Project Professional 2010 Not Publishing to Project Server 2010

I am having trouble publishing a project from Project Professional 2010 to the Project Server 2010 (PWA). What I am trying to publish is a master project which is contains many enterprise projects as subprojects. When I press publish, it prompts me
to save and if I click yes then it goes through and saves all the subporjects and then just stops there and doesn't publish the changes to the master project. If I press publish and click no to the save prompt then it gives me the status "sychronizing
data to server" for around 15 seconds and then just does nothing after the sychonization finishes.
It usually should be giving a "publishing job done 0%" or "publishing job completed" when it publishes, but it gives nothing like that. I also check the project through the PWA and it has not updated yet, but when I open it for editing in the client it has
everything updated and up to date, meaning that the save is working properly and just not the publishing.
All my subprojects are able to publish correctly, it's just this master project that is not working.
Does anyone know why this is happening? Is the publishing process timing out for some reason? Or is it something else?
Please help.
EDIT: The progress notification at the bottom of Project Professional just stops at "save completed sucessfully" whenever I try to publish

To check the queue, navigate to Server Settings > Manage Queue and view the jobs that are present. If there is an error when publishing you should see it in the queue.
Alex Burton
www.epmsource.com |
Twitter
Project Server TechCenter |
Project Developer Center |
Project Server Help | Project Product Page

Similar Messages

  • How do I create a project site after I publish a project in Project Server 2013?

    How do I create a project site after I publish a project from project pro 2013 in Project Server 2013? I'm trying to look for an option in the ribbon but haven't found any. 
    Thanks
    James T.F

    Hi James,
    See in the article the procedure for site provisionning settings.
    Note that the project site is created based on the template associated to the chosen project type (EPT) when the user first publishes his project. Be aware that if you allow the user to choose weither or not he'll create a sharepoint site when publishing
    his project, he will be prompted in Project Pro with a dialog box giving the choice to create or not the site.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • When finalizing iMovie with less than a minute an error message said can not publish because project is already open!

    My question is I get error message when finalizing imove projects saying "can not plublish your project with an open project"
    Where do I find this open project?
    Thanks
    John

    It seems like there's a number of these being posted all around the iMovie Discussion Group. So the solution posted most recently that seems to work for the largest number of people is this:
    This requires using the Terminal app, in your Applications/Utilities folder
    To turn off Time Machine snapshots type in the following command:
    sudo tmutil disablelocal
    The Mac will likely ask for your password, so type it in and hit the return key. The type the word, exit and hit return. Quit Terminal.

  • Unable to use project professional to establish connection to project server

    I fail to use project professional 2003 to access to the project server 2003 using MSDE 2000 in local area network, following message was shown,
    Connection failed:
    SQLState: '01000' SQL Server Error 1326 [Microsoft][ODBC SQL Server Driver][DBNETLIB]ConnectionOpen (Connect())
    Connection failed:
    SQLState '08001'
    SQL Server Error: 17
    [Microsoft][ODBC SQL Server Driver][DBNETLIB]SQL Server does not exist or access denied.
    I have seen these pages with similiar cases but can't help.
    http://support.microsoft.com/kb/818047/
    http://support.microsoft.com/kb/837653/en-us
    Can anyone help me?? Thanks a lot!

    Pher,
    Is this still an issue?
    Thank you!
    Ed Price, Power BI & SQL Server Customer Program Manager (Blog,
    Small Basic,
    Wiki Ninjas,
    Wiki)
    Answer an interesting question?
    Create a wiki article about it!

  • RoboEngine is not publishing RoboHelp Projects

    Hi All,
    We are currently using RoboHelp 2.0 that is installed on Windows NT box. We wanted to migrate our RoboHelp Projects from NT box to Windows 2003 Server.
    I have installed RoboEngine Configuration Manager 2.00.082 on Windows 2003 server but not able to publish the existing projects.
    Do you have any idea what are the steps need to be followed to configure the existing projects?
    Is there any settings we need to change for Windows 2003 server? Is Windows 2003 server supports RoboHelp 2.0?
    Kindly help me to fix that issue.
    Thanks for your help.
    M.P.

