Hi all, 
Is there any way to see the detail information of a resource in PWA? In Project Professional 2013, we can check all the task\project the resource is assigned and all the planned work for the resource under resource usage view. However, we can not find it
in PWA. Any suggestion?
Regards,
Anna

Hi Anna,
From the resource center, you can select one or more resources and check for their availability. You'll have a graph will all resources assignments by time periods and projects with a grid for the details.
http://office.microsoft.com/en-us/project-server-help/view-resource-availability-HA010059812.aspx
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS |

Similar Messages

  • Project Server 2013 for Resource Planning & Project Portfolio Management

    We are looking to  use project server 2013 for resource and project portfolio management.  We are an IT department of approximately 600 growing to 1,000 within the next several years.
    We would like to us PS2013 to do the following :
    Manage Portfolio of Projects
    Manage Resources against this Portfolio
    Calculate Project Finances using resource roles and rates
    I would be grateful to have both comments on experience , both positive and negative.
    Thank You

    Many teams within organizations are turning to Project Server to help them control resources, deliverables and costs better.    It does resource management very well with work & cost resources, baseline costs, material costs, budget costs and
    out of the box earned value analysis (EV).  The Strategy (portfolio) component is very powerful and it will help you identify project that align to your objects then do what if analysis to find the right mix of projects.
    Here are a couple of things you should think about when moving to PS2013:
    1) Who will be using the tool?  If it is a mix of onsite staff, remote staff, vendors, contractors etc. you may want to think about a hosted solution.
    2) Training.  Don't assume everyone will just magically 'know' how to use the tool.  Train everyone (team members, PMs, Executives) then train them again.  It's the only way to truly get the value out of the tool.
    3) Who will manage the system?  This is not a typical application.  The right administrator needs SharePoint, Project Server, SQL Server,  MS Project, Analysis Services and SQL Report writing skills.  Please note that much of this can
    be learned by the right person but DEFINITELY find the right person.
    4) Don't start customizing right out of the box.  You will get frustrated.  Adjust your organization to the tool early on.  I know that is easier said than done but you need a realistic approach to get tool acceptance moving early.  
    5) Use workflows but don't use them right out of the gate.  Workflows are great but I suggest you wait until phase 2 or 3 to start aligning them to your business processes.  
    6) Lastly and most importantly, you must first establish your own business processes THEN  align them to the tool.  DO NOT assume the tool will create business process for you.  You must think about how you are going to initiate a project,
    how are you going to track deliverables, how will time sheets be managed, etc.  Get to a whiteboard, crack open Visio and start building and establishing your processes now.  PS 2013 is pretty flexible and usually will align well with existing business
    processes.
    And don't forget to hire a good consultant.  They can be brought in during key phases of your roll-out to add value, help you avoid risks, and provide you with best practice advice.
    Good luck.

  • Project Serial Number column in Project Server 2013 (PWA)

    Hi All,
    Whenever any new projects are created on Project Server 2013, they are arranged automatically by Alphabetical order. So i would like to know or need support through which i can create serial number column in Project Center so that projects are aligned. as
    per numbers.
    Kindly help..

    Hi,
    It is actually 2 questions. 
    First you want to create a unique ID for projects? Here is an excellent
    blog about this subject.
    Then you want to sort projects along a number? It could be a custom number field or the unique ID above. You just have to go to the server settings, manage views and go to the "sort by" section and select your number field.
    Note that the field used to sort the project center view must be in the view to be used as a sorting criteria.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Task column not editable in Project Server 2013 (PWA)

    Hello,
    is that possible that Project's task column which are published on PWA cant be editable for any Project Manager, Team members?
    We have  a scenario where my management team wants that after creating project from MS Project Professional 2013 (where we have provided standard template for projects to chose from ) needs to published on PWA. After publishing it, no one can't modify
    task name in Projects but can add task if required.
    Is it possible??

