Project Server 2010 Timesheets not Updating Project Plans

We have several project plans that are not getting updates from approved timesheets.
Troubleshooting steps I've taken:
1) Verified the timesheet/task submissions by the resources
2) Verified they have been approved
3) Verified they have been accepted by the Status Manager and processed
4) All project plans have been published (I even used ProjTool ON the App server to do a full publish of all plans as a second step of publishing)
5) Verified OLAP was built successfully overnight (and every night)
6) Tasks have both remaining work and NO actual work in the Resource Usage view
7) Had a user recall and resubmit his timesheet using "Send Timesheet" to see if the task updates would come through - they did not (I am Status Manager and the timesheet shows Approved), and even published the plan and rebuilt the OLAP again,
just in case.
8) Verified that no tasks are marked for closure under Close Tasks for Update in Server Settings.
9) Verified Timesheet shows Actual Work on the Tasks via Pivot Table; compared Timesheet_User_View with MSP_Portfolio_View pivot table for project which shows 0 hours. Timesheet_User_View shows 33 hours.
All tasks have Remaining Work, are within the date range of the timesheet and are open for submitting time. Timesheets are still out of sync with project plans for many users and there is no apparent reason. I'm out of ideas!

Hi,
In status manager's approval center, history, status updates, can you check the status of the approval? Do you have any errors in the ULs log for the approval or publish jobs?
Hope this helps,
Guillaume Rouyre, MBA, MVP, MCP |

Similar Messages

  • MS Project Pro file on Project Server 2010 does not accept [No Group] selection when clicking on Group view

    MS Project Server 2010 gives me the following error when I try to click on the [No Group] group:
    Error message:
    The group "" cannot be found. You tried to display a view that references a group that is not available.
    Specify a different group for the view."
    Note: When I look at the drop downlist for the Group on the View Ribbon, [No Group] appears in the Built-in section of the list. It also appears on the Organizer.

    Michael W --
    I have seen this error message several times when the project got corrupted due to drops in my network connection while the enterprise project was open.  If memory serves me correctly, the method for resolving this problem is to use the Save For
    Sharing feature.  To do this, complete the following steps:
    Add the Save for Sharing button to your Quick Access Toolbar, if you have not already done so previously.  Use the Project Options dialog for this.
    Open the project in question and click the Save for Sharing button.
    In the Save for Sharing dialog, save the MPP file in a location where you can find it easily, such as your Desktop.
    Close the MPP file and then reopen it.
    Click File > Save As and then click the Save button.
    Using this process, Microsoft Project will resolve the corruption in your project.  Please let us know if this process works for you.
    Dale A. Howard [MVP]

  • Project Server 2010 Site Template Update

    Hi,
    I have a Project Server 2010 environment in which there are several site templates created and there are about 500 projects.
    Now, I have the requirement of changing some templates (add a list, some fields in a existing Risks and Issues lists, etc.)
    How Can I update current template?
    If I update current template, Will the sites created be updated with the new lists and fields? Or Should I do these additions by hand?
    Thanks!
    José Quinto Zamora SharePoint and Search Specialist MCITP and MCPD in SharePoint 2010
    http://joSharePoint.com

    Hi,
    Another related question,
    We have created custom Web Template by saving as a template one site. Later we have created 20 sites using that Web Template. And now we want to update this template to "Site Template v2". We create other Web Template and now we have two
    "Site Template v1" and "Site Template v2". Should we remove "Site Template v1" from Solutions Gallery? Or it is neccesary while exists sites created with version 1?
    José Quinto Zamora SharePoint and Search Specialist MCITP and MCPD in SharePoint 2010
    http://joSharePoint.com

  • Project Server 2010: PWA Removing Default Project Site Security Groups When Creating a New Project

    I looked for this specific issue with Project Server 2010/PWA/SharePoint and could not find an exact answer... hopefully someone can help.
    We are currently using Project Server 2010 and have a number of project site templates that are used dependent upon the enterprise project type selected. Each of these project site templates have unique permissions which should create the default security
    groups on the project site upon publishing/syncing:
    <Project Name> Members
    <Project Name> Owners
    <Project Name> Visitors
    <Project Name> Project Managers (Project Web App Synchronized)
    <Project Name> Team Members (Project Web App Synchronized)
    Web Administrators (Project Web App Synchronized)
    Whether a user creates a project through PWA or Project Pro 2010 and imports the project into PWA, we get a weird result in the Site Permissions of the newly created project site. PWA will remove all default security groups from the project site template
    and add a whole list of users in the Site Permissions list without groups. 
    Once the project is published and the project site is created, we can then go back and add those default security groups back in the project Site Permissions and even add a couple of custom groups without them being removed on all subsequent project syncs
    or publishing. 
    How do we get PWA to not overwrite the project site templates' security groups and place each user in the proper default security groups? At the same time, how is PWA adding a number of users into the Project Site Permissions?
    Thanks in advance.