    Hi Mahesh and welcome to the RH community.
    That sure is an old copy of RH. Adobe is currently up to version 8 of both the RH Client and RH Server applications so I'm not surprised if things don't work as you'd expect on Windows Server 2003.
    Read the RoboColum(n) for a tips, tricks and musings on the Technical Communication Suite products.
    Follow the RoboColum(n) on Twitter

  • One photo will not publish on any server

    Hi, one photo in one of my albums just refuses to publish in any server, and leaves an empty space where it should be. I've tried replacing it with another photo, but the new one wouldn't publish in that spot either, and then when I removed the photo next to it to try and clean the page up, it left two empty spaces side by side. Any suggestions would be greatly appreciated.

    Hi Hazel, thanks for asking. The site hasn't been officially launched yet, but what's there is at http://SameHand.com. Then to see the problem area please go to "Imagery" at the top of the page, then down to the album at the bottom right called "Five Frames of The Same Shot". Then about 3/4 the way down that page you'll see an empty row where the one image refuses to print, and the one next it that's been removed. I've looked closely at the problematic image and it's title, and there doesn't seem to be anything different about it, and I've even tried a different photo in that spot, but nothing publishes. And if I reverse that one with the one next to it, the empty spot goes with it. Any help solving this strangeness would be greatly appreciated.

  • Upgrading Classic based 2010 web application to claim based 2010 web application in Sharepoint server 2010 RTM

    hi all,
    i have a web application with classic based authentication in SharePoint server 2010, need to configure FBA for the same app in SharePoint server 2010 RTM.
    While trying to change the Authentication Provider, m getting the Form option deactivated.
    please let me how to upgrade the Classic mode authentication web app to the Claim Based authentication web app.
    Thanks and Regards,
    Arun Kumar

    Hi Arun Kumar,
    Below the grayed out “Form” authentication type, is there a message with a link about how to enable Forms Based Authentication in claims mode?
    You should perform the following PowerShell script to convert the existing web application to claim based authentication.
    $w = Get-SPWebApplication "http://<server>/"
    $w.UseClaimsAuthentication = 1
    $w.Update()
    $w.ProvisionGlobally()
    For more details, please refer to:
    http://technet.microsoft.com/en-us/library/ee806890.aspx
    http://www.chakkaradeep.com/post/FBA-in-SharePoint-2010-requires-claims-mode.aspx
    Thanks & Regards.
    Lily Wu

  • OAB not updating on Mailbox Server 2010

    I have searched the forums and have not found a solution.
    Statistics: Two Mailbox servers with Exchange 2010 SP3 RU6. One CAS/HT with Exchange 2010 RU6.
    OAB last date modified on the generating Mailbox server is August 28 and today is September 8. Several changes are not showing up in the Offline Address Book.
    The LZX files and oab.XML show up on the mailbox server I set as the generating server, however they never update. I have restarted every server and still the same problem persists. I have restarted FDS on the CAS and BITS on the MBX. Moved the generation
    server several times. Ran Get-OfflineAddressBook | Update-OfflineAddressBook -verbose and see no errors. There has to be something simple that I am missing.
    Thanks,
    Don

    Hi
    Have you moved mailboxes from older Exchange Versiones? If so, please use this command to check legacy Mailboxes.
    get-mailbox -resultsize unlimited | Where { $_.RecipientTypeDetails -eq ‘LegacyMailbox’ }
    I also recommend you to set the Diagnostic Logging on the OAB Generation Server to Expert for OAB Service.
    http://technet.microsoft.com/en-us/library/dd335139(v=exchg.141).aspx
    Georg

  • While in imovie, when working on a project, I can NOT view the project in the right hand screen. I have made several videos and it has always worked before. I am not able to edit the videos because they won't play in the right hand screen.