    For the field:
    Go to server settings, enterprise custom fields and lookup table,
    Click on Create
    Select task type, then formula,
    Click on the field selector button and pickup the [task name] field under the text group,
    Save.
    For the view:
    Go to the server settings, then manage views,
    Select the view in question under "project" (for example tasks details)
    In the field section, select your new field from the left side and add it to the right side,
    Select the default task name field from the right side and remove it (it'll go to the left side),
    Validate.
    To validate:
    Go to the project center and open your project,
    Navigate to the schedule PDP and select your view tasks details)
    Click on "edit" to open the project schedule,
    Publish the project plan and check that your field is there and cannot be edited.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project server 2013 - PWA: My Tasks page is not loading and disabled

    Hi
    i had an issue that suddenly occur for one of my users (just to him).
    My Tasks page is not loading, it shows "Loading" in the middle of the page and stuck that way, and also the Ribbon buttons are disabled.
    Anyone knows what could he had done to make this happen?
    The print screen is in Hebrew but i described what appears.
    Ofir Marco , MCTS P.Z. Projects

    Hi Ofir,
    I've had a similar issue in a previous version of Project Server. A corrupted assignment was causing this in my case. I found the corrupted assignment using the following procedure:
    Retrieve all published assignments & related projects for the user (in the database)
    Open each project one by one in MS Project & set the 'Publish' value to 'No' for the user's assignments and publish the project
    Everytime after publishing a project, retry to open the Tasks page
    At a certain moment your Tasks page should work again and you know now which project/assignment is causing the error, just replace the corrupted assignment by a new one and it should work again
    Hope this helps

  • Project server 2013 PWA - Can't open project in PWA

    When attempting to open a project in PWA the following message is generated:
    An error occurred while opening your project. Give us a few minutes and try again. If this happens again, contact your administrator.
    It happens in all PWA sites.
    In addition you can open and edit the projects using Project Pro without any problem.
    Any suggestions?

    Can you run the below command in SharePoint Management shell:
    set-spprojectpcssettings -maximumworkerscount 260
    Once done restart the Project Services and then check the behavior.
    Cheers! Happy troubleshooting !!! Dinesh S. Rai - MSFT Enterprise Project Management Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can be beneficial to other community members reading
    the thread.

  • Resource time phased data in project server 2013/project 2013

    Hi all,
    I am using project server 2013 .
    one resource availability percentage is set as 80% ie 6.4 hrs per day. But when we are doin task assignment, only 5.6 is taken for a day and rest is pushed to next day ( i have noticed this in the timephased data in the task usage screen).
    for eg. if 6.4 work is assigned to the resources for a task with start date 1/1/2014 and end date 1/1/2014.  5.6hrs is taken for first day and 0.8 hr is moved to next day. Also the duration still shows as 1 eventhough task finish date is changed to 1/2/2014.
    Please help to understand is there any settings where 5.6 is taken for a day though the resource capacity is set as 80% ie, 6.4hrs.
    Thanks, Rose

    Hi Rose,
    is there any chance you have auto leveling turned on?  Menu Resource > Leveling Options > Automatic.

  • Project Server 2013 - User cannot create or see his timesheet

    Hi everyone,
    One of my project server user has a little problem with his timesheet.
    When he try to create a timesheet, he has an error message :
    "Sorry ... We can not create the timesheet, because we have encounter a problem with Project Web App or with the data validations,
    especially resources who are users or work resources invalid. Please check
    your environment and try again."
    Or with timesheet which was create before encounter this error, he has this message :
    "Failed while loading the view. Press OK to reload this view with default parameters. Press Cancel to sélect an other view."
    I'd try to check every project where he is as a resource but I didn't found something wrong.
    Maybe it's because one of the custom field is required but other user have no problem to create and view their own timesheet.
    If you have any idea to help me.
    Thanks,
    Patmol

    Please be sure about the permission required for users. If your users are having permission then Check URl which is talking about your issue which is common in PWA 2013
    http://sharing-the-experience.blogspot.in/2013/10/project-server-2013-timesheetaspx-view.html
    http://blogs.technet.com/b/projectsupport/archive/2013/12/11/project-server-2013-error-loading-views-if-the-default-view-is-missing.aspx
    http://carldalton.tumblr.com/
    Hot fix is talking about issue and having Resolution http://support.microsoft.com/kb/2760261/pt
    Cause of the issue
    Run the Sql
    Profiler 
    The timesheet contained two tasks were the value of ASSN_ACT_WORK was NULL instead of 0.00000.
    This caused the System.InvalidCastException in the ULS log and the user error the view failed to load. 
    Remove this kind of entry then you will not face the issue 
    kirtesh

  • Access Project Server 2013 from personal mobile device

    Dear All,
    This is something great about Project Server 2013 (PWA) where users can view theirs task & other information on their personal mobiles, tabs etc. But i not able to access my company Project Server 2013.
    Is that i am missing something to install or configure PWA 2013 as i am admin for this application?
    Kindly let me know 

