Project have resource which is not in enterprise resource pool

I am getting notification on project that the following assignments have been updated.
The assignments you own below have changed.
  Assigned to:
  Task Name: 
  Start: Remaining Work:  Completion: etc
I am not a project manager of the project neither owner. I m administrator.

Project Help --
It sounds like you are the Default Assignment Owner for the resource in question.  First of all, navigate to the Tasks page in PWA and locate the assignments in question.  Look in the Resource Name column for the resource who is actually assigned
to the tasks.
Next, I would recommend that you navigate to the Resource Center page, select the checkbox for only this resource, and then click the Edit Resource button to check out this resource for editing using the PWA interface.  In the Assignment Attributes
section of the page, locate the Default Assignment Owner field.  My guess is that you will see your name there, or perhaps no name at all.  Click the Browse button and select the name of this resource in the Pick Resource dialog, and then click the
Save button to save these changes.
Finally, the PM of this project will need to open the project or projects containing the tasks that you are seeing.  He/she will need to apply the Resource Usage view and then temporarily insert the Assignment Owner column to the right of the Resource
Name column.  He/she will need to set the Assignment Owner to the name of the resource for all tasks assigned to that particular resource, then save and publish the project.
Please let us know if this helps.
Dale A. Howard [MVP]

Similar Messages

  • I have songs which are not selected in my library, but are still on my Iphone. How can they be deleted? Can they be deleted manually?

    I have songs which are not selected in my library, but are still on my Iphone. How can they be deleted? Can they be deleted manually?

    Ariana...
    so I assume there should be some track of them
    Yes.
    In the iTunes Store on the right under Quick Links click Purchased (new).
    You'll be able to re download past purchases for free if you are a resident of the U.S., and have iTunes 10.3 or later installed.
    Downloading past purchases from the App Store, iBookstore, and iTunes Store

  • Resources view: how not to show resource from under Org Units

    Hello experts!
    In cProjects/xRPM 4.5, when we assign a user as Staffing Manager of an Organizational Unit, not only the resources from this Org Unit appear in his resources view, but also the ones from sub Org Units.
    We would like to prevent this, and display ONLY the resources at the same level.
    Is there a way to achieve this: BADI, authorizations?
    Thanks a lot!
    Matthias

    Solved by our own with a custom enhancement.

  • How to declare a JNDI resource which is not a datasource ?

    Hi,
    I'm looking for a way to create a jndi bound resource, as a jang.lang.String for instance, within oc4j enterprise console or maybe by editing config files.
    I'm trying to configure an application once for all, so that I can deploy a .ear which is identical for development, testing, validation, production, ... environments while being able to configure those instance independently.
    Can it be done with oc4j ? (it's intuitive to create a jndi bound resource if it's a datasource, but it seems to be the only kind of resource we can create) and if so, how ?
    thx in advance
    Olivier

    Hi Olivier,
    As far as I know, this is not possible. I see only three ways
    1. Add an OC4J startup class and bind the desired names into JNDI
    (not sure, whether this is really possible)
    2. If you need the bound JNDI objects only in a web application: just add them to your web.xml file
    3. Write your own provider and add it to the default application.xml or to your application's application.xml
    Best,
    Manfred

  • How do I change the track names on a cd I have imported which is not in grace notes?

    I have imported a foregn book on CD so gracenotes has incorrect track names and sequence. This means that disc 2 appears before disc one in the playlist. How do I change the tracknames so the discs will appear in correct order in the playlist?

    File>Get Info

  • Mail responds with this error when I have attachments which are not that large.  How can I get around this. very aggravating. error reads Your message has size 32.1 MB, which exceeds 28.3 MB, the maximum allowed by the server.

    error message is-Your message has size 32.1 MB, which exceeds 28.3 MB, the maximum allowed by the server.  What can I do to get it to accept larger files. This was only 4 pages scanned.

    You can use the Preview app to reduce the fille size or send multiple emails.