    The videos that I import (and are located on the bottom of imovie) will show up and play on the right hand screen. But if I move that clip to the actually project area it won't play in the right hand side! I somehow must have clicked something that now won't play the project videos and now plays the clips below instead! Help please I need to fix this! Everythign else works, I can still edit videos, add transitions, music, etc I just can't see it on the right hand side- so I can't edit because I can't see

    See my post here on how to do this.
    https://discussions.apple.com/docs/DOC-4141

  • Palm Pre does not Sync with Exchange Server 2010

    Only folder architecture visible.  No content.  Is there a fix coming or workaround available?
    Post relates to: Pre p100eww (Sprint)

    This was reported recently in this thread:
    Pre and Exchange 14
    http://forums.palm.com/palm/board/message?board.id=wireless_email&message.id=8867

  • Sharepoint 2010 - Not able to access Sharepoint 2010 Public facing site on mobile browsers

    Hi All,
    Earlier, I posted a similar question in the forum , but did not get appropriate response . Posting it again with some more information .
    We are not able to access Sharepoint public facing site on Mobile browsers like chrome, IE, Safari (However the site is working fine on Firefox mobile browser and on PC/Laptops as well .)
    Following is the error we are getting :
     "Cannot set custom attribute on mobile controls in this page. Custom attributes specified are Access Key=0."
    I checked in the event logs , following was the exception :
    Exception captured in Exception HttpModule: System.Web.HttpException: Server cannot append header after HTTP headers have been sent.
       at System.Web.HttpResponse.set_RedirectLocation(String value)
       at Microsoft.SharePoint.Utilities.SPMobileUtility.Redirect(String url, SPRedirectFlags flags, HttpContext context, String queryStrings)
       at Microsoft.SharePoint.ApplicationRuntime.SPRequestModule.HandleMobilePageRequest(HttpContext context)
       at Microsoft.SharePoint.ApplicationRuntime.SPRequestModule.PostResolveRequestCacheHandler(Object oSender, EventArgs ea)
       at System.Web.HttpApplication.SyncEventExecutionStep.System.Web.HttpApplication.IExecutionStep.Execute()
       at System.Web.HttpApplication.ExecuteStep(IExecutionStep step, Boolean& completedSynchronously)
    Also, there was a microsoft OS security  patching on our farm servers post which the error starts coming . Following were the patches that were installed
    1. MS14-005          
    KB2916036          Security Update for Windows Server 2008 R2 x64
    Edition (KB2916036)
    MS14-009          
    KB2898857          Security Update for Microsoft .NET Framework 3.5.1
    2. on Windows 7 and Windows Server 2008 R2 SP1 for x64-based Systems
    (KB2898857)
    3. MS14-009          
    KB2901112          Security Update for Microsoft .NET Framework 3.5.1
    on Windows 7 and Windows Server 2008 R2 SP1 for x64-based Systems
    (KB2901112)
    4. MS14-009          
    KB2911501          Security Update for Microsoft .NET Framework 3.5.1
    on Windows 7 and Windows Server 2008 R2 SP1 for x64-based Systems
    (KB2911501)
    5. MS14-011          
    KB2909210          Security Update for Windows Server 2008 R2 x64
    Edition (KB2909210)
    6. MS14-012          
    KB2925418          Cumulative Security Update for Internet Explorer 8
    for Windows Server 2008 R2 x64 Edition (KB2925418)
    7. MS14-015          
    KB2930275          Security Update for Windows Server 2008 R2 x64
    Edition (KB2930275)
    8. MS14-016          
    KB2923392          Security Update for Windows Server 2008 R2 x64
    Edition (KB2923392)
    Has anyone of you ever faced similar(site not opening on mobile browsers) issue after installing these patches on farm servers .
    Any help would be much appreciated .
    Thanks
    Saquib Khan