    Paul,
    Thanks for that information. Right now we are using the Test environment to turn the Auto-sync feature back on. I suspect that the reason this is happening is due to PWA groups/categories/security templates. There may be more than one PWA group that is "overwriting"
    the default project site groups upon initial creation of the project. We will look further into the security settings to tighten up the policies. 

  • Project Server 2013 timesheets not showing up for approval

    We're using Project Server 2013 and entering timesheets. I'm a team manager who is set up as the timesheet approver for a few people, including Nicole.
    Nicole opens her timesheet and fills it in for the week.  She applies time to four Administrative tasks and two project tasks.
    Nicole submits her final timesheet for approval.  (We have also tried having her save it first, then to the final submission, with the same results.)
    I go to my approval screen and see the four Administrative tasks listed as separate lines.  I do not see the project tasks.
    I select the four Administrative tasks and approve them.  They disappear when the screen is submitted.
    In previous weeks, and with some other employees, I would immediately see a single line item that said "My Timesheet" for Nicole which I could then approve.  But recently this stopped, and I do not see her timesheet.
    If Nicole checks the status of the timesheet it says it's submitted to me.
    On my Approval page if I go to History, Timesheets this timesheet is not listed under "approved by me" nor is it under "my resources unsubmitted timesheets."  It's in limbo.
    The only fix is for Nicole to recall the timesheet and resubmit it.  Then it shows up on my Approval page.
    Any suggestions?
    -- Paul

    We resolved this. The solution was as follows:
    Go to PWA Settings, and under Security choose Manage Groups.
    Click the Team Members group.
    Scroll to the Categories section, and in the Selected Categories area highlight (select)
    My Tasks.
    Click the box to allow the permission called Adjust Timesheet which is under the grouping for Resource.
    Now don't ask me how or why that works.  It's not a setting that intuitively matches what's going on.  But it fixed it for us.
    By the way, we had a number of other timesheet issues (view failures, etc.) that were all cleared up when we installed the April 2014 Cumulative Update for Project Server 2013, as well as SharePoint 2013 SP1.  I highly recommend both.
    -- Paul
    Paul LoSacco, Web Presence Team, Omnicare

  • Project Server Task Approvals not Going into Plan

    Hi,
    After approving a task, we are finding that it is not going into the plan - on our separate test environment, the same steps work ok.
    Any ideas?
    Thanks

    Hi,
    Could you please let me know, if the issue is happening for only one projects or all the projects.
    Also, Check for failure transactions.
    select
    ASSN_UID,
    * from pub.MSP_ASSIGNMENT_TRANSACTIONS
    where ASSN_TRANS_STATE_ENUM
    =4 and
    proj_uid like'Proj_Uid'
    Also let me know on which patch level you are on?
    Check if you have any projects affected with lost resource bug
    http://blogs.technet.com/b/projectsupport/archive/2014/02/06/project-server-2013-and-project-online-what-happened-to-my-resources.aspx
    SELECT DISTINCT A.PROJ_UID, P.PROJ_NAME
    FROM DRAFT.MSP_ASSIGNMENTS A
    LEFT JOIN DRAFT.MSP_PROJECT_RESOURCES PR ON A.RES_UID = PR.RES_UID AND A.PROJ_UID = PR.PROJ_UID
    INNER JOIN PUB.MSP_RESOURCES ER ON A.RES_UID = ER.RES_UID
    INNER JOIN DRAFT.MSP_PROJECTS P ON A.PROJ_UID = P.PROJ_UID
    WHERE PR.RES_UID IS NULL
    UNION
    SELECT DISTINCT C.PROJ_UID, P.PROJ_NAME
    FROM DRAFT.MSP_PROJECT_CALENDARS C
    LEFT JOIN DRAFT.MSP_PROJECT_RESOURCES PR ON C.CAL_UID = PR.RES_UID AND C.PROJ_UID = PR.PROJ_UID
    INNER JOIN PUB.MSP_RESOURCES ER ON C.CAL_UID = ER.RES_UID
    INNER JOIN DRAFT.MSP_PROJECTS P ON C.PROJ_UID = P.PROJ_UID
    WHERE PR.RES_UID IS NULL
    ORDER BY P.PROJ_NAME
    Thanks,
    Phani

