Project Server 2013 Default Pivot Excel report

Hi All,
We have configured the default excel report available in the BI Center. When we open the project overview report and select the project names we are getting the below error. But when we open the report in excel it is working fine. I have followed the steps
in the below post, but still same issue.
http://blogs.technet.com/b/excel_services__powerpivot_for_sharepoint_support_blog/archive/2013/01/31/powerpivot-for-sharepoint-browser-refresh-fails-data-refresh-not-supported-in-office-web-apps.aspx
Thanks in advance, Taj

Hello. The ODATA reports will not refresh / update in Excel Services when using Project Server on-premise, open these in Excel client to update. ODATA reports will refresh in Excel Services in Project Online (office 365). If on-premise, use either the
OLAP cube or the Reporting schema database tables / views as the data source in the Excel reports if you these to be refreshable in the web. Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS

Similar Messages

  • How to consume the Calendar Exception details from Project Server 2013 to an SSRS report using PSI ?

    Hello,
    Can anyone guide me how to access the calendar exception details from Project Server using PSI?
    I need to extract calendar details of enterprise resources , like exception name, exception type, exception start date and exception end date into my SSRS report hosted in SharePoint 2013 and 2010.
    I would be helpful if I can get a sample of this. I have read through many PSI documents in fact still going through ,what  PSI does and doesn't ,  PSI methods etc. from Project Server SDK and MSDN . Moreover, I
    am a beginner in .NET programming. I am confused and have lots of questions in my mind, like which PSI service should be used in my report(is it  just Calendar.svc), can we pull the details as XML type data source my SSRS report ,are
    there any other configuration settings apart from " setting up an event handler by installing an event handler assembly on each Project Server computer in the SharePoint farm, and then configuring the event handler
    for the Project Web App instance by using the Project Server Settings page in the General Application Settings of SharePoint Central Administration" (as per prerequisites for PSI in SDK) , how can I implement authentication settings
    -(when user with proper SharePoint permission
    can accesses the SSRS report  )
    Kindly bear with me if my questions are not appropriate .
    Please do guide me, and .
    Thanks in Advance!!
    Mridhula
    Mridhula.S

    Hi Brendan,
    Project server reporting database doesn't contain the calendar info. The only supported way to use the PSI to read the calendar info from Published database.
    See this
    reply from Amit.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Excel 2010 reporting with Project Server 2013

    Our company purchased SharePoint Server 2013 and Project Server 2013, mainly for the reporting/BI attributes. I read that the report templates, etc. that can be used by Project Server web app can only be accessed with Excel 2013?? Does that mean that our
    group/customers have to upgrade to Excel 2013 to take advantage of the Excel Services? This is a huge deal. Can you please let me know as soon as possible? Yikes!! :-O

    Hi,
    As far as I know, Excel 2010 is still supported by Project Server 2013.
    See here:
    https://technet.microsoft.com/en-us/library/ee683978.aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Server 2013 Report Configuration

    Hi All,
    We are using project server 2013. We have configured the reporting server according to the below URL. But some default excel report (especially graphs) are not working i.e not showing the data. When we try to refresh the report getting the below error. is
    there any additional configuration needs to be done.
    Thanks in advance, Taj

    Hi
    Is it a Odata connection ? If it is then it might not work.
    Below is the information taken from the site
    http://office.microsoft.com/en-us/office365-suite-help/office-365-known-issues-HA102919011.aspx?CTT=5&origin=HA102901439
    Excel reports using OData connections can't be refreshed in Excel Services  
    In both Project Server and Project Online, when an Excel file is selected and displayed in the browser using Excel Services, if the Excel file has connections to the Project OData feed, a user may attempt to refresh data connections, but the refresh will
    not be successful.  
    Workaround    To refresh your data, open the file in Excel 2013, refresh the data, and then save the file back to the SharePoint document library where it resides. Next time the report is viewed using Excel Services, it will have the most
    recent data.