    That means your PWA site collection in not published externally so your mobile device can't resolve the DNS. If you connect your mobile device to the same network your Project Server environment is on, it will work as the DNS would resolve. You probably
    want to look at publishing PWA externally if you want to use it on mobile devices. Here are some links for you / your IT department, the process is the same for PWA and any other SharePoint site collection:
    http://www.brightstarr.com/sharepoint-technology-and-application-insights/securely-publishing-sharepoint-externally-using-web-application-proxy
    http://blogs.msdn.com/b/sambetts/archive/2014/04/02/setting-up-a-reverse-proxy-for-sharepoint-with-tmg-server.aspx
    http://www.isaserver.org/articles-tutorials/installation-planning/Planning-SharePoint-Publishing-TMG.html
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Project server 2013 csom save and publish

    Hi,
    In Project server 2013 PWA when you edit project custom fields and save the queue job execute the following jobs: 
    - "Project Update from PSI"
    - "Project Publish Summary"
    - "Reporting (Project Publish Summary)"
    In my code (CSOM)  i can only use : " QueueJob Job = projChechedOut.Publish(true);"
    which is creating all these jobs:
    Project Update from PSI
    Project Publish Notifications
    Project Publish
    Project Checkin
    Prepare Project Web App Permission Synchronization For Projects
    Reporting (Project Publish)
    Project Workflow Check-in
    Synchronize Project Web App Permissions to Project Web App
    Synchronize Project Web App Permissions to Project Site
    Reporting (Project Sync)
    Is there way to "simulate" the save from PWA instead of fully publishing the project using CSOM,  because it is a lighter solution since my code is supposed to only set custom field value (if i only update, not publish it is written to the
    Draft) and secondly performance (less jobs) is better ?
    Thx in advance !!

    Hi,
    as an update to my post:
    - In PSI the method is project.queuepublishsummary(guid jobid, guid projuid)
    http://msdn.microsoft.com/en-us/library/office/gg200290.aspx
    the description says: Publishes the stage summaries of the specified project, in a partial publish operation.
    I am wondering if the equivalent method exists in CSOM. There is this method: PublishedProject.UpdateVisibilityCustomFields() but it seems doing exactly the same thing as publishing a DraftProject.
    Any ideas ?
    Thx

  • Can new PWA views be created whereby a filter can be set and associate to the view by default? (Project Server 2013 ONLINE)

    My main question is: Can new PWA views be created whereby a filter for that view can be set, and associate to the view by default? (Project Server 2013 ONLINE)? and can I have a filter set to filter on person logged on to...
    In previous versions of Project Server, when CREATING a PWA view, we were able to apply/ define a filter for that view.  Does not seem like it is the case in Project Server 2013 Online.  And if I remember, we could also use the URL Guid_view_id. 
    Please confirm; and / or tell me how-to.
    What I was hoping to do is the following... Given that our standard that we have adopted for reporting time is 'My Timesheets' (fyi, Single Mode Entry=ON), we have some resources who have others who do it on their behalf via 'My Tasks' (ie., accomplished
    by using the 'Assignment Owner' field, accordingly).  Therefore, when entering time on someone else's behalf within 'My Tasks', we like to present the user that is logged in only the tasks that they are are assigned to update on others' behlaf.
    I know that there is another more elegant approach to doing this which may be to use the Delegation feature. But since we are trying to stick to Sharepoint Security mode for now, this is not an option for the time being.
    Any help appreciated would be greatly appreciated.
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    1- You still can define in Project Online a filter in the view settings, it is located just above the category setting. Here is a screenshot of the summary project center view:
    2- The view GUID is not anymore in the URL, since the URL triggers an action only on the webpart and not on the whole page. I agree this is annoying since it was great to send a URL with a specific view.
    3- Concerning the access to my timesheet versus my task, I'm not sure to get a full understanding but on a general way, it is much more easy to deal with those situation using categories which you cannot do with the SP permission mode.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • "View failed to load" error when I open Resources - Project Server 2013

    Hello,
    I get the following error when I open the Resources Page (I am using Project Server 2013):
    "The view failed to load. Press OK to reload this view with the default settings. Press Cancel to select another view"
    Help please.

