Project 2013- Trying a to move a task within the project and have it respect new predecessor rather than old one

Ok, I am working on a rather large project schedule.
Before having to upgrade to Project 2013, the file was used in Project 2007.
Basically I am having a problem with moving tasks only to have them still respect their old predecessor instead of just the new one.
Basically I have 4 tasks ( with start dates): Task A: 1st of month, Task B: 5th of month, Task C: 9th of month, Task D: 13th of month.
I would want to move say Task D infront of Task B and have it go A/1st, D/5th, B/9th, C/13th. But all that happens is that the tasks change order but all the dates remain with their original tasks. This wasn't a problem before Project 2013.
Is there any fix for this outside of having to unlink and relink every time I make  change?

GarrettW23,
You're right, it doesn't work the same in Project 2010 & later as it did in Project 2007 and earlier. The feature you desire is controlled by the option setting to autolink inserted or moved tasks. As far as I can tell there is a bug that was likely
introduced when manual scheduling was added to Project 2010. Now, if the option is set, two links will be set up, the original link to the old predecessor and a new one to the new predecessor.
I'm surprised this bug hasn't been fixed but I guess it's not something a lot of users have an issue with. Meanwhile, edit your links after drag and drop as Rod suggests.
John