  • Can new PWA views be created whereby a filter can be set and associate to the view by default? (Project Server 2013 ONLINE)

    My main question is: Can new PWA views be created whereby a filter for that view can be set, and associate to the view by default? (Project Server 2013 ONLINE)? and can I have a filter set to filter on person logged on to...
    In previous versions of Project Server, when CREATING a PWA view, we were able to apply/ define a filter for that view.  Does not seem like it is the case in Project Server 2013 Online.  And if I remember, we could also use the URL Guid_view_id. 
    Please confirm; and / or tell me how-to.
    What I was hoping to do is the following... Given that our standard that we have adopted for reporting time is 'My Timesheets' (fyi, Single Mode Entry=ON), we have some resources who have others who do it on their behalf via 'My Tasks' (ie., accomplished
    by using the 'Assignment Owner' field, accordingly).  Therefore, when entering time on someone else's behalf within 'My Tasks', we like to present the user that is logged in only the tasks that they are are assigned to update on others' behlaf.
    I know that there is another more elegant approach to doing this which may be to use the Delegation feature. But since we are trying to stick to Sharepoint Security mode for now, this is not an option for the time being.
    Any help appreciated would be greatly appreciated.
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    1- You still can define in Project Online a filter in the view settings, it is located just above the category setting. Here is a screenshot of the summary project center view:
    2- The view GUID is not anymore in the URL, since the URL triggers an action only on the webpart and not on the whole page. I agree this is annoying since it was great to send a URL with a specific view.
    3- Concerning the access to my timesheet versus my task, I'm not sure to get a full understanding but on a general way, it is much more easy to deal with those situation using categories which you cannot do with the SP permission mode.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to import the Issues list from an Excel File in Project Server 2013

    Hi,
    I'm using Project Server 2013.
    A Project Manager has been playing with the Issues List, deleting some fields, creating new columns and modifying some columns name. The result of this is that I'm getting this error everytime the task
    Reporting (Project Sync) is executed:
    General
    Reporting Wss list sync failed:
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='4feafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='5deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='69eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='75eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='81eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='8deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    Reporting message processor failed:
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='5beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='67eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='73eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='7feafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='8beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='97eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    Queue:
    GeneralQueueJobFailed (26000) - ReportingWSSSync.WSSSyncMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='98eafda7-f147-e411-940d-005056957f05' JobUID='9e937da7-f147-e411-940e-005056957f0d' ComputerName='b579360a-53ab-4fe0-bf9b-c62f5e8d3529'
    GroupType='ReportingWSSSync' MessageType='WSSSyncMessageEx' MessageId='1' Stage='' CorrelationUID='0945bd9c-0d6a-a0f1-47b0-68cdfcfbff9a'. For more details, check the ULS logs on machine
    b579360a-53ab-4fe0-bf9b-c62f5e8d3529 for entries with JobUID
    9e937da7-f147-e411-940e-005056957f0d
    What I'm trying to do is to create a new Project from the scratch, update the Issues List, not deleting or modifying columns, just creating new columns in order to match the names he (the Project Manager) put in his Issues List, then Export the list to Excel,
    and then create a datasheet view matching the Exported list, but here I don't know how to import the list (copy / paste or whatsoever it can be done...)
    Do you know how to do it, or do you know another/any method to solve this problem?
    Thank you in advance,
    José Espases

    Hi José,
    2 considerations: 
    The first one is that (as you experienced) one should not delete or rename any of the predefined columns in the risk/issue list. What you did is the right way, meaning keeping the native column as is and creating new ones based on the business needs. Finally
    you just need to create view with the appropriate fields.
    Then for importing risks from an Excel list, I can't test it right now, but you should have a datagrid view (MS Access type) allowing you pasting data from Excel.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2013 reporting security

    HI
    I have a question and I have seen a couple similar ones but nothing definitive on the topic of permissions/security for Project server 2013 (in project server security mode) for either Excel(Odata) reports or for SSRS reports. 
    Even setting security aside the Out of the box configuration is certainly not elegant or even usable.
    Situation:
    In PWA project managers and team members can only see projects they, own, are team members on, or have been granted permissions explicitly to. (Pretty standard - is using security templates and "my Projects"). We are using secure store
    and impersonation for access to reports. We do have report authors groups.
    As an example a PM needs to create a weekly  status report but should not have to pull all the data back to then filter for their one project.
    However, when a PM goes to either SSRS or Excel using oData they can see every project in the company.  This is just does not make a lot of sense. Why would I hit the database for 100projects when I only care about one and yet there seems
    to be a lack of information on the topic. In contacting Microsoft we were told there was nothing we could do that is how it was designed.
    REALLY???? (see above)
    What we have come up for our approach is  that we're currently using the UserID value to set parameters in our data sources, but are looking for more 'elegant' approaches
    to security (if they exist) as there are some liabilities with this approach (EX is a report author forgets to put the parameter in the users will get everything back.
    QUESTION:
    If there is not another approach then we will stay with it. We can't imagine there isn't a better way.
    Additionally, the Project user view only contains the identity of the project owner not the rest of the team members (including sponsors who might need to see the data.) so where are they in the database?
    Tasks