  • Project Templates with Enterprise Resources

    I'm using Project Server 2013 ( latets updates installed for both Client and Server)
    I've created a project template and attached this to a project type. My template has enterprise resources speciified. So far so good.
    Now I'm trying to create a project using this template and I'm getting some errors.  (See below)
    As soon as I remove the resources from my template the project creates fine.
    It looks like 'rsResourceCannotAddLocalWithSameNameAsEnterprise'  in the error below means that Project Server looks at the resource in the template and considers the resources in the template always to be a local resources. And of
    course the resource already exists in my enterprise resources and therefore the project creation fails.
    Datasets:
    ProjectDataSet
    Table ProjectResource
    Row:  RES_UID='0bb2c5b5-1716-e311-a1c1-005056992257' PROJ_UID='3121855b-f13b-e311-9f7f-005056991b52'
    Error rsResourceCannotAddLocalWithSameNameAsEnterprise (2058) - column
    RES_UID
    General
    Queue:
    GeneralQueueJobFailed (26000) - ProjectCreate.ProjectAddToMessage. Details: id='26000' name='GeneralQueueJobFailed' uid='353d845c-f13b-e311-9f7f-005056991b52' JobUID='3a21855b-f13b-e311-9f7f-005056991b52' ComputerName='13fdabbe-0ac0-4cca-b382-49d1853aec73'
    GroupType='ProjectCreate' MessageType='ProjectAddToMessage' MessageId='1' Stage='' CorrelationUID='147f4f9c-ae30-b04b-aec7-382a52fa5fdf'. For more details, check the ULS logs on machine
    13fdabbe-0ac0-4cca-b382-49d1853aec73 for entries with JobUID
    3a21855b-f13b-e311-9f7f-005056991b52.
    My questions are:
    Are Enterprise Resources in templates supported?
    Is there a way around this? We're trying to make it easy to select a subset of the enterprise resources available.

    I have experienced this exact same thing and my situation is highly irregular. 
    This is with Project Server 2013.
    I had an EPT with a Project Schedule that had Generic Enterprise Resources assigned and was able to create new projects without problems using the EPT from the New button in the Project Centre in PWA.
    I was creating new projects to test and demonstrate Portfolio Analysis and was able to model Organisational Capacity represented by my Generic Resources and also the Surplus/Deficit element of Resource Constraints on a Portfolio. The Hired Resource Report
    was failing.
    A Service Pack and Cumulative update were applied to the Server and now I cannot create new projects using EPTs that have a project schedule with Generic Enterprise Resources assigned to tasks in the schedule.
    I checked the error message for the Failed and Blocking job in the queue and the GUIDs were for my Generic Enterprise Resources. I deleted the offending Generic Enterprise Resources and then re-created them anew, edited the Project Template to have
    these Generic Enterprise Resources on the Project Team and randomly assigned them to tasks in the schedule to generate a notional demand for work in the Project Template. I then Saved the Template in Project as a new Project Template and edited my EPT
    to reference this new Project Schedule. 
    Same error encountered again.
    Perversely I can open the Template schedule in Project Professional and do Save As and save it as a new project to the Server and that works just fine - the schedule is visible in the Project Centre and I can edit the schedule in both Project Pro and in
    PWA.
    My hunch is that the Cumulative Update and Service Pack which were applied to try and resolve the failing "Hired Resources Report" in Portfolio Analysis, which sadly it didn't resolve - has probably provoked this interesting challenge as it is
    the only material thing to change on the Server during the time that this issue has manifested itself.
    Am I the only one to encounter this?
    Dominic Moss | MAPM Microsoft Certified Technology Specialist | Our Newsletter:
    PM News Project Server Specialists
    Project Server PRIME | Twitter:
    @Twitter | Facebook:
    @Facebook | Linkedin:
    Wellingtone

  • Sync extra AD attributes to Enterprise Resources

    Working with Project Server 2013...
    I am looking for a way to bring in AD attributes like employeeID and physicalDeliveryOfficeName and have them added and updated to user resources when running the "AD Enterprise Resource Pool Synchronization".  I cannot find a way to add any
    extra attributes for the sync job to connect to the resource.  Can this be done?

    Hi Nate,
    You should not write directly to project DB. To create/update Resource Custom fields in Project Server 2013, you can use .NET based Client side object model (CSOM)
    Your starting point to read about CSOM based Project Server API for custom fields will be
    http://msdn.microsoft.com/en-us/library/office/microsoft.projectserver.client.projectcontext.customfields_di_pj14mref(v=office.15).aspx
    Hammad Arif EPM Advice Blog
    Hello Hammad,
    have you updated enterpriseresource customfields with CSOM yet ? 
    Regarding informations from the Project Customization and Programming forum and after checking it on a dev system, i come to the conclusion that it is not possible with CSOM for resource level customfields (...at least not yet).
    Of course you can go with the PSI resource service (web/wcf), but only if you develop for on premise installations not for project online.
    So, question is how do we get customer resource data, from AD or 3rd party system, into ProjectOnline, without entering it manually :-)
    Greets
    Maik

