Project Based MRP run issue

Hi Friends,
There is one issue reg. Project Based MRP Run as below :
We are running MRP through MD51 (Project based MRP run). For this we are assigning FG material code under respective WBS Element which generates Network reservation with movement type 281Q  which is base of MRP run in MD51. After MRP run we get planned order generation and then convert it to Production order and execute Production Order to receive Project Stock after GR.
After receiving Project stock and then selling it through Post Goods Issue through SD cycle, project stock is consumed but network reservation is not getting closed which results in again generation of planned order if MRP is run again. 
I need your valuable inputs if we are missing any configuration setting which can set Final issue indicator in reservation while Posting Goods Issue (PGI) in SD because FI indicator checking will only ensure reservation doesnu2019t take part in planning again.
Your earliest reply will be highly appreaciated.
Regards,
Tejas

Hi Vivek,
Thanks for your reply. Actually my issue has got resolved the way suggested by Mario Adler.
Hi Mario,
Thanks for your solution. PGI through Project is working fine for me.
Hi Krishna,
Follow the procedure as suggested by Mario which will resolve your issue.
Once again thank you all for spending your precious time to respond my query.
Regards,
Tejas

Similar Messages

  • Generating a production order through projects, without MRP run?

    Hi to all
    Is it possible to generate planned orders and further proceed to production order through projects  WITHOUT MRP run?
    Regards
    surya

    create the production order in CO01 and assign WBS element in the assignment tab of the order.
    whether it ll solve ur purpose....
    ashis

  • Exclude special stock (project) from MRP run

    Hi,
    Would need to exclude special stocks representing project stocks from MRP calculation. Could not seem to find a way to control this via config similar to options available for blocked and in-transit stocks.  Is there an option to do this in config?  Thanks...

    Hi,
    You can exclude the stock by creating storage location MRP.
    Create separate str location for project stock by MMSC.
    In the material master of mrp 4 view, str location indicator - select Exclude str loc from mrp  for new ie, project str loc.
    Check your Plant & str location by checking Plant/ data view in material master whether you have excluded the correct str location which you have newly created.
    When mrp run system exclude this str location.
    Regards,
    Dharma

  • Project based MRP

    hi all,
    i have a requirement please help me.
    we are working on planning strategy 21 ( MTO with Project ).
    we have created some limited SFG codes which are common in almost all plants.
    suppose i have sfg material "A" in Projects "A,B,C,D "
    i want to run mrp on material "a" with specific project "B" only.
    is it possible in standard process ?
    if not what is the next solution ?
    please help

    hi
    you have to maintain the MRP VIews in the Material Master
    MRP Type PD
    requirement : "1" - Individual.
    MD51 is for project MRP run
    MBBS is the Project stock checking.
    chk this http://help.sap.com/saphelp_erp60_sp/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm
    regards
    muthuraman.d

  • CONSUMPTION BASED MRP RUN

    HI
    How to run the mrp run for various materials  which belong diiferent stroage locations with the plant.Pl five me transaction.
    Eg.
    If i have 100items which kept in various storage locations with the plant.But i have to run for mrp for that 100items.
    Regards
    UMAPATHY.M

    Easy solution is define the same MRP controller for all those 100 items in material master.
    Than activate the user exit M61X0001 using CMOD and SMOD (take help of developer if you need)
    in this user exit enter the code in function module EXIT_SAPMM61X_001
    select materials for one MRP controller (specified in user_par)
        WHEN '005'.
          UXPAR = USER_PAR.
          CONDENSE UXPAR.
          WRITE UXPAR+0(3) TO DISPO.
          IF DISPO IS INITIAL.
            EXIT.
          ENDIF.
          IF MT61D-DISPO <> DISPO.
            NO_PLANNING = 'X'.
          ENDIF.
    Than activate the user exit
    now in the tcode OMIX enter the 005 in user exit field and description is MRP controller
    now run the MD01 with plant and in the user exit key enter 005 and in parameter field enter your MRP controller now execute the transaciton adn it will only run for those material which has mrpp controller you defined here.
    This is the best solution for this kind of requirements

  • Change the MRP run fro Reorder Point to Forecast Based.