    Hi Paul,
    I have a similar situation only I'm using Project Online. I have setup Groups and Categories where there is a relationship between clients and groups, and projects and categories. 
    Only issue is that when running a report a user receives an error and then all the data shows for all projects irrespective of the group/category/project relationship and the fact that user only exists in one group (and therefore can't see
    or access the other projects in PWA outside of their group.
    Hope that makes sense.
    Regards,
    Conrad

  • Project Server 2013 - OOB Report do not work - Overview report...

    Hi.
    I have followed all of the step to configure reporting as mentioned in text book " implementing and administering project server 2013'. However after configuring the secure store, excel services, analysis service and sql 2012 I am unable to see the
    OOB reports appear with information.
    I have built the OLAP cube in projects service application successfully, however when I try to run the report no information appears.
    What can I do to resolve?
    Thanks

    I assume that you have configured excel services,secure store and built OLAP cube correctly and you are also having data in your Project server.
    You can open cube report and excel report, then select row column or value according the need it will display data.
    If you are using report viewer and author group make sure account from which you are trying to open report will have sufficient access or you can check with service account.
    Also check when you open report, you select enable data which appears in the upper ribbon of the reports.
    If you still facing any issue please let us know,what exactly is the issue.
    kirtesh

  • Excel Services for Project Server 2013 - Parameter

    I have an
    S curve graph project.
    Using Excel Services connected to Project
    Server 2013. You can pass parameter
    by querystring to filter design?
    Torres

    Hello,
    You could add the Excel Services report to a PDP and filter it using a query string filter web part, example below:
    http://azlav.umtblog.com/2012/12/05/filtering-excel-webparts-in-office-365-part-2/
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Default ODC connection in Project Server 2013

    Hello every one.
    Anyone know where the default ODC connector used in the BI reports is stored within Project server 2013. I need to create a custom default ODC connection so that the fully qualified domain name is used instead of the alias currently used.
    Thx
    mt

    Default location is
    /PWA/ProjectBICenter/Data%20Connections%20for%20PerformancePoint/English%20(United%20States)
    Hrishi Deshpande Senior Consultant

  • Need to create a TASKS page with a filter default in PWA Project Server 2013 (Online)

    Never done this so, I am wondering How to go about or what I would need to create a simple PWA page like "Tasks" in Project Server 2013 online where it default to a filter that is set to not equal to the user that is logged on?
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    The "my tasks" page or "my timesheet" are automatically filtered on the user currently connected. Unless you are using workarounds such as status manager or delegation, I see no way to bypass this.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Server 2013 reporting database change in Schema from Project Server 2010

    I have a current Project Server 2010 implementation, I am planning to migrate to Project Online.
    We have Customized Reports that consume from the PS 2010 Reporting DB.
    Are there differences in the Reporting DB schema  between PS 2010 and Project Online?
    My Question is: if we migrated to Project Online, will the reports crash?
    Another question is that, is PS 2013 Reporting DB schema the same as Project Online?

    Hi Atia,
    IN project server 2013 we have only one database instead of 4, it means draft, archive, published and reporting with in one database.Project Server 2013 reporting database schema tool that can be downloaded.
    http://blogs.msdn.com/b/project_programmability/archive/2013/01/28/project-server-2013-reporting-database-rdb-schema-reference.aspx
    There are differences in reporting of on-premises vs. Project Online
    The Project Server 2013 reporting schema includes three new tables, 27 new views, and a total of 33 tables and views that include new fields.
    Answer-1 : Yes there are some differences between PS 2010 and project Online.
    Answer-2 : Reports will crash as In Project Online you have to use ODATA to create report. You can not query project online data for reporting directly you have to have use ODATA. 
    http://msdn.microsoft.com/en-us/library/jj163015.aspx
    Answer-3 : NO, PS 2013 Schema and Project online Schema is different. 
    kirtesh

