Hi,
I would like to confirm if availability control / check happens only at actual posting level or also during commitments and other trigger points?  Please also advise where to set the proj availability control for different trigger points.
Vivian

SAP as provided different business transaction groups to control budget at different levels (PR,PO, FI Postings etc).
Please refer Note :628978
Glimpse of the note:
Business transactions are assigned to a business transaction group in the availability control. You can define tolerance limits for each budget profile for the availability control actions in the various business transaction groups. It is not clear which business transactions belong to the individual business transaction groups of the active availability control.
Business transaction group 00 (Purchase requisition)
Business transaction group 01 (Purchase order)
Business transaction group 03 (Goods movement)
Business transaction group 04 (Financial accounting document)
etc.
Venkat

Similar Messages

  • Warning Messages related to Reconstruct Availability Control for Project

    Hi Gurus,
    In Transaction IM52 - Change Original Budget for Investment Management Program, after changing the Budget Values of Investment Management Position and when we check the transaction for error, we get Warning Messages, the warning message is as follows:
    You Must reconstruct the availability control for Project P.000XXX.
    We tried to reconstruct the Availability Control in Transaction CJBN and again checked for errors in IM52, then also we get Warning Messages.
    As these are only Warning Messages we can ignore and save the modified budget values for the Investment Management Program.  But we want to know whey these Warning Messages are keep on cropping up inspite of reconstructing the Availability Control for Project.
    You inputs on this will help us immensly.
    Thanks,
    KRN

    hi KRN!
    I am also facing the same issue.
    Even if i am having enough budget, while making a PO, the system says " Budget exceeded".
    i could processs the PO, after performing CJBW (deactivate), CJEN (refresh) and then performing CJBV ( activate availabilty control) for that project.
    This is repeating everytime i make a PO. is there any permanent solution?
    Even after performing all the above, if i check in IM52, and check for budgets (perform from menu), the error is " You Must reconstruct the availability control for Project P.000XXX"

  • Question about project plan value and  availability control

    dear expert:
    I had built a project, and with CJ30, Allocated budget is 10000, in one of  WBS element.
    I created  a network and internal activities,
    when I  assiged a material component (Res + PR) and system can be saved even if the total plan cost value is crossing the budget value.(There is no PR created, now. )
    But, Budget checking is showing error message that budget is exceeded when I created any external service activity and crossing the budget value.(There is also no PR created, now. )
    My question is: what is the difference of the two plan value? Why one is relevant to the budget,and the other is not?
    Note:1) the tolerance limit with ++ (all activity groups), usage say 100% & action 3 (error) to the budget profile. The budget prifile is considered with only overall budget.
    2)In tables COSP, "value types" are all 01 (plan), but VRGNG field values ​​are different, components plan is: KPPE
    Service activities are: KPPP
    3)in CJ30 u2013 Extras>> Availability Control>> Analysis. I could see the following in red colour, these values system not considering into account.
    Entries in this color make no contribution to the assigned value!
    V: Value type not relevant ( Act./Plan/Stat.Act./Stat.Plan/Commt)
    D: Delivery
    S: Settlement to object with no budget control
    R: Revenue cost element
    C: Cost element is exempt cost element
    M: Minimum from actual + commitment and plan per order value update
    P: Plan value is not on apportioned order / network
    B: Plan Costing Single Position
    S: Funds Commitment in Balance
    Following is for material
    COSP 2011 01 8001110100     0000000200 KPPE D RMB             200,000.00  RMB   B
    Following is for service
    COSP 2011 01 8001110400  KPPP D RMB                                10.00  RMB
    regard
    mao jian

    Hi,
    Its not per item category. If  N or L sytem will check the budget if in your system if proper GL's are maintained in OBYC settings BSX and GBB > VBR nad cost elelemtns are created for them. for this you have to cosult with your MM / CO consultant.
    PS is highly inteergratd with CO and all values are updated per cost elements. If values are not updated in cost elements then budget chek wil not happen.
    In you case for material values may be updated in cost elements due to improper OBYC setting so budget check was not done.
    Chekc your OBYC setting and try to create material PR system will check for the budget.
    Check and confirm.
    regards,