    We have found below error related in ULS as well as event viewer both :
    Exception captured in Exception HttpModule: System.Web.HttpException: Server cannot append header after HTTP headers have been sent.   
     at System.Web.HttpResponse.set_RedirectLocation(String value)   
     at Microsoft.SharePoint.Utilities.SPMobileUtility.Redirect(String url, SPRedirectFlags flags, HttpContext context, String
    queryStrings)   
     at Microsoft.SharePoint.ApplicationRuntime.SPRequestModule.HandleMobilePageRequest(HttpContext context)   
     at Microsoft.SharePoint.ApplicationRuntime.SPRequestModule.PostResolveRequestCacheHandler(Object oSender, EventArgs ea)   
     at System.Web.HttpApplication.SyncEventExecutionStep.System.Web.HttpApplication.IExecutionStep.Execute()   
     at System.Web.HttpApplication.ExecuteStep(IExecutionStep step, Boolean& completedSynchronously)
    Saquib Khan

  • MacBook pro late 2010 not charging, MacBook pro late 2010 not charging

    The ac charger info says that charer isn't connected when it is !! I have tried 2 chargers and no luck!!

    reset the SMC
    http://support.apple.com/kb/HT3964
    see http://support.apple.com/kb/PH11294

  • Unable to save/publish Projects on Project Server 2010() using Project Pro 2007 and 2010

    Hi,
    Recently we have upgraded from Project Server 2007 to 2010 SP-2 (BCM enabled) environment and from last few days we are getting issue with Project Plans where PMs are not able to update Projects means save and publish the Project using MS Project  2010/2007.
    Whenever PMs try to open project using MS Project 2010 SP-2, it gets load successfully but when they hit save and publish no jobs are getting fired up nothing is happening. Only way to get out from MS Project 2010 window is to close the Project window and
    and click discard changes. No error and exception windows are popping out in MS Project 2010, no error/problem/issue clue at all from MS Project 2010.
    But when I try to update this Project plan for very first time using MS Project 2007 Sp-2 then I am getting below error
    for any subsequent save and publish using MS Project 2007-SP2 getting below error
    As an alternative I have tried to open this Project Plan using web and there it is getting opened saved and published successfully from PWA absolutely no issue.
    Also I have saved this Project locally as XML and saved and published it on Server successfully. But after someday again this project got corrupt PMs started getting same problem again
    I have also looked at ULS logs but not getting anything useful there.
    So any guesses why this could happen that can give me pointers to find actual root cause, please let me know.
    Thanks much !!!
    Sachin Vashishth MCTS

    Used below steps to fix the Projects on MSP 2010.
    1) Open corrupted project in MS Project connected to PS 2010 Prod env.
    2) Goto > Resource > Add Resource  > Build Team From Enterprise
    3) Check is there any local resource who has not replaced with corresponding enterprise resource. If yes then replace all those local resources with enterprise resource. If not then move to next step.
    4) Open resource sheet view and sort or filter by local resources.
    5) Then add few columns in resource sheet view like "Windows User Account, Email Address , Base Calendar etc".
    6) Now check has any local resource having enterprise attribute assigned to it, if yes then delete or assign local value as appropriate.
    7) Then GoTo > File > Save & Send > Save as project file > Save for sharing (at local location)
    8) Close project plan window and click "Yes" to save changes.
    9) Restart MS Project 2010 and open your project from local location.
    10) Then Goto > File > Save & Send > "Publish to Project Server". This will open "Import Project Wizard" to validate Resources and Task in Project.
    11) Then in Import Project Wizard window at left hand side click "Map Resource" to validate project resources.
    12) This will "Map Project Resource to Enterprise Resource " check all the resources highlighted with "Red" font and map "Standard" calendar to local resources.
           Note: Don't worry about local resource assigned "Standard calendar" but still highlighted "Red".
    13) Then click "OK" and click on "Continue to step 2" at bottom of "Import Project Wizard".
    14) Make sure you get number of errors 0 in step 2, else click on validate resource and take proper corrective action as explained in step 6.
    15) If you leave at least one resource as a local resource (unmapped to an enterprise resource), you will see the local resource in the Import Resource grid on the right side
    of the Confirm Resources page.         
    Examine the value in the "Import" column (if not able to see this column then insert this as new column) for the local resource . 
    The default value is "Yes", then change the value in the "Import" column
    to "No", else system will import the local resource as an enterprise
    resource.
    16) Then "Continue to step 3, 4 and 5".
    17) Then at Step 5 , Save project to Project Server by clicking "Save as" link.
    18) Then publish the project to update the plan at PWA 2010.
    Sachin Vashishth MCTS