  • Project Server 2013 SSRS reports by logged in user group

    Hi All,
    We are using project server 2013. We have developed SSRS report. We need to display the projects based on the logged in user security group(e.g Project Manager, Administrator etc.) I tried with the below query got from a forums. But it is not working. Is
    there is any way to get the security group of the logged in user using SQL query.
    SELECT     MSP_WEB_SECURITY_GROUPS.WSEC_GRP_NAME, MSP_WEB_RESOURCES.RES_NAME
    FROM         MSP_WEB_SECURITY_GROUP_MEMBERS INNER JOIN
                          MSP_WEB_RESOURCES ON MSP_WEB_SECURITY_GROUP_MEMBERS.WRES_GUID = MSP_WEB_RESOURCES.WRES_GUID RIGHT OUTER JOIN
                          MSP_WEB_SECURITY_GROUPS ON 
                          MSP_WEB_SECURITY_GROUP_MEMBERS.WSEC_GRP_GUID = MSP_WEB_SECURITY_GROUPS.WSEC_GRP_GUID
    Thanks in advance, Taj

    Taj,
    The query above gives you a complete list of user groups and users. It does not filter by resource name/group.
    You can get the logged in user using the "USer Filter" webpart, on which the SSRS report is being displayed (assuming you are displaying it on a SharePoint page).  You will need to pass this as a parameter into your SSRS report.
    http://www.wonderlaura.com/Lists/Posts/Post.aspx?ID=214
    http://www.wonderlaura.com/Lists/Posts/Post.aspx?ID=91
    Prasanna Adavi,PMP,MCTS,MCITP,MCT TWitter: @prasannaadavi Blog: http://www.prasannaadavi.com

  • Project Server 2013 - Reporting ( Project publish ) Queue Job Error - 24006

    I am trying to publish a project and getting below error
    please provide me a solution your help greatly appreciated
    Reporting ( Project publish ) Queue Job Error - 24006 
    General
    Reporting message processor failed:
    ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='5a10ad83-4736-e311-941a-00155d0c1708' QueueMessageBody='Project
    UID='eaf690a4-5fda-e211-af15-b8ac6f50f278'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'.
    ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='e412ad83-4736-e311-941a-00155d0c1708' QueueMessageBody='Project
    UID='eaf690a4-5fda-e211-af15-b8ac6f50f278'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'.
    ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='6e15ad83-4736-e311-941a-00155d0c1708' QueueMessageBody='Project
    UID='eaf690a4-5fda-e211-af15-b8ac6f50f278'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'.

    If your farm is not updated please update it  from OCT  CU for 2013 project server.
    Please update it as cumulative update is having hotfix for this issue.
    http://www.intersoft.no/blogg/item/33-april-2013s-cumulative-update-for-project-server-2013
    http://www.datazx.cn/Fv7p5a/xw-US/dc6mbbt6-btss-fxi4-s8c4-8jsribt69m8x/nnn.projectserverexpertrs
    As per the 2nd link Oct Cu for 2013 is fix this issue hence i would suggest you to upgrade from OCT CU.
    kirtesh

  • Using oDATA for BI in Project Server 2013

    Hi gang,
    I am looking to create a BI report that I was able to do quite readily in previous versions of Project Server.  I'm trying to create a graph that simply plots resource capacity and work as measures over time, with the resource roles as a filter. 
    That is it, no more no less. Using Project Server 2013 ON-LINE.
    I have successfully connected to the tables using the Data Connection Wizard in Excel to do this.  Seems that these are 3 tables I need to get to the data I need--Resource, ResourceTimephasedData, and ResourceTimephasedData.  
    Fact of the matter is, timephased data tables are causing very very very long delays in populating the Pivot Report that I am looking for.  This a fairly new system with hardly any resource and project data in it yet.  This approach does not seem
    user friendly either.  I found it much easier in previous versions.  If I do recall, all my data is in one table before.
    I am wondering if I am approaching this in the wrong way.  Is there another way I should be looking at to get to my data and ultimately my graph?
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hello,
    Unfortunately not, OData if the way forward for reporting in Project Online. Is this still slow for you? When you do get more data in the system I would definitely recommend filtering this as much as possible at the source before Excel etc.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS