will help in changing the standard hierarchy nodes.
    Help is much appreciated.
    Regards,
    Hari

    All,
    The requirement is to change the profit center group and cost center group from one node to another. Please remember it is trying to simulate the transactions KCH5 and OKEO programatically.
    I would like to know if somebody had this requirement previously and had made use of some function module or some other technique which will help in changing the standard hierarchy nodes.
    Help is much appreciated.
    Regards,
    Hari

  • Can we change existing profitcenter to  new profit center  of a cost center

    hai,
    can we change existing profitcenter to  new profit center  of a cost center in ks02
    is there any problem in alredy existing data related to that cost center

    Hi,
    If data is already there for the Cost centre with old profit center the change of profit center is not possible.
    If you transfer the data to other costcenter then i think you can change the Profit center.
    Just try this.
    Regards
    Balaji

  • Change the profit center of the cost center.

    Hi Friends,
    I want to change the profit center of the one cost center but system is not allowing because the posting done against this cost center. i transfer the value of that cost center in other cost center then i tried but system dose not allow.
    following error is coming.
    Changing profit center from 101257 to 101271 is not permitted
    Message no. FAGL_ORG_UNITS011
    please provide the solution.
    Regards,
    MAhesh

    HI,
    system behaviour is explained in SAPNET note 1358080, there you find also how to change the message. Check the consequences carefully in test client...
    best regards, Christian

  • Change the profit centre in the cost centre master after a year

    Hi All,
    Could you'll please let me know whether it was possible to change the profit centre in the cost centre master and if i did what will be the implications.
    Thanks and Regards,
    Vandana

    Refer transaction code OKEG.
    You can maintain master data for cost centers, cost elements, activity    
    types, and business processes with time dependencies. You can make        
    changes at any time for any given time interval. Data storage also takes  
    place with a time reference. In this way, a master data record can have   
    multiple database records storing different information.                                                                               
    The smallest interval is one day. To ensure data consistency, you cannot  
    change each field daily. The timeframes in which you can change a field   
    depend on the field functions, which are fixed by the system and cannot   
    be changed. Master data maintenance includes an automatic check for each  
    field's time-based consistency, resulting in individual time-based        
    maintenance for each field.                                                                               
    The following dependencies are supported:                                                                               
    o   Not time-based                                                                               
    o   Day-based                                                                               
    o   Period-based                                                                               
    o   (Fiscal) year-based                                                                               
    This function provides an overview of the time dependencies of           
    individual master data fields during master data maintenance, along with 
    checks and storage of consistency timeframes. You find this information  
    in the "Time dependency" column.                                                                               
    If you use fields requiring characteristics greater than one day and     
    which are changed for the system lifetime of the object, the system      
    automatically creates a new database record for this processing          
    interval, and changes the time-based validity of existing records. The   
    change is logged in the master data record with the time reference.      
    However, a great number of changes in multiple timeframes will result in 
    a correspondingly great number of data records.                                                                               
    Fields which you can change freely (indicated in the DAY column) can     
    possess different time dependencies only if you mark them additionally   
    as historically relevant. This activates the time-based updating for the 
    records.
    Object 1000 has one master data record created with a fiscal year of 12 
    periods and the cost center name AAAAAAAAAA. During master data         
    maintenance, you change the cost center name in period 5 to BBBBBBBBBB. 
    The system reacts with one of two options.                                                                               
    o   "Name" is marked as historically relevant. The existing master data 
         record for periods 1 - 12 must now become three records:            
         1000   01-04   AAAAAAAAAA                                           
         1000   05      BBBBBBBBBB                                           
         1000   06-12   AAAAAAAAAA                                                                               
    o   "Name" is not marked as historically relevant. The existing master  
         data record remains intact, with the name changed for the entire    
         existence of the record:                                            
         1000   01-12   BBBBBBBBBB
    Edited by: Ravi Sankar Venna on May 19, 2009 4:03 PM

  • Transaction data from one cost center to another cost center

    Hi All
    Can any one tel me how to move the Transaction data from one cost center to another cost center .
    My scenario is basically : Users posted for  company code 1003 for Cost center S00570 for the period 01.04.2007  to 30.11.2007 but it has to go to company code 1000  instead of 1003  for the same Cost center .S00570 .
    What we have done is that we have changed the cost center from 01.12.2007 on words to the correct company code 1000 and now all postings are going to the right company code ie
    to company code 1000.
    Now the problem is how to bring back the old historical data posted  from 01.04.2007 to 30.11.2007  to wrong company code the 1003 to correct company code  1000 .
    Is there a way to bring back the historical data which has posted to wrong company code .
    Thanks in Advance .
    Any help highly appreciated and points are assigned .
    Cheers
    Ravindra.

    Ravindra
    Once you have changed the company code in the master data, then the entries with respect to the different company code cannot be transferred. Please follow the process below and let me know if it works.
    1. Revert the cost center master data to the original company code.
    2. Repost the line items from this cost center to another cost center. Use tcode KB61. The cost center you will be reposting will be a routing cost center (say XXXXX).
    3. Once all the line items have been reposted, change the master data of the cost center to the correct company code.
    4. Again repost the costs from the routing cost center(XXXXX) to the correct cost center. You should have all the line items to the correct cost center now.
    For more on reposting refer the link below:
    http://help.sap.com/SAPHELP_470/Helpdata/EN/27/c98a46db7011d1a5400060086e9494/frameset.htm
    Let me know if it worked.
    Karthik Coneru

  • Profit center compulsory in cost center master

    Hi,
    Would anyone know how to render compulsory the profit center when creating a cost center?
    With regards,
    Ronan

    Fixed value: KS, short text: RK-S master data maintenance.
    b) Release 4.6: Add message class 'KS' to view V_T100SA.For this purpose, call Transaction SM31, enter view V_T100SA and choose 'Maintain'. Add application area 'KS'.
    c) <= 4.6C: Using Transaction SM31, add the following entry to table T100S: Application area   MsgNo   Allowed   Standard   Switch Off
    KS                 096    IWE       W          X
    Now you can use Transaction OBA5 to change message KS096 to information message / error message or to deactivate the message completely.

Maybe you are looking for

  • Script does not work after download

    Hi,    I have build a form in SAP enviornment using Adobe Life Cycle designer, while designing I have been using XML datasource and wrote scripts for different events on the elements of the form, the script works perfectly fine while designing, but f

  • Calculate the % of a numeric field

    Hello, how to calculate the % of a numeric field ? Thank you.

  • Font screwups in photoshop cs5, cs6, CC

    my fonts keep coming out in all caps when the caps lock isn't even on. This only happens to my caligraphy fonts. How do I fix this annoying issue?

  • Anyone seen error 4010 in the itunes store?

    After I copy a CD to my itunes and it attempts the match with the store, I get an error 4010 saying there was some sort of error at the store and my task could not be completed.  I am not sure what was not completed since the cd is copied and then it

  • Install Oracle Application Server

    I have an Oracle 8i database running. Now I want to install Oracle Application Server 9i in a new home, as the installation guide says. When doing this another 8i database is installed. Is that necessary or can it be avoided???