    Hi,
    Is your environment up to date with the latest SP/CU?
    HAve you tried selecting another view?
    See those hotfix : 
    http://support.microsoft.com/kb/2760261/en-us
    http://support.microsoft.com/kb/2863881/en-us
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Assigning resources in Project Server 2013

    Hi,
    Is it possible to assign a resource to a task through PWA in Project Server 2013?
    I have a created a project in PWA, built team,saved and published but can't assign resources.
    Do i need to open Project Professional to assign the resources?
    K.Gokulraj

    Hi José,
    This behavior is normal. See my example below with 1 resource on a fixed duration and effort driven task:
    If I add a second resource, the duration is fixed so it will not change. The task is effort driven so the total effort will be kept at 40h, but splitted between the 2 resources:
    The units will still be 100%, the assignment unit behavior has significantly changed in Project 2010, see references below:
    http://blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx
    http://ntrajkovski.com/2012/11/20/units-and-peak-units-in-ms-project-2010-what-are-they/
    If you insert the peak column in the task usage view, you'll see that the % unit for the 2 assignments are 50%.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2013 - Remove user from resource pool via sync

    Hello everyone,
    has anyone managed to configure their Project Server 2013 box with a resource pool sync that will actually remove user from the resource pool (disable "User can be assigned as resource" or deactivate users) when the user is removed from the AD
    group(s)?
    Setup: Single box, SQL 2012 SP1, SharePoint/Project Server 2013 + PU March + CU April. 2 PWA instances, 1 in SharePoint and 1 in Project permission mode. Tried on 2 different machines (different setup, accounts, domains).
    Proceedings:
    Create AD user U, AD group G. Add U to G.
    Go to PWA, setup resource pool sync with G, sync.
    U is now in the resource pool, has no PWA permissions.
    Remove U from G. Resync resoure pool.
    U is still in resource pool, still a resource, still active, can still be assigned as resource.
    Adding U back to G an repeating the whole spiel with a resource pool and a PWA group sync of G will result in U being added and removed from the user list (as expected), and U being added but not removed from the resource pool.
    Having read
    http://technet.microsoft.com/en-us/library/gg982985.aspx and
    http://technet.microsoft.com/en-us/library/gg750243.aspx, there does not seem to be an omission on my part.
    The first article states:
    Note:
    The corresponding Project Server User Account is not deactivated based on this synchronization. If the same Active Directory user is configured to synchronize with a Project Server security group, the Project Server user account will be inactivated when
    that synchronization occurs. For more information, see
    Best practices to configure Active Directory groups for Enterprise Resource Pool synchronization in Project Server 2013.
    Unfortunately, this deactivation either does not seem to occur even with a PWA group sync or I misunderstood the article.
    So, did anyone manage to setup their resource pool sync in a way, that new resource will be added, but also be removed from the resource pool?
    Kind regards,
    Adrian

    Hi Adrian,
    you tried to sync the same AD group that you used for the resource pool sync also with a Project Server permission group?
    And on removal of the user of the AD group the project user/resource is not deactivated? Only removed from the group
    Regards
    Christoph
    Hi  Christoph,
    even though I might have tried that before, I tried it again in several constellations. It didn't change anything. The the user will be properly added to and removed from the PWA group whenever I remove them from the AD group, the use will also stay active
    (but cannot logon without permissions). However, the user will always remain in the resource pool, i.e. the "User can be assigned as resource." checkbox will remain unless it is cleared manually.
    Having re-read the technet articles, none of the scenarios actually seem to descibe or address the process that I require, or maybe I'm just misunderstanding. Let me just try to outline the core issue:
    Add user to AD group. Sync AD group with resource pool. User is now a PWA resource and PWA user.
    Remove user from AD group, but do not deactivate/delete user from AD.
    (Magic happens!)
    User cannot be assigned as ressource in PWA.
    So, is there anything to make this step 3 happen, or is it just not possible to sync users out of the resource pool anymore unless they are deleted/deactivated in AD?
    Kind regards,
    Adrian