  • Change mailform for Availability Control e-mail in Project Systems

    Hi Experts,
    We have set up availability control and maintained all the necessary tables in order to activate this.
    We are also auto forwarding this emails to outlook using SO36.
    Presently , mail content is as follows :
    Controlling posting 100007807
    The assigned funds are 807.22 INR less than budget in document item
    001 WBS element GSC-15-006-1-1-1-1 .
    I want to change content of this mail.
    how can i do this ?
    Thanks

    Hi
    How you are sending message from SAP to outlook, using autoforward option?
    If yes then remove the autoforward option from SBWP t.code. Once you receive the message from SAP system (Budget exceeded), copy the message and create the new message and send to the required user.
    Thanks
    S.murali

  • Availability Control e-mail in Project Systems

    Hi,
    We have set up availability control and maintained all the necessary tables in order to activate this.
    We are generating e-mails in Microsoft Outlook which is great, however I have been asked if we can change the content of the e-mail?
    The current layout is as follows:-
    Controlling posting 13224907
    Budget was exceeded by 1,100.00 GBP in document item
    001 WBS element B/000003-PREP-B .
    I want to be able to change this and add additional text.

    Hi
    How you are sending message from SAP to outlook, using autoforward option?
    If yes then remove the autoforward option from SBWP t.code. Once you receive the message from SAP system (Budget exceeded), copy the message and create the new message and send to the required user.
    Thanks
    S.murali

  • Exempted cost element not working for budget availability control

    Hi,
    I have configure the exempted cost element in our sandbox client. In the SAP IMG menu Project System -> Costs ->Budget-> Specify exempted cost element I maintain the following entry.
    COAr      cost element        Origin Group
    0200         433010                     *
    Then in the material master of a material I maintain the origin group in costing 1 view as 001. Then I do a material issue against the network of a WBS in MB1A tr code mvt type 281 and post the cost to the cost element 433010. As per the exempted cost element logic this should not affect the budget availability since the cost element 433010 is define as an exempted cost element. But the system shows actual incurrence for this transaction and reduce that must amount from the budget. I check this is the S_ALR_87013558 report. To re-ensure I do the Project Info database rebuilt in CJEN tr code then activate the availability control in CJBN but this is of no use. The S_ALR_87013558 still shows the budget available as total budget minus the cost incurred in the cost element 433010 in the above transaction.
    Please let me know if anybody has configured the exempted cost element in their client and have resolve this issue.
    Thanks and regards'
    Preetam

    Hi,
    This is a std SAP Functionality and system should exempt the costs for the cost element maintained in the Configuration for that Controlling Area.
    Muzamil

  • Purchase Requisition Committment and Availability Control

    Hi,
    We are using availability control based on usage 1 i.e. during the budget allocation/release, the availability control gets activated.
    Now i have poject structure where a user have already created PR i.e. committment of 10000 USD and whereas i got an budget of 5000 USD. So when i go in CJ30 and CJ32, then system is not allowing me to release the budget as the existing committment is greater than the budget.
    My question is that do this PR committment is to be considered as Real comittment. My understading is that if there is no budget then the committment of any type should not be allowed at first instance. How generally it works?
    Thanks in advance

    My understading is that if there is no budget then the committment of any type should not be allowed at first instance.
    Rajesh, Not everybody will use the budgeting functionality for Project, So it is not forbidden in Std. SAP design. But, if you want to forbid posting of committment cost or actual cost before budgeting, then read these notes
    Note 599813 - Availability control before budgeting
    Note 602588 - Availability control before budgeting
    Follow the suggestions mentioned in the note.
    Is there anything by which we can avoid the committment creation by using the user status on WBS element (even though the commitment is created at activity, it gets rolled up to the parent WBS)?
    As Gokul mentioned, you can restrict creation of PR on WBSE by User Status, but you cannot restrict rolling up of Commitment cost from activity to WBSE by any user status.
    Edited by: Ahmed Rifaee on Aug 13, 2010 3:22 PM

  • Can Budget Availability Control be turned off at WBS elements Level?