  • Converting Local resource to corresponding Enterprise resource using Macro

    Hi Folks,
    Using Macro, we could replace a local resource with an enterprise resource. But what we want to achieve is replacing local res with
    corresponding Enterprise resource. 
    Can anyone help here? Thanks.
    Best Regards,
    Anuja

    Unfortunately it is not just a property wich is required to change the local resource into an enterprise resource. Project will overwrite the local resource's metadata with the enterprise resource metadata (calendar, rate, custom fields...). It could be
    quite complicated to override this process and require a complex coding solution.
    Why not asking the users to first create the project team from the enterprise resource pool, so they'll use from the beginning enterprise resources and will not have the dialog box while saving the project?
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • I have one folder with several projects all of which Aperure can not find the original.  I do not use referenced files.  I can't make any adjustments like cropping etc. What can I do to print any of these photos?

    I have one folder with several projects all of which Aperure can not find the original.  I do not use referenced files.  I can't make any adjustments like cropping etc. What can I do to adjust or print any of these photos?  IO have no ther projects with this problem.  My Aperture Library is automatically saved to two external drives.
    Dick Koos

    I have one folder with several projects all of which Aperure can not find the original.
    Have you checked inside your Aperture library, if the original files are still there?
    Try to find out, when the images in those projects have been originally imported, then open the Aperture library by ctrl-clicking it and using the command "Show package contents" from the pop-up menu. In the window that will open, select the folder "Masters" and browse the contents. You need to find the subfolder with the year you imported the images, then the folders with the month and the day.
    Are your original files still there?
    If yes, copy them to a folder on your desktop for safe-keeping, and then try, if repairing the permissions and the other Furst Aid tools will help Aperture to connect to these missing files again - see this link:  Repairing and Rebuilding Your Aperture Library: Aperture 3 User Manual
    If the First Aid Tools don't help, then check, if Aperture has moved the missing images to a "recovered folder". If not, reimport the images, you saved to your Desktop and use the Lift&Stamp tool to transfer any adjustment and captions to your reimported images.

  • Project Server 2010 - Active Directory Enterprise Resource Pool Synchronization limitations

    Greetings again.
    I have a quick question about the limitations of Active Directory Enterprise Resource Pool Synchronization.  Specifically, what has your experience
    been with extremely large numbers of users (10k plus).  Is anyone aware of a
    practical limit of users in your AD group you would recommend when using the
    Schedule Synchronization feature on a nightly or weekly basis?
    There is a caveat to this question however.  The client has decided (perhaps for some misinformed reasons) to allow access for every user, to every
    project site, within their PWA environment.  They’ve selected the View Project Site option within the
    Categories for the Team Members PWA Group for which 90% of their intended users reside.  So when we ran a couple test syncs in DEV with a smaller AD group of about 8,000 users, the sync understandably
    lasted upwards of 18 hours.  Obviously unacceptable for a PROD environment on a nightly basis and not necessarily ideal for a weekly sync either.
    Experience in addition to documents like these, “Best
    practices for managing a large number of resources in Project Server 2010” tell me that we are way over the practical limit of a scheduled resource pool synchronization...IF
    the client really desires that all users access all their sites.  But before I submit my recommendations, I wanted to check with the community just in case others may have found a way to synchronize large numbers of users (10k plus) on a nightly or weekly
    basis, within a reasonable time frame AND allowed all users to access all sites within PWA.
    What do you think?
    As always, thanks for your help.
    Chris Addis - MCTS