  • Project Server 2010 / Sharepoint 2010 Permissions not syncing to Project Site

    Project Permissions not syncing to Project Site
    Project Manager Group
    New project is created and published project server sends permissions to Sharepoint which puts users into the following groups:
    <dir><dir></dir></dir><dir><dir>
    Web Administrator (Microsoft Project Server)
    Project Managers (Microsoft Project Server)
    Team members (Microsoft Project Server)
    Readers (Microsoft Project Server)
    At this time the creator/owner, owner’s management, portfolio managers, and executives should all have Project Manager rights on the sharepoint site, and Admins will have Web Admin permissions.
    Issue #1: Only the Web Admin permissions and creator/owner permissions are being added to the Sharepoint permission groups
    Workaround #1: Going into the project site permissions and adding the
    Project Managers (Microsoft Project Server) group manually and the sync will keep the permissions
    Workaround #2: Going into the Server Settings, Manager Groups then removing or add all users to the No Permission Group, which forces an sync to all workspaces. Con: This workaround can only be down at night when users are not active since it will
    block the queue for at least an hour.
    Project Owner Transfer
    Previously created project has owner change, once saved and published project server sends permissions to update user’s permission to
    Project Managers (Microsoft Project Server) on Sharepoint project site.
    Issue #2: When Project owner is changed and project is published the owner is not getting permissions to the Sharepoint project site. However, if owner is also added to the team using the Build Team Feature the sync will give the owner Project
    Manager permissions on the Project Site.
    Workaround #1: Going into Server Settings, Project Sites, select project and Synchronize. Once this is done, the owner will have Project Manager Permissions without being added to the team.
    Users who have been added to this project in Project Server 2010, but not assigned to tasks. Users who have assignments in this project in Project Server 2010 and are contributors to the project workspace site,
    meaning that they can create and edit documents, issues, and risks. Users who have published this project or who have
    Save Project permission in Project Web App and are contributors to the project workspace site, meaning that they can create and edit documents, issues, and risks. Users who have
    Manage SharePoint Foundation permission in Project Web App and are contributors to the project workspace site, meaning that they can create and edit documents, issues, and risks.</dir></dir>

    By default when you create project build team add users in the task and publish the project plan then All the User which are available in the project plan including Project owner will go to below mentioned group in project site:
    1. creator/owner, owner’s management, portfolio managers, and executives should all have Project Manager will get access to Project Managers (Microsoft Project Server)
    2. User who are having team member access to PWA will get Team members (Microsoft Project Server) access if they are assigned to the project task.
    3. User who are having team member access to PWA will get Readers (Microsoft Project Server) access if they are not assigned to the project task.
    4. Only PWA Administrator will get the access to Web Administrator (Microsoft Project Server)
    Sharepoint permission you have to use when you want to give permission manually to users on project site  
    In the Project Site provisioning setting under Server setting if you have Check to automatically synchronize Project Web App users with Project Sites when they are created, when project managers publish projects, and when user permissions change in Project
    Server.
    Then all the user get access as per describe above and if you will give access manually to any of the user either in project server group or in Sharepoint group once you will publish the project next time all the manually given permission will go away.
    IF you want to give permission to user manually to sharepoint group or project server group then uncheck automatically synchronize Project Web App users with Project Sites when they are created, when project managers publish projects, and when user permissions
    change in Project Server.
    You check PWA site setting --> Site permission then member of Sharepoint group user who will have access to sharepoint group in PWA site setting site permission will have access to all the project site sharepoint group as Project site inherit permission
    from PWA root site.
    Both the issue which you have described is behavior of project site.
    For issue 2 when first time project owner create and publish the project and projectsite is getting created then porject owner name gets access  in the porject manager (project server group) nect time if you will change the owner and publish the project
    until he will not present in the project plan will not get the permission.
    If you want to give sharepoint permission to users then uncheck automatically synchronize Project Web App users with Project Sites when they are created, when project managers publish projects, and when user permissions change in Project Server and give
    the permission manually. 
    Project site in 2010 has some issue and not full filling customer need some time ,Ms has came up with 2013 which is having tight integration with project sites .
    Project workspace security groups are equal to the SharePoint Server 2010 security groups.
    Web Administrator equals Full Control
    Project Managers equals Design
    Team members equals Contribute
    Readers equals Read
    Users who have Manage
    SharePoint Foundation permission in Project Web App and are contributors to the project workspace site, meaning that they can
    create and edit documents, issues, and risks will get access to Web Administrator (Microsoft Project Server)
    http://technet.microsoft.com/en-us/library/cc197668(v=office.14).aspx
    kirtesh