  • Project Server 2010 - Unable to open project, no valid Project Detail Page could be found for the project error

    I have a workflow being deployed for the first time on a farm. When I create a project with an EPT connected to the workflow it runs and can enter the required field in a PDP.  Then I Submit the workflow to go to the next stage and I get the "Unable
    to open project, no valid Project Detail Page could be found for the project" error.  After that the project is stuck on the same error.  All of the 18 stages have PDP and Schedules assigned to them.
    Any ideas on why the workflow cannot see the PDPs?  Is there a farm permissions that I am missing?  Thanks!

    Hi David,
    It starts to be a bit technical for me, but here is what I found on the web (seems to be an authentication issue with Sharepoint 2010):
    http://social.technet.microsoft.com/Forums/en-US/120ab535-63d2-4205-a51f-1987e9c0cf79/sharepoint-fba-the-content-type-texthtml-charsetutf8-of-the-response-message-does-not-match-the
    http://social.msdn.microsoft.com/Forums/silverlight/en-US/5cc70ff6-50d9-4cd3-b092-12007f4e495b/response-message-contenttypebindingtype-mismatch
    http://stackoverflow.com/questions/5263150/the-content-type-text-html-charset-utf-8-of-the-response-message-does-not-match
    Hope it will help you going forward in resolving your issue.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Project Server 2010 TimeSheet line classification sorting order- Issue

    Hi,
    We have PS 2010 SP-2 environment , and having few time sheet custom line classifications in order to sort them I have prefixed my custom time-sheet line with numbers like 100, 110, 115 and it is perfectly sorted in Line Classification settings under server
    settings, please see below.
    But strangely when a user creates time sheet and click insert new row then "Add an existing task" modal dialogue box shows "Standard" OOTB line classifcation on top and all custom line classifications underneath it.
    Please check below
    Don't know why it is not considering sorting order defined under "Line Classifications" settings. Same configuartion used to  work fine in PS-2007. But dont know why its not working in 2010.
    May be some silly configuration I am missing or something serious here, seriously not able to make out why this is happening.
    Please let me know, Thanks much !!!
    Sachin Vashishth MCTS

    Hey Thanks Guillaume,
    That's what I want to confirm in context of 2010. Because same configuration used to work in our 2007 environment. So want to confirm its default behavior or I have missed something in configuration.
    Any other idea do you have, like putting some java-script code in modal dialogue box to get this sorting done or any other customization.
    As of now considering "javascript" but need some pointers to get start working on this.
    Thanks much !!!
    Sachin Vashishth MCTS

  • Project Server 2010 custom workflow - get project GUID

    I am trying to get the Project GUID from the ProjectWorkflowContext and all I get are zeros.  Any idea why?  Thanks!
    David L. Crooks

    Received the answer from Mark Laukkanen:
    Guid prjGuid = projectSequence1.WorkflowContext.ProjectUidl
    David L. Crooks

  • Project Server 2010 / Sharepoint 2010 Permissions not syncing to Project Site

    Project Permissions not syncing to Project Site
    Project Manager Group
    New project is created and published project server sends permissions to Sharepoint which puts users into the following groups:
    <dir><dir></dir></dir><dir><dir>
    Web Administrator (Microsoft Project Server)
    Project Managers (Microsoft Project Server)
    Team members (Microsoft Project Server)
    Readers (Microsoft Project Server)
    At this time the creator/owner, owner’s management, portfolio managers, and executives should all have Project Manager rights on the sharepoint site, and Admins will have Web Admin permissions.
    Issue #1: Only the Web Admin permissions and creator/owner permissions are being added to the Sharepoint permission groups
    Workaround #1: Going into the project site permissions and adding the
    Project Managers (Microsoft Project Server) group manually and the sync will keep the permissions
    Workaround #2: Going into the Server Settings, Manager Groups then removing or add all users to the No Permission Group, which forces an sync to all workspaces. Con: This workaround can only be down at night when users are not active since it will
    block the queue for at least an hour.
    Project Owner Transfer
    Previously created project has owner change, once saved and published project server sends permissions to update user’s permission to
    Project Managers (Microsoft Project Server) on Sharepoint project site.
    Issue #2: When Project owner is changed and project is published the owner is not getting permissions to the Sharepoint project site. However, if owner is also added to the team using the Build Team Feature the sync will give the owner Project
    Manager permissions on the Project Site.
    Workaround #1: Going into Server Settings, Project Sites, select project and Synchronize. Once this is done, the owner will have Project Manager Permissions without being added to the team.
    Users who have been added to this project in Project Server 2010, but not assigned to tasks. Users who have assignments in this project in Project Server 2010 and are contributors to the project workspace site,
    meaning that they can create and edit documents, issues, and risks. Users who have published this project or who have
    Save Project permission in Project Web App and are contributors to the project workspace site, meaning that they can create and edit documents, issues, and risks. Users who have
    Manage SharePoint Foundation permission in Project Web App and are contributors to the project workspace site, meaning that they can create and edit documents, issues, and risks.</dir></dir>

    By default when you create project build team add users in the task and publish the project plan then All the User which are available in the project plan including Project owner will go to below mentioned group in project site:
    1. creator/owner, owner’s management, portfolio managers, and executives should all have Project Manager will get access to Project Managers (Microsoft Project Server)
    2. User who are having team member access to PWA will get Team members (Microsoft Project Server) access if they are assigned to the project task.
    3. User who are having team member access to PWA will get Readers (Microsoft Project Server) access if they are not assigned to the project task.
    4. Only PWA Administrator will get the access to Web Administrator (Microsoft Project Server)
    Sharepoint permission you have to use when you want to give permission manually to users on project site  
    In the Project Site provisioning setting under Server setting if you have Check to automatically synchronize Project Web App users with Project Sites when they are created, when project managers publish projects, and when user permissions change in Project
    Server.
    Then all the user get access as per describe above and if you will give access manually to any of the user either in project server group or in Sharepoint group once you will publish the project next time all the manually given permission will go away.
    IF you want to give permission to user manually to sharepoint group or project server group then uncheck automatically synchronize Project Web App users with Project Sites when they are created, when project managers publish projects, and when user permissions
    change in Project Server.
    You check PWA site setting --> Site permission then member of Sharepoint group user who will have access to sharepoint group in PWA site setting site permission will have access to all the project site sharepoint group as Project site inherit permission
    from PWA root site.
    Both the issue which you have described is behavior of project site.
    For issue 2 when first time project owner create and publish the project and projectsite is getting created then porject owner name gets access  in the porject manager (project server group) nect time if you will change the owner and publish the project
    until he will not present in the project plan will not get the permission.
    If you want to give sharepoint permission to users then uncheck automatically synchronize Project Web App users with Project Sites when they are created, when project managers publish projects, and when user permissions change in Project Server and give
    the permission manually. 
    Project site in 2010 has some issue and not full filling customer need some time ,Ms has came up with 2013 which is having tight integration with project sites .
    Project workspace security groups are equal to the SharePoint Server 2010 security groups.
    Web Administrator equals Full Control
    Project Managers equals Design
    Team members equals Contribute
    Readers equals Read
    Users who have Manage
    SharePoint Foundation permission in Project Web App and are contributors to the project workspace site, meaning that they can
    create and edit documents, issues, and risks will get access to Web Administrator (Microsoft Project Server)
    http://technet.microsoft.com/en-us/library/cc197668(v=office.14).aspx
    kirtesh

  • Line Classification Reporting in Project Server 2010

    I’m trying to understand the Line Classification (LC) functionality and reporting in Project Server 2010 having not used this before. 
    I have added a new LC titled ‘Billable’ to the system and then added a task to my timesheet with the new Billable LC and then logged time to both the Standard and Billable LCs of the same task (not sure why MS have decided to call this Billing Category
    – rather confusing).  I was expecting that when the timesheet was approved the hours in both the Standard and Billable LCs would be combined and the total show-up on the task in the MS Project Professional plan but this appears not to be
    the case, only the hours logged to the Standard LC show in the project plan. 
    Is this correct or am I missing a step to get the new LC hours into reporting?
    Thank you.

    Hi Jane,
    I'll try to be more explicit. Hours logged against other LC than standard will NOT be lost, they will simply not be pushed to the project plan. Only those against standard LC will be pushed as actual work after PM approval.
    That being said, ALL actuals regardless of the LC will be in the Reporting DB and OLAP cubes for example. Meaning that using for example one of the 3 timehseet OLAP cubes, you'll be able to report actual hours against LC, periods, projects, resources, managers...
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2010 Resource Assigments - Need a license for every Resource?