    Hello Hrishi.
    My delayed response has been due to a large amount of testing we have been performing on this particular topic.  Here is an update, please feel free to provide feedback.
    We went back to testing and spent more time reviewing the documents: 
    Best practices for managing a large number of resources in Project Server 2010 and
    SharePoint Server 2010 capacity management: Software boundaries and limits.  Our team interpreted those documents as saying, 1,000 security
    scopes per site is a recommended limit.  It does not say it’s a hard limit, just a recommended limit.  “When the recommended unique security scope boundaries are exceeded, performance issue can occur.”
    So we decided to perform some tests (31 in total) to try and get a gage of what we are seeing.
    We needed to establish a baseline first.  So we performed a series of 23 Active Directory Resource Pool Synchronizations with various settings in a clean, Out of the Box, environment in order to see some consistent numbers.  Here is it’s summary:
    Our AD group of 8,000 users took about 32 minutes, on average, every time to sync.  The difference between the first sync and last sync differed only by 1-3 minutes.
    Adding 40 project sites increased the average sync time from 32 to 120 minutes.
    Adding 100 users to each of those 40 project sites, did not increase the sync times.
    One setting (identified at this time) reduced the synchronization time.  It was the
    Project Site Permissions check box found within the Project Web App > Server Settings > Project Site Provisioning Settings area.  By deselecting this check box we reduced or synchronization time back to the 32 minute
    average.
    The View Project Site check box within the Project Web App > Server Settings > Manage Groups > Team Members group had no apparent effect on the sync times besides what we had gleaned from the Microsoft documentation.
    Naturally, this left us with a problem.  As I’m sure you know, by deselecting the check box (Project Site Permissions), our project sites are now (figuratively speaking) orphans with no connection to the parent site.  This generates
    a new set of issues.  For example:
    Newly created project sites cannot be accessed by the owner and team members.  They will require someone like the farm admin to come in behind them and add the intended users to the project site along with their required permissions.
    All current and futures sites will no longer have users added via the standard method of building a team and publishing the project, but will have to be added manually.
    You can use the Synchronize option found within Project Web App > Server Settings > Project Sites page, but that kinda defeats the purpose.  It would require constant updating on a per site basis to keep up with
    PM changes.  Not very sensible, but it does work.
    With this baseline information, we moved our tests into our DEV environment which somewhat mimics our PROD environment.  This environment has 352 project sites and we performed 8 tests.  This is where we had some large sync time numbers. 
    Here is the DEV test summary:
    With the Project Site Permissions check box cleared, our AD group of 8,000 users took on average 30 minutes to sync.  This was in line with our baseline times.  With the exception of one test sync that took 99 minutes to complete. 
    That anomaly is acquiescent with what I’ve seen over the years.  Sometimes syncs do some unusual things.
    With the Project Site Permissions check box selected, our AD group of 8,000 users took on average 690 minutes (11.5 hours) to sync.  Unacceptable of course.
    So here’s what we’ve learned when dealing with extremely large numbers of active directory users in your Resource Pool sync:
    We did not see a decrease in subsequent sync times after the initial Active Directory Resource Pool Synchronization as some might expect.
    Our attempt to decrease sync time via the option of removing the View Project Sites was not successful.  (Unless we interpreted Microsoft's document incorrectly.)
    However, our interpretation of the recommended software boundaries and limits of SharePoint Server 2010 as it pertains to security scopes per site at 1,000, appears to be correct.
    Using the option of clearing the Project Site Permissions does produce a reduction in AD sync time, but at a cost segregating your project sites and thus the creation of new processes of maintaining them.
    I’ll remind others that these results are particular to our environments, there may still be exceptions yet to discover.  Others may see numbers contrary to ours.
    The biggest surprise to some members on our team (myself excluded) was that we did not see a reduced sync time after any of our initial syncs.  Some are under the impression that after your initial sync, you should see reduced sync times.  I haven’t
    found that to be the absolute case in all situations, just in some situations.  The reason for this still eludes me.  Any thoughts would be appreciated.
    I’ll let this sit a bit longer, but if no one disagrees with the results, I think we have our answer:
    The number of project sites directly affects your Active Directory Resource Pool Synchronizations if you are using the
    Project Site Permissions option.  If you plan on synchronizing over 1,000 users
    and you have a large number of project sites, proceed with the knowledge that you may have performance issues and long sync times.
    As always, I’d love to hear from you or others just in case I’m missing something.
    Chris Addis - MCTS

  • Change Default resources Assignment Owner in Project Professional, in the checked-out Enterprise Resource Pool?

    Hi,
    i'm not able to change the default Assignment Owner (massive) in the Checked-out Enterprise resource pool in Project Professional 2013.
    I've also unlocked the "Windows account edit" in the Register Editor.
    Do you know if is this possible or i have to change it for each resource one by one???
    Thanks
    Best regards 
    Daniele
    Daniele

    Hello Daniele,
    I think what you are seeing is by design behavior. Per below article you can set the Default Assignment owner in Project Web Access and it appears in various places in Project client.
    http://office.microsoft.com/en-in/project-help/default-assignment-owner-resource-field-HA010167482.aspx
    If you want to set the same default assignment owner for multiple resources then you can try bulk edit option in resource center.
    Hope this helps.
    Thank you,
    Kiran K.