  • Project Server 2013 AD Enterprise Resource Pool Synchronization Exception

    Hello,
    I am looking for assistance from the project server community.
    When I click “Save and Synchronize” on the Active Directory Enterprise Resource Pool Synchronization page nothing happens and the status does not change.
    This is a new instance of PWA and I am preforming this task using the farm admin account. The farm admin account can read AD.
    Error 1:
    w3wp.exe (0x1B98) 
    0x0B8C       Project Server              
    General      aeby7         
    Exception [bucketHash:F08803DE] Exception occured in method 'Admin.ResolveActiveDirectoryGroups' System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.    
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)    
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String searchRoot)    
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()    
    at System.Linq.Buffer`1..ctor(IEnumerable`1 source)    
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)    
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClassf2.<AdminResolveActiveDirectoryGroups>b__f1()    
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace: 
    at Microsoft.Office.Project.Server.Native.dll: (sig=[sig]|2|microsoft.office.project.server.native.pdb, offset=3C1E) at Microsoft.Office.Project.Server.Native.dll: (offset=1254D)                       
    d360539c-6d89-70e7-c077-92da686b0689
    Error 2:
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes: 
    System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.   
     at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)   
     at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String searchRoot)   
     at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()   
     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)   
     at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)   
     at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClassf2.<AdminResolveActiveDirectoryGroups>b__f1()   
     at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName,
    IEnumerable`1 actions)  . Standard Information: PSI Entry Point: 
    Project User: i:0#.w|[DOMAIN\UserID] Correlation Id: f1f1a77f-6b45-e311-9407-00155d2abe21 PWA Site URL: [PWA URL] SA Name: Project Server Service Application PSError: GeneralUnhandledException (42), LogLevelManager Warning-ulsID:0x00101622 has no entities
    explicitly specified.

    Hi,
    I also get the same error when I'm trying to do the synchronization between Enterprise Resource Pool and Active Directory.
    I am in a single domain topology between Project Server 2013 and AD, and I'm doning the synchronization with the farm admin account, who has read/write access to AD.
    Here are the last relevant messages I see:
    w3wp.exe (0x2BE8) 0x1568 Project Server General aeby7 Exception
    [bucketHash:F0FACBDF] Exception occured in method 'Admin.ResolveActiveDirectoryGroups' System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain, String searchPath, String searchFilter)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String encodedClaim)
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()
    at System.Linq.Buffer`1..ctor(IEnumerable`1 source)
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace:
    2b3d83ee10e5|2|, microsoft.office.project.server.native.pdb, offset=3C1E)
    at Microsoft.Office.Project.Server.Native.dll: (offset=1255D)
    w3wp.exe (0x2BE8) 0x1568 Project Server Unified Logging Service c91s Monitorable
    Watson bucket parameters: Microsoft Project Server 2013, ULSException14, 070f6ea0 "project server",  0f001181 "15.0.4481.0", 6962a0f6 "microsoft.office.project.server.administration", 0f0011ad "15.0.4525.0", 51ade0c4 "tue jun 04 14:42:44 2013",  0000020f
    "0000020f",  0000003b "0000003b",  0560164b "keynotfoundexception", 00101621 "aeby7"
     w3wp.exe (0x2BE8) 0x1568 Project Server General aeby8 Medium
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes:  System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain,  String searchPath, String searchFilter)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String encodedClaim)
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions)  . Standard Information: PSI Entry Point:  Project User: LUXAIRLG\SQLADMIN2012
    Correlation Id: 6cef3814-b3a2-e311-93f9-005056921080 PWA Site URL: xxx SA Name: PS2013 - Project Server Service Application PSError: GeneralUnhandledException (42). LogLevelManager Warning-ulsID:0x00101622 has no entities explicitly specified.
    w3wp.exe (0x2BE8) 0x1568 Project Server Project Web App af04k Medium
    Void SaveButtonClick(System.Object.System.Web.UI.WebControls.CommandEventArgs) : GeneralUnhandledException
    Any ideas?
    Thanks in advance

Maybe you are looking for

  • New imac as external monitor for macbook pro?

    I have a 2011 macbook pro that I use for work. I am thinking about buying the new imac for use at home. The question is can I use the imac as an external screen for my mbp? Or do I have to have another external monitor to use for that?

  • MUSE CC WON'T DISPLAY BEBAS NEUE WEB FONT IN DESIGN MODE

    For some reason I can't seem to view the Bebas Neue web font in design mode any more, yet when I switch to preview or even go ahead and publish my site it works just fine. It wasn't bothering me too much at first but it really confuses things after a

  • Captivate 5 won't launch after install

    I've just installed captivate 5  on a Windows XP sp3 (fully patched) (previously the computer had adobe elearning suite installed) but I can't launch captivate 5.  each time I launch I get he captivate splash screen,  and I can see that it's load ing

  • Popup message in the middle of a method

    Hi, In method A exists method B which is used to popup a message window but the message didn't show until the end of method A. The message window should be displayed only after the process of part of method A not at the end of method A. Best regards,

  • I need some suggestions.....

    I have a reporting requirement with ODS but that ODS is not available for Bex reporting Can i change the ods settings (like enadle the available for  Bex reporting option) in production server. if i cange that setting next what can i do? can u please