    Dear Experts
    My client is a battery manufacturing company, its Semi Finished product is Make-to-Stock and Finished Product is Make-to-Order. Initially the MRP was configured as reorder based and in Material master it was set as VM     (Automatic reorder point plng ). But now we need to change the MRP form reorder point to Forecast Based. The rolling forecast of the coming 3 three months is given in Planned Independent requirement (MD61) as version u201800u2019 - REQUIREMENTS PLAN.
    We have changed the MRP procedure in Material Master form VM to VV Forecast-based planning of the finished product but unable to get any result means no Automatic PR is getting generated, the we have changed all the materialsu2019 MRP procedure of that Particular BOM to have the required MRP and Automatic PR raise but still no expected result is coming.
    I would request you to provide your expert opinion to execute the Forecast Based MRP, what else should I do achieve the Linking between the Rolling Forecast and MRP instead of Reorder point. Should I have to make changes in Material Master (Only on finished product, In house developed/manufactured Product, Raw material etc), any configuration change in MPR and PR . Looking forward for your specialist advice.
    Regards
    Sony

    I have provided the demand in MD61 and make stock level of the material in such a way that it should raise the PR for MRP run but it is not generating any PR. have checked that if I put value in the forecast tab of the material master manually then it is raising the PR but I need the system to pick the value form the demand that I provided in MD61. Is there any configuration related issue to get the values form the demand and generate PR accordingly. Please guide
    Should I have to provide 'VV' at the first level of the Material at its master data or at each component of the BOM irrespective of
    the components for Semi-Finished (In house production), Raw materials (Procure from the supplier). Please suggest...

  • AFS MRP Run based on Category (Quality Grade-A, Quality Grade-B Etc.)

    Hello All,
    We have a requirement in AFS MRP Run.
    MRP should suggest the replinsment quantities for the higher quality material when there is a deviation in quality.
    E.g:
    The Customer requirement is 100PC of Quality Grade-A.
    But after quality chack, produced quanities are of Quality Grade-A : 90PC and Quality Grade-B : 10 PC.
    How to replenish the shortage quanity of Quality Grade-A:10PC.
    As the Customer will not accept the Quality Grade-B Product.
    Our GR is for 90+10 PC against the Order, there is no scrap also.
    How to map this requirement in AFS.
    MRP should suggest the replinishment quantities as per the category.
    This is a critical issue for us now. Suggestions will be rewarded.
    Thaks,
    Siva

    Dear Siva,
    First of all don't show your reward gimmick to get a solutions. As you are aware, we are not here to get a reward / bonus points. We are here to support and help SAP Community.
    This scenario can't be mapped directly in Std. SAP R/3 System with best of my knowledge.
    Please note that Quality scoring / Grading will come after Goods Receipt in SAP System.
    If you want to take care at the time of MRP run, then you have to create separate material / article master codes with your desired characteristics.
    Based on your MRP type, system will create demand, I mean Purchase Requisition. This demand you can convert into PO for both Quality Grades.
    Based on your usage decision, you can accept desired material Grade and other Grade you can Reject and sent to Vendor.
    If you have accepted in first place then if you want to Return back (inferior grade material) then you can use Return PO.
    Hope this info will be useful.
    Bye,
    Muralidhara

  • Budget error while issuing stock to the project based production order

    Ours is project based Engineering company, we mfg euipments for the client which is part of the project.
    We define separate WBS element for equipment to be manufacture & create reservation under this WBS element.
    Secondly we follow production process through PP & define BOM for equipment which contains component rquired to mfg the equipment. To control cost(budget) component group wise we create separate sub WBS element for each component group(plates, motors etc) under above equipment WBS element
    Kindly refer e.g.below
    1.  Equipment (Finished code) to be manufacture is attached on WBS MYC-210952-06-03
    2.  Production order(1003780) created with reference to above WBS element
    3   Material procured under WBS MYC-210952-06-03-001
    4.  Stock available under WBS MYC-210952-06-03-001
    We would like to issue material available under MYC-210952-06-03-001 to production order which is attached to WBS MYC-210952-06-03. (Tcode MB1A)
    System allows to issue stock, but gives budget error.
    Is it possible to transfer budget auto in the transaction MB1A itself from MYC-210952-06-03-001 to MYC-210952-06-03 or what is the best solution available for above situation.
    Kindly confirm.
    Thanks & regards
    Sanjay Karnekar

    Hi Sanjay,
    You have consumed a budget at lower level WBS for material procurement. And at upper level you want to do stock transfer.
    But while doing budget allocation you have distributed the budget from Upper level to lower level so there is no distributable value is avaialble at upper level for the amount of the materail stock you want to transfer.
    In this either you have to keep your all budget values at upper level where your doing equipment aeembly and not distribute the budget further at lower level.
    Now you alredy this so you cant do anything.
    Now you have following option available with you. You have perform following activity by the given sequence.
    Deactivate the Budget check by CJBW
    Do your stock transfer
    Do budget return by CJ38 from level WBS to upper level WBS
    Now Activate the budget check by CJBV.
    regards,
    Pradeep

  • MRP issue after MRP run

    Hello Everyone,
    We have a issue in the MRP process. When we run MRP it creates PR for additional quantity then needed not considering the Purhcase Order that exisits already. Below example will explain you in detail.
    Product A Plant ABC
    Stock 4
    Product A safety stock = 8
    Purchase Order creatred = 3
    So when MRP run it should create another Purchase requistion for Quantity 1 (4-8+3 =1). But it is creating a Purhcase Requistion for Qty 4 which means it is not looking into the Purhcase Order Qty 3 that is coming in. There is no minimum lot size or any rounding rule.
    Please can you tell me if there is a settings/config where we allow/not allow the Purchase Order to be considered during MRP run. I think it should be a plant specific config as for our other plant I dont see this happening.
    Any help will be appreciated.
    Thanks
    SAP Fan

    hi,
    Few checks:
    1. Check rescheduling horizon...
    2. check the plannning key set while running the MRP....is it NETCH...try with NETPL or NEUPL if doing for first time...
    Regards
    Priyanka.P

  • How to make MRP run based on Target Safety stock

    Dear Experts,
    For our MRP-planned materials with safety stock we would like MRP run to take into account  target stock level defined for each month.
    for example: we know the target stock level values will be for M1 = 1000, M2 = 0, M+3 = 5000 etc.
    MRP should then propose orders to replenish up to the target stock level at the end of each month:
    needs for current month = (target stock level defined for current month  minus safety stock)
    needs for M1 = (target stock level defined M1 minus safety stock)
    needs for M2 = (target stock level defined for M2 minus safety stock)
    etc
    Do you know if there is any simple way to achieve this?
    Thanks you!
    Elynn

    Dear Experts,
    in my company, we are facing exactly the same issue,  we would like the MRP to consider a target stock exaclty as described by Elynn.     To be more clear, if we could reproduce the TDSS like in SNP in MRP, we'll be happy !.
    We imagine already to manage the target stock level in APO DP and released into ECC6 as a different MRP element than Forecast.  this target stock should not be considered as forecast neither consumed by any sales order.   Only to force the MRP to generate planned orders to increase the final stock when needed.  This is only an idea, we have nothing tested yet.
    someone have an idea if there's a standard solution for make this ?  I mean, why this fonctionality exist in SNP but not in MRP?
    thanks for any help
    Celia

  • Viewing the mrp run output based on mrp groups

    Hi, please advise how to view the mrp run result based on mrp groups? also advise how to run mrp on the basis of mrp groups?
    thanks.

    Hi,
    Can you use MRP Controller instead MRP Group. Because you have option to view MRP result by MRP Controller in MD05.
    And you can execute MRP based on MRP Contoller by using user exit M61X0001 in MD01.
    Regards,
    Vishal

  • MRP Run - Planning file entry Issue

    Dear All,
    We are facing one problem in MRP Run. We run MRP in the background for a plant (MDBT) System is not creating planned order for few component. I have checked all relevant setting. I found that planning file entry is missing. I would like to know that how system can miss the material? How system creates & delete planning file entry ? I have some data related to this.
    Last MRP run date is 22-04-09
    PIR changed date on 30-04-09
    MDRE Run on the 30-.4-09 at night.
    MRP Run on 02-05-09 at night.
    Problem reported that no planned order for the material on 07-05-09.
    We have huge number of material so its difficult to check all material individually whether MRP run happend or not ?
    Please let me know the possible reason for this.
    Thanks & Regards
    Kundan Kumar

    Dear,
    If you carte materaial or uplod materail before activation plant for MRP this may be the cause for this.
    Planning File creates all the materials relevant for the planning run.
    The planning run and the scope of the planning run (which materials are planned in which planning run) are controlled by the planning file.
    For planning file entry use the following transactions,
    MD20 : Create planning file entry
    MD21 : Display planning file entry
    MDAB : Set up planning file entry in background
    MDRE : Check planning file entry Please run this in it will solve your problem
    All materials assigned with MRP are automatically entered in planning file entry.
    Depends on changes in material planning or in proposal , system will create planning file entry.
    When MRP run system will consider only which materials having entry in above contents of planning file entry. After MRP run system delete the planning file entry. And again material gone the changes like GI GR on any other demand  then system generate planning file enty again.
    Hope it will help you to understand basic concept.
    Regards,
    R.Brahmankar

  • How to carry MRP run based on MRP areas

    Hi All,
    I want to run MRP for selected MRP area irrespective of plant and material.
    Is there any configuration to get this option.Please let me know ASAP.
    Regards

    Please check these answered links:
    Run MRP by MRP area - Tcode?
    MRP-Run settings
    Re: material provide to vendor for MRP run
    Re: mrp run
    Re: MRP Run in an excluded Storage Location
    Edited by: Afshad Irani on May 5, 2010 12:30 PM

  • PROJECT MRP RUN

    Hi all,
    During mrp run with md03; Planned orders are created according to respective wbs elements. e.g one planned order will be for wbs 1; second for wbs 2 and so on.
    is it possible to club the requirement of all schemes?
    Regards
    Ramesh Arora

    Hi,
    Clubbing of Planned order is possible by changing lot sizing procedures. In Material master MRP 1 view which lot size is being used?
    Regards,
    Krishna Mohan

  • STO issue in MRP Run

    Dear All Experts,
    I am not from SD module but i have a query related to MRP Run. In our plant we have STO and it uses the 641 movement type. As i know During MRP Run STO is considered in net requirement calculation. It is the standard process. But in one of the plant STO is not being considered in net requirement calculation.
    In MD05 it is showing the requirement but it not increases the requirement. So what could be the possible reason.
    Please answer it. It is very important for me.
    Regards,
    Saurabh

    Dear Experts,
    This is the situation in which 4th line we can see that STO having requirement of 2. But available stock is not reduced by 2.
    And Dear Srinu S in this case delivery is not happened.
    Regards,
    Saurabh

Maybe you are looking for

  • Latency in Dreamweaver CS5 ... help me speed it up ...

    I hope someone can help me because this is driving me crazy. I was using CS3 for 3 years now and it worked beautifully, but my company made me update ot CS5 today. This runs so slow and when I start typing the code or select code from another documen

  • Web page breaks when adding utility JARs to my EAR

    Hi All, I am creating a Web Application (.war) that runs some java code and has some JSP web pages to control the code/display results (as a dashboard sort of thing). I have then put this .war file in an enterprise app (.ear file - I have done this a

  • XML Streaming to LabVIEW

    How could I input a streaming XML data set into LabVIEW? The XML data are measurements from an Xtorr mass spectrometer. Any help would be greatly appreciated.

  • Photo Printing on laserjet

    Can't find the settings for photo printing on my new laserjet m277dw ? Under paper it lists a lot of different paper types but no gloss photo paper and no photo quality settings. Help !!!

  • Solotion upgrade to 10.1.0.3, it show internal 500 error im em web console

    Note: solotion upgrade from 10.1.0.2 to 10.1.0.3, it show internal 500 error im em web console If you do not run the catpatch.sql script as described in this section and you start up a database for normal operation, then "ORA-13516: SWRF Operation fa