    For Project and WBS elements, we activate the budget  availability control in the budget profile and assign the budget profile to the Project. So once we budget one WBS elements under that project and release the project, the availability control is active for all WBS elemens under this project.
    My question is whether we can turn off the availability control for one WBS element under that Project and let the availability control on for the other WBS elements under that project.
    thanks,
    Ting

    Hi,
    I doubt if this can happen. CJBW will deactivate avalability control for entire project. Try OPSX for that particular WBS, it will reset budgeted status. Not sure if this will help, try and confirm.
    One more way could be assigning userstatus to the WBS and restricting 'Availablity control' by that status. This option looks more practical.
    Regards
    Edited by: Shrikant Rakate on Sep 10, 2008 9:21 AM

  • Internet expense report migrate with Project budgetary control

    Dear All ,
          Does anyone use Oracle internet expense and enable Oracle Project budgetary control  ?
          Casue Oracle Project standard function budgetary controls are not enforced for project-related expense reports
    entered in Payables , the expense report amout is not calculated as deduction of project available fund.
          for example : create one expense report $100 , complete manger approval and export to Payables .  Project budget $150.
          For out client  , the project  available fund should $50 . however , when I create one Procecument $80  and process fund checking . It will  be passed . because system considers the available fund is $150 ( not deduct expense report entry )  . Does anyone have workaround or customization solution ?
    regards,
    Karol

    Hi Jennifer,
    Are you using AME for Internet Expense Approval or Supervisory hierarchy.
    If using supervisory hierarchy than Signing limits of approving user must be define.
    Also apply the Recommended Patches - Patch 16234880:R12.OIE.B
    NEW! R12.1: Oracle Internet Expense Recommended Patch Collection (OIE RPC), March 2013 (Doc ID 1534509.1) -

  • BPC - Budget Availability Control

    Dear Experts,
    I am interested in knowing whether Budget Availability Check functionality is available in BPC. If not, then does it mean that when both SAP ECC and BO-BPC co-exist, the Budget Availability Control configurations are required to be maintained in SAP ECC through modules such as Funds Management, Internal Order or Project System.
    Thanks,
    Sudhakar Shetty

    hELLO,
    Can anyone provide a specific answer on the possibility of having Budget Availability Check in BO-BPC. I understand that data has to be transferred from an operational system like SAP ECC to BPC. And, so a real-time Budget Availability Check may not be possible in BPC. But, wanted to know whether there is a solution to this.
    Thanks and Regards,
    Sudhakar Shetty

  • How to hide or supress availability control screen in VA01

    Hi,
    I want to hide Availability Control Screen in VA01. Can you please help me how can i supress that screen.
    Regards
    Malik

    Hi Nabheet ,
    disabling the Button wont solve the problem , System automatically do availability check based on the stock and scheduled delivery date , if no sufficient stock then system will  propose new schedule line dates....
    so disabling the Button wont stop doing all these checks........it needs to be done thru config/E Spot which will skip all these validations...
    regards
    Prabhu

  • Error while creating Project Change Control - You are trying to access a page that is no longer active.

    Hi there
    We are on Release 12.2.4 (on Linux x86-64) and getting the following error while assigning the Agreement to a Change Control's Action Item. As a result of this we are unable to proceed ahead with completing the Project Change Control process.
    Any help will be greatly appreciated.
    Steps to reproduce
    Navigation - Project SU Vision Services Responsibility > Project > Control > Change Orders
    1. Create a new Change Order > Create a new Action > Impact > Check Financial Impact checkbox
    2. Under the 'Agreement Information' choose the Funding Agreement. Following error is thrown:
    You are trying to access a page that is no longer active.
    - The referring page may have come from a previous session. Please select Home to proceed.
    3. I tried clearing the cache, bounced Apache, and even restarted the entire Application Tier. The error doesn't go away.
    Regards
    Kabeer Khan

    Hi there
    We are on Release 12.2.4 (on Linux x86-64) and getting the following error while assigning the Agreement to a Change Control's Action Item. As a result of this we are unable to proceed ahead with completing the Project Change Control process.
    Any help will be greatly appreciated.
    Steps to reproduce
    Navigation - Project SU Vision Services Responsibility > Project > Control > Change Orders
    1. Create a new Change Order > Create a new Action > Impact > Check Financial Impact checkbox
    2. Under the 'Agreement Information' choose the Funding Agreement. Following error is thrown:
    You are trying to access a page that is no longer active.
    - The referring page may have come from a previous session. Please select Home to proceed.
    3. I tried clearing the cache, bounced Apache, and even restarted the entire Application Tier. The error doesn't go away.
    Regards
    Kabeer Khan

  • Delivery Proposal is DISABLED in Standard Order Availability Control

    Hi Experts,
    Please help me solve my issue, I almost checked everything under SPRO>SD>BF-->Availability Check, but still cannot resolve my issue.
    Following are the symptoms of the issue that I'm encountering:
    Material cannot be confirmed (even though there are stocks)
    Complete Delivery, Delivery proposal & One time delivery are disabled in Availability Control Screen
    Here are some of the relevant configs which I checked:
    OVZJ entry for sales area is C (Delivery proposal)
    Checking group maintained in Material Master
    Any ideas please? ANy help would be much appreciated!

    1) Check the reservations for the material in MD04. The available quantity might have been confirmed for earlier sale orders and hence reserved for those sale orders.
    There are 11,000 cases in unrestricted stock. No reservations for the material.
    2) Check the inhouse production time in MRP2 view of the material master. It should be filled with production lead time.
    Done
    3) In OVZ9, the checkbox "check w/o RLT" is unchecked.
    This is our current setup
    Net, issue is still there.

  • Availability control on statistical WBS element

    Hi everybody,
    The issue deals with <i><b>availability control on statistical WBS element</b></i>.
    <u>Part 1</u> : I released 25000 as budget (CJ32) for a <b>statistical WBS element</b>.
    Availability control is active for this WBS element.
    We made a good receipt (MIGO) for 20000 on an AUC (asset under
    construction) - so we get the value as statistical value on the WBS
    element -, then invoice verification (MIRO) and finally the asset
    transfer (ABUMN) from asset under construction to fixed asset.
    On this statistical WBS element we get +20000 (MIRO) and -20000 (ABUMN).
    The problem is that the amount that is used for the availability check
    is 0, instead of 20000 as you can check !!!
    We set a budget on the statistical WBS element in order to have the
    availability check ... and this is not working as the system in the described case shows 25000 as available but for me we should have only 5000 (= 25000 - 20000).
    <u>Part 2</u> : This is working perfectly (I get the expected value for available) when we use a <b>"real" WBS element</b>, put an expense on it, then run the period end closing tranction CJ88 in order to transfer the cost on an AUC, and finally run CJ88 again in order to transfer from AUC to fixed asset.
    Did anybody already encountered this problem with statistical WBS element ? How did you solve this (we would like to keep our statistical WBS element) ?
    Thanks in advance for your help.
    Benjamin

    Hi Benjamin,
    Pl go through the link below :
    http://help.sap.com/saphelp_47x200/helpdata/en/3e/a98337dd34ca76e10000009b38f8cf/frameset.htm
    I have not faced this but as far as I remeber for AUC Statistical assignments have some limitations.
    Any specicfic reason for keeping the WBS Statistical? Are you able to see "0" zero on this WBS in CN41.
    Regards,
    Sudhanshu
    PS: Assign points as a way to say thanks.
    Cheers,
    Sudhanshu

  • Activate projects in controlling area RCPL in 2011

    Dear sir
    i am create WBS , Ofter goods issue on MB1A ,MVT 221 , ofter enter wbs that time below error is come
    "Activate projects in controlling area RCPL in 2011"
    please provide ofter create WBS how to assign  wbs  over company,

    Hi
    Now something good. Profitability analysis (COPA) is a component using which you can analyse your profitability from different dimensions such as product,dealer,sales area, sales organisation and so on. If COPA is in the scope of project then only it has to be activated.
    Hence Profitability analysis is not required to activate at the initial times in co area as it automatically when you activate your operating concern.
    Activity based costing again, should be activated on the client requirement only.
    Regards
    Rajneesh Saxena