    I am trying to determine the requirements for Project Server 2010 licenses.
    In Project Server 2010, I need to add resources to the pool, then assign a resource to a project task.  The task will be maintained/statused through a manager, not the resource.  
    Does that resource need to have a Project Server license even if the resource never accesses Project Server even through PWA?

    Hi JenKranich,
    You need licences only for users that will access
    Project Server data by any means :
    MS Project Pro, Sharepoint sites and/or
    PWA.
    But resources not associated with users are not "real person" accessing data but just informal entity, thus no need for licences for those resources.
    It is important to note that if those resources can access the SharePoint site, since it contains Project Server data (risks, issues, deliverables), then they DO need a licence.
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Any good training videos for project server 2010

    Hi All,
    I am working on SharePoint for several years and we had installed project server & created PWA site. But project server looks lot different from SharePoint. is there any good training video's for project server 2010?
    Thanks for any help
    Rithu

    Rithu,
    This would be a good place to start: http://technet.microsoft.com/en-us/library/ff628958(v=office.14).aspx
    There are also several videos on Youtube as well. I am not sure if there is a 'structured' course available for Project Server 2010
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Setting Up Earned Value Reporting in Project Server 2010, Using Hours Not Dollars

    Hello All,
    Are there instructions for setting up Project Server 2010 for Earned Value data capture and reporting?  I'm not certain that we are capturing the correct data to report EVM (i.e., Physical % Complete), and I was unable to find any videos on YouTube.
    Also, I noticed that Project Server 2010 defaults to reporting EV in Dollars.  Can we set it up to report in Hours instead?
    Julie  

    Hi Julie,
    If you allow to jump in to complement Dale's excellent reply and comment some of your concern...
    5. The status date is a fundamental parameter while talking about the EVM (it is ANYWAY a key setting for tracking projects with MS Project). The EV field will take into account actuals up to this date. Meaning that if your project plans have been updated
    by the PM on tuesday and you are running the analysis on friday, you set the status date to tuesday and the uncomplete work between tuesday and friday will not be considered as late work since you are running the analysis as of tuesday. The status date can
    be set from the "project" tab either in the project information dialog box or directly in the project tab, status group.
    6. MS Project proposes 3 EVM tables by default. A table is a predefined set of column which composes a view, together with a Gantt chart or a timephased grid. If you go to the view tab, click on "tables" then "more tables",
    you will find EV, EV cost indicators and EV Schedule indicators tables which will display the out of the box EVM fields calculated by MS Project based on the costs, actuals, Baseline, status date.
    Then about the cumulative data, you might be refering to S-curves which are a representation allowing you showing the cumulative values of the EV. To do that, you'll have severals ways:
    Use the cumulative calculated field in the visuals reports
    Create
    Dashboards from the report tab using the cumulative data (actual, Baseline, cost)
    Create
    MDX mesures in the OLAP cubes for cumulative data and create excel reports
    Develop custom SSRS reports
    Buy a 3rd-party addon
    Finally please let me give you an excellent reference for the EVM in MS Project with EPM Central blog articles:
    http://www.epmcentral.com/msproject/evintro.php
    http://www.epmcentral.com/msproject/evprereq.php
    http://www.epmcentral.com/msproject/evterms.php
    http://www.epmcentral.com/msproject/evexplain.php
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Server 2010 , Project Center, Resource Center, My Work not loading

    Hi,
    We have Project Server 2010 SP-2 env
    Yesterday one of my Project Manager told me that he is not able to access any of the following page Project Center, Resource Center, My Work in our Quality env. Issue is it shows page is loading infinitely long and on botton it shows some script error mentioned
    below
    Webpage error details
    User Agent: Mozilla/4.0 (compatible; MSIE 8.0; Windows NT 6.1; WOW64; Trident/4.0; SLCC2; .NET CLR 2.0.50727; .NET CLR 3.5.30729; .NET CLR 3.0.30729; .NET4.0C; .NET4.0E)
    Timestamp: Tue, 21 Oct 2014 13:55:19 UTC
    Message: 'null' is null or not an object
    Line: 217
    Char: 4
    Code: 0
    URI: http://XXXXXXXXXXX/_layouts/inc/pwa/library/webmethodmanager.debug.js?rev=BtnvMSOtt14tg%2FnfhDTJpA%3D%3D
    Also I have checked event logs in shows WebHost failed error with Event ID 3 , complete detail mentioned below.
    Event Log Error
    WebHost failed to process a request.
     Sender Information: System.ServiceModel.ServiceHostingEnvironment+HostingManager/45523402
     Exception: System.ServiceModel.ServiceActivationException: The service '/_vti_bin/PSI/ProjectServer.svc' cannot be activated due to an exception during compilation.  The exception message is: Could not load file or assembly 'FirePoint.SharePoint.RssViewerWebPart,
    Version=1.4.7.12, Culture=neutral, PublicKeyToken=e891f27e2edd24d0' or one of its dependencies. The system cannot find the file specified.. ---> System.IO.FileNotFoundException: Could not load file or assembly 'FirePoint.SharePoint.RssViewerWebPart, Version=1.4.7.12,
    Culture=neutral, PublicKeyToken=e891f27e2edd24d0' or one of its dependencies. The system cannot find the file specified.
    File name: 'FirePoint.SharePoint.RssViewerWebPart, Version=1.4.7.12, Culture=neutral, PublicKeyToken=e891f27e2edd24d0'
       at System.Reflection.Assembly._nLoad(AssemblyName fileName, String codeBase, Evidence assemblySecurity, Assembly locationHint, StackCrawlMark& stackMark, Boolean throwOnFileNotFound, Boolean forIntrospection)
       at System.Reflection.Assembly.InternalLoad(AssemblyName assemblyRef, Evidence assemblySecurity, StackCrawlMark& stackMark, Boolean forIntrospection)
       at System.Reflection.Assembly.InternalLoad(String assemblyString, Evidence assemblySecurity, StackCrawlMark& stackMark, Boolean forIntrospection)
       at System.Reflection.Assembly.Load(String assemblyString)
       at System.ServiceModel.Activation.ServiceHostFactory.CreateServiceHost(String constructorString, Uri[] baseAddresses)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.CreateService(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.ActivateService(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.EnsureServiceAvailable(String normalizedVirtualPath)
    WRN: Assembly binding logging is turned OFF.
    To enable assembly bind failure logging, set the registry value [HKLM\Software\Microsoft\Fusion!EnableLog] (DWORD) to 1.
    Note: There is some performance penalty associated with assembly bind failure logging.
    To turn this feature off, remove the registry value [HKLM\Software\Microsoft\Fusion!EnableLog].
       --- End of inner exception stack trace ---
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.EnsureServiceAvailable(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.EnsureServiceAvailableFast(String relativeVirtualPath)
     Process Name: w3wp
     Process ID: 5052
    Also I have checked Brian Smith blog to resolve WebHost error with Event ID 3, but that didn't help.
    So kindly help me to get this issue resolve and do let me know in case need further details.
    Thanks

    Hi,
    From error log it seems you have some custom or thrid party web part activated in your application and that web part is not able to load which might causing those pages to get corrupt.
    As a fix can suggest you below to two thing to check
    1) Remove that "FirePoint.SharePoint.RssViewerWebPart" from your environment and try to access those PWA pages again.
    2) Even after removing above web-part solution does not fix this issue, as it is quality env can you try to disconnect and reconnect the share-point farm . Then try to access those pages again.
    Share us the latest update and your finding on this issue.
    Regards
    Sachin Vashishth MCTS

Maybe you are looking for

  • How to specify fonts in text in SVG file?

    I've got an Edge Animate composition that includes a bunch of SVG files which specify (inside the svg files themselves) that a particular font should be used. So for instance, there's text in the SVG that's set to render in Arial. If I view that SVG

  • I'm connected but can't get browser, email or even FTP ????

    Special thanks for the article "Sun PPPoE on Solaris" by Phil Dibowitz and "Setting Up Solaris OS to Work with Cable Modems" by Muhammad Talha (I have DSL however). Without these 2 articles I wouldn't have gotten as far as I did. First off I'm runnin

  • Amazon UK and Playbook

    Hi there, I have been looking at buying a Playbook here in the uk. Yes you can get them at present from UK suppliers but know that it will us spec and would rather a UK one. However the online pre orders like Dixons and PC world have a  short window

  • Replacing video clip causes project to become corrupted.

    I'm not sure if this would be considered a bug or not, but I'll explain what happened.  I'm using CS4 with all Adobe software mentioned below. I'm working on an animation project that has foreground characters created using Anime Studio Pro software

  • When syncing iBooks this appears- 'Unknown error occurred (0xE8000004)', how can I fix this?

    I'm using 'The New Ipad' . When the message appears it also suggests a website that will help get it to work - http://www.apple.com/support/iphone/appstore/ - However, i've tried all of the suggested and nothing has worked. I've looks up many website