  • HT1386 I have a new apple iphone 4 and a ipod touch im trying to add songs from my ipod to iphone which are not on my computer it says my computer is not authorized how do i do this

    I have a new i phone 4 and an older ipod touch ...i have songs on my touch which are not on current computer ...i want to put songs on my iphone but computer says its not autorized ive read all the manuals they dont help . I cant update the ipod to new ios until i transfer bought items to library and if i do this i will lose my songs previously downloaded from cds onto my ipod the computer that had songs on it had to be restored to factory settings Can anyone help? The ipod has an old apple id associated with it and i dont have that id or password for it.Ive tried to recreate and change pass just doent work Thanks

    Hey jtom234412,
    Thanks for the question. Based on the information you have provided, it sounds like your device is not detected in iTunes for Windows. The following resource may help resolve this issue:
    iOS: Device not recognized in iTunes for Windows
    http://support.apple.com/kb/ts1538
    Furthermore, if your device is in recovery mode (displaying an iTunes symbol, with a plug), see the relevant information under Step 5.
    Thanks,
    Matt M.

  • Project Server 2013 AD Enterprise Resource Pool Synchronization Exception

    Hello,
    I am looking for assistance from the project server community.
    When I click “Save and Synchronize” on the Active Directory Enterprise Resource Pool Synchronization page nothing happens and the status does not change.
    This is a new instance of PWA and I am preforming this task using the farm admin account. The farm admin account can read AD.
    Error 1:
    w3wp.exe (0x1B98) 
    0x0B8C       Project Server              
    General      aeby7         
    Exception [bucketHash:F08803DE] Exception occured in method 'Admin.ResolveActiveDirectoryGroups' System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.    
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)    
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String searchRoot)    
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()    
    at System.Linq.Buffer`1..ctor(IEnumerable`1 source)    
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)    
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClassf2.<AdminResolveActiveDirectoryGroups>b__f1()    
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace: 
    at Microsoft.Office.Project.Server.Native.dll: (sig=[sig]|2|microsoft.office.project.server.native.pdb, offset=3C1E) at Microsoft.Office.Project.Server.Native.dll: (offset=1254D)                       
    d360539c-6d89-70e7-c077-92da686b0689
    Error 2:
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes: 
    System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.   
     at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)   
     at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String searchRoot)   
     at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()   
     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)   
     at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)   
     at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClassf2.<AdminResolveActiveDirectoryGroups>b__f1()   
     at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName,
    IEnumerable`1 actions)  . Standard Information: PSI Entry Point: 
    Project User: i:0#.w|[DOMAIN\UserID] Correlation Id: f1f1a77f-6b45-e311-9407-00155d2abe21 PWA Site URL: [PWA URL] SA Name: Project Server Service Application PSError: GeneralUnhandledException (42), LogLevelManager Warning-ulsID:0x00101622 has no entities
    explicitly specified.

    Hi,
    I also get the same error when I'm trying to do the synchronization between Enterprise Resource Pool and Active Directory.
    I am in a single domain topology between Project Server 2013 and AD, and I'm doning the synchronization with the farm admin account, who has read/write access to AD.
    Here are the last relevant messages I see:
    w3wp.exe (0x2BE8) 0x1568 Project Server General aeby7 Exception
    [bucketHash:F0FACBDF] Exception occured in method 'Admin.ResolveActiveDirectoryGroups' System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain, String searchPath, String searchFilter)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String encodedClaim)
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()
    at System.Linq.Buffer`1..ctor(IEnumerable`1 source)
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace:
    2b3d83ee10e5|2|, microsoft.office.project.server.native.pdb, offset=3C1E)
    at Microsoft.Office.Project.Server.Native.dll: (offset=1255D)
    w3wp.exe (0x2BE8) 0x1568 Project Server Unified Logging Service c91s Monitorable
    Watson bucket parameters: Microsoft Project Server 2013, ULSException14, 070f6ea0 "project server",  0f001181 "15.0.4481.0", 6962a0f6 "microsoft.office.project.server.administration", 0f0011ad "15.0.4525.0", 51ade0c4 "tue jun 04 14:42:44 2013",  0000020f
    "0000020f",  0000003b "0000003b",  0560164b "keynotfoundexception", 00101621 "aeby7"
     w3wp.exe (0x2BE8) 0x1568 Project Server General aeby8 Medium
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes:  System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain,  String searchPath, String searchFilter)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String encodedClaim)
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions)  . Standard Information: PSI Entry Point:  Project User: LUXAIRLG\SQLADMIN2012
    Correlation Id: 6cef3814-b3a2-e311-93f9-005056921080 PWA Site URL: xxx SA Name: PS2013 - Project Server Service Application PSError: GeneralUnhandledException (42). LogLevelManager Warning-ulsID:0x00101622 has no entities explicitly specified.
    w3wp.exe (0x2BE8) 0x1568 Project Server Project Web App af04k Medium
    Void SaveButtonClick(System.Object.System.Web.UI.WebControls.CommandEventArgs) : GeneralUnhandledException
    Any ideas?
    Thanks in advance

  • [svn:fx-trunk] 11652: The damageHandler needs to invalidateSize because the damage could have been caused by a programmatic change which would not have gone thru the EditManager .

    Revision: 11652
    Author:   [email protected]
    Date:     2009-11-11 06:06:14 -0800 (Wed, 11 Nov 2009)
    Log Message:
    The damageHandler needs to invalidateSize because the damage could have been caused by a programmatic change which would not have gone thru the EditManager.  Need to make sure invalidating the size and remeasuring doesn't cause another damage event to avoid an infinite loop.
    QE notes:
    Doc notes:
    Bugs: SDK-23052
    Reviewer: Gordon
    Tests run: checkintests, TextArea, TextInput, NumericStepper
    Is noteworthy for integration: no
    Ticket Links:
        http://bugs.adobe.com/jira/browse/SDK-23052
    Modified Paths:
        flex/sdk/trunk/frameworks/projects/spark/src/spark/components/RichEditableText.as

    My daughter has had her Razr for about 9 months now.  About two weeks ago she picked up her phone in the morning on her way to school when she noticed two cracks, both starting at the camera lens. One goes completely to the bottom and the other goes sharply to the side. She has never dropped it and me and my husband went over it with a fine tooth comb. We looked under a magnifying glass and could no find any reason for the glass to crack. Not one ding, scratch or bang. Our daughter really takes good care of her stuff, but we still wanted to make sure before we sent it in for repairs. Well we did and we got a reply from Motorola with a picture of the cracks saying this was customer abuse and that it is not covered under warranty. Even though they did not find any physical damage to back it up. Well I e-mailed them back and told them I did a little research and found pages of people having the same problems. Well I did not hear from them until I received a notice from Fed Ex that they were sending the phone back. NOT FIXED!!! I went to look up why and guess what there is no case open any more for the phone. It has been wiped clean. I put in the RMA # it comes back not found, I put in the ID #, the SN# and all comes back not found. Yet a day earlier all the info was there. I know there is a lot more people like me and all of you, but they just don't want to be bothered so they pay to have it fix, just to have it do it again. Unless they have found the problem and only fixing it on a customer pay only set up. I am furious and will not be recommending this phone to anyone. And to think I was considering this phone for my next up grade! NOT!!!!

Maybe you are looking for

  • How Do I use TM to find a file on my computers Idisk from today's backup?

    Where do I find the file that is on my Idisk's Time Machine Backup that was on my laptop this morning when TM backed up????? My Idisk had a problem this morning and when I sought help, they had me hit the stop and restart the syncing. The problem is

  • What is the best way to set up one family imac with multiple iphones?

    We basically have one imac that we all use (one user account). We also have our own iphones with our own apple id. What i would like to get my head around is setting up each iphone individually to use itunes.(i.e music, videos, contacts). It seems th

  • Drag and drop from Pallette not working

    I installed studio enterprise 8.0 When I click any object from the palette to drag into my design screen, it does not drag to a specific location. I don't have the option to move it around the screen and place it where I want. Is there a setting prob

  • Tour freezing up: uncaught exception: Application errors

    I have been experiencing frequent freezing up of my device fairly recently-- often when saving messages to memo pad, with the following message:  net_rim_bb_messaging_app (190) is not responding:  process terminated.  When the device freezes, I shut

  • Validation of profit center for MIGO transaction

    Hi! For MIGO transaction I want to restrict users of one profit center to post for another profit center. I have tried it with GGB0 , OB28 as well as OKC7 but i was unable to do it. please help me out with details. thanks Amit