  • Project Server 2010 permissions granted through RBS are not flowing through to Project Sites.

    Hi,
    I have configured RBS as "The Project Owner is a descendant of the user via RBS"  its working fine for Projects.
    But users are  facing access denied issue when working with project sites RBS is not working for project sites.
    Can any  one Help me How can i grant permissions Automatically for project sites also as same like projects is it possible ?
    The Members in  Executives group can see all projects in organization but same like can they see all project sites ? 
    I have found one blog of
    RaymondRis he is recommending to do it manually as its not possible to grant Project site permissions Automatically.
    http://blogs.technet.com/b/raymond_ris/archive/2013/05/09/project-server-2010-permissions-granted-through-rbs-are-not-flowing-through-to-project-sites.aspx
    Thank You, Kumar KSV

    Kumar,
    The permissions to project sites is not cotrolled by the RBS, as you have discovered. It is controlled by the Security Category permisisons, and the settings if the permssions are auto synced. The permissions work like this:
    Project managers who have published a project or who have Save Project permissions on a project are added to the Project Managers (Microsoft Project Server) site group.
    Team members with assignments in a project are added to the Team members (Microsoft Project Server) site group.
    Other Project Server users who have View Project Site permission on a project are added to the Readers (Microsoft Project Server) site group. 
    As long as you use the Auto Sync of permisisons for project sites, i do not think there is any work around.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

Maybe you are looking for

  • Defining default value for financial reports display in the workspace (9.3)

    Hi I need to change the default value for financial reports workspace preview mode, for every workspace user. It is actually set on html, and I would like to have pdf instead. This option can be changed when logged on the workspace, in file->preferen

  • Illustrator file missing objects when placed in InDesign

    I created an Illustrator file that has text converted to outlines. Some of it is white and some of it is other colors. When I save the file as eps, pdf or export as jpg and then place the files in InDesign, the white outlined text doesn't show up. Ad

  • AMD cool n quiet

    Can I get some BIOS with AMD Cool n Quiet option enabled? I get irritate when my A8 5550m cant get higher than 2.1GHz when the CPU can handle even 3.1GHz. I can fix this with restarting only, and it get back to 2.1GHz when I power on my laptop G405s-

  • Suggestions for new sound interface

    I've been working with a Tascam US-122 for a while. It is a USB device and I've been running into a lot of latency issues. Can someone suggest a few firewire-based interfaces in the $300-400 range that would compliment my setup? Thanks!

  • Since Safari 3.0.4 lost admin access to SMC 7008BR router

    Mac OS X 10.4.11 Tiger and Safari 3.0.4 (523.12.2) versus SMC 7008BR router with firmware R1.84a. The normal way to configure the router is via the browser at URL http://192.168.100.254 (on my local lan). This will display a status page and a field i