Project Server 2013 timesheets not showing up for approval

We're using Project Server 2013 and entering timesheets. I'm a team manager who is set up as the timesheet approver for a few people, including Nicole.
Nicole opens her timesheet and fills it in for the week.  She applies time to four Administrative tasks and two project tasks.
Nicole submits her final timesheet for approval.  (We have also tried having her save it first, then to the final submission, with the same results.)
I go to my approval screen and see the four Administrative tasks listed as separate lines.  I do not see the project tasks.
I select the four Administrative tasks and approve them.  They disappear when the screen is submitted.
In previous weeks, and with some other employees, I would immediately see a single line item that said "My Timesheet" for Nicole which I could then approve.  But recently this stopped, and I do not see her timesheet.
If Nicole checks the status of the timesheet it says it's submitted to me.
On my Approval page if I go to History, Timesheets this timesheet is not listed under "approved by me" nor is it under "my resources unsubmitted timesheets."  It's in limbo.
The only fix is for Nicole to recall the timesheet and resubmit it.  Then it shows up on my Approval page.
Any suggestions?
-- Paul

We resolved this. The solution was as follows:
Go to PWA Settings, and under Security choose Manage Groups.
Click the Team Members group.
Scroll to the Categories section, and in the Selected Categories area highlight (select)
My Tasks.
Click the box to allow the permission called Adjust Timesheet which is under the grouping for Resource.
Now don't ask me how or why that works.  It's not a setting that intuitively matches what's going on.  But it fixed it for us.
By the way, we had a number of other timesheet issues (view failures, etc.) that were all cleared up when we installed the April 2014 Cumulative Update for Project Server 2013, as well as SharePoint 2013 SP1.  I highly recommend both.
-- Paul
Paul LoSacco, Web Presence Team, Omnicare

Similar Messages

  • Project Server 2010 Timesheets not Updating Project Plans

    We have several project plans that are not getting updates from approved timesheets.
    Troubleshooting steps I've taken:
    1) Verified the timesheet/task submissions by the resources
    2) Verified they have been approved
    3) Verified they have been accepted by the Status Manager and processed
    4) All project plans have been published (I even used ProjTool ON the App server to do a full publish of all plans as a second step of publishing)
    5) Verified OLAP was built successfully overnight (and every night)
    6) Tasks have both remaining work and NO actual work in the Resource Usage view
    7) Had a user recall and resubmit his timesheet using "Send Timesheet" to see if the task updates would come through - they did not (I am Status Manager and the timesheet shows Approved), and even published the plan and rebuilt the OLAP again,
    just in case.
    8) Verified that no tasks are marked for closure under Close Tasks for Update in Server Settings.
    9) Verified Timesheet shows Actual Work on the Tasks via Pivot Table; compared Timesheet_User_View with MSP_Portfolio_View pivot table for project which shows 0 hours. Timesheet_User_View shows 33 hours.
    All tasks have Remaining Work, are within the date range of the timesheet and are open for submitting time. Timesheets are still out of sync with project plans for many users and there is no apparent reason. I'm out of ideas!

    Hi,
    In status manager's approval center, history, status updates, can you check the status of the approval? Do you have any errors in the ULs log for the approval or publish jobs?
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Workflow in Project server 2013 online not going particular stage after Approval

    Hi All,
    i have created workflow using sharepoint designer 2013 for project server 2013 online. and i have also set the approver after the first stage. when i create a project using this workflow, project is created successfully and the approval task also go for
    a approval to specific user. and i have set the property that after approval it has to go on specific stage. but the problem is when user approve the task it shows approved but my stage in workflow is remain same. it is not going to any stage. 
    i don't know why this type of problem is occur. 
    FYI, i have created same workflow for Project server 2013 on premise(Which is installed in my server) and
    it is working fine but when i want to deploy this workflow in
    project server 2013 online its giving error.
    so please help me to solve this type of issue.
    Thanks

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

  • Error using Line Classifications in Project Server 2013 Timesheets

    Background:
    I'm working on a Project Server 2013 environment that is using Timesheet Line Classifications. In our environment we are not utilizing the Standard Classification but, we are instead using Billable Onsite, Billable Offsite and Nonbillable.
    Issue:
    If I have created a timesheet, then I am assigned an additional task and try to add the task to my timesheet using a Line Classification other than standard, I get an error pop-up. As long as I add the Standard line classification first, everything
    works fine. If I delete and recreate the timesheet it prepopulates the standard tasks which also resolves the issue.
    Questions:
    1.) Has anyone else ran across this issue and have a fix?  
    2.) Is anyone aware of a product fix in a CU or Hotfix to resolve this issue?
    Thanks,
    Dustin

    Dustin - as I understand it Timesheet Line Classifications allow you to
    "Duplicate" Timesheet lines for business purposes or accounting reasons. When I first saw this explanation I was at a loss as to the benefit or purpose of this feature, fortunately I work with some smart customers and they soon opened my eyes to the
    potential of this feature.
    The operative word in the description is "Duplicate". Additional Timesheet line classifications are available but
    not in lieu of the Standard Line Classification. As you have experienced if the "Standard" line is added to a Timesheet then an associated Duplicate Line Classification for the same task can be
    added to the Timesheet.
    To realise your requirement you might just decide what type of work is it you do that is most prevalent and regard that as being "Standard" and then use other line classifications to identify other Billable time - Non Billable Time reporting in a Timesheet
    is available by default if it is enabled in Timesheet Settings and Defaults.
    As an alternative do your Timesheet compilers decide the classification of the work they are booking time to?
    You could consider Task Custom Fields using a lookup table to denote whether work is on-site or off-site with the Calculation for Assignment Rows option set to "Rolldown unless manually specified" - this will associate the task field value with the associated
    Assignment. Using Task level fields set by whoever creates the project plan would remove the responsibility for differentiating the work "type" for your Timesheet users.
    The querying and reporting of the different classifications of work as recorded in Timesheets would then be possible by virtue of the task field.
    Dominic Moss | MAPM Microsoft Certified Technology Specialist | Our Newsletter:
    PM News Project Server Specialists
    Project Server PRIME | Twitter:
    @Twitter | Facebook:
    @Facebook | Linkedin:
    Wellingtone

  • PowerView In Project Server 2013 is not working

    Hi All,
    I am working on environment with Project Server 2013. In report part i am not able to see or view only power view reports.
    I am testing this with default report provided by Microsoft, where other reports (power pivot) are working fine.
    My power view report is not showing any error, it is simply gets opened as blank sheet.
    Quick replies and help will be appreciated. 
    Note: I have installed silver light latest version too.
    Thanks
    Abbas 

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

  • Task Updates By Team Members In Project Server 2013 but not reflects in MSP 100% completed

    Hi,
    My problem is related to Project Server & Project Professional 2013
    My scenario is like that Project Manager publish the project plan, and respective team member get their task. And Team Member is updated the task,then send to  the Project Manager for approval. Project Manager is approved the task. But, while opening my
    project in MSP 2013, it is not synced means, in msp it is not showing task 100% completed.
    Please solve this problem, I am waiting for your response.
    Thanks
    Saikat 
    Consultant

    Hi Guillaume,
    I have tried your procedure, but not get any solution.
    Yes, two errors are showing while opening in MSP like:
    1) The following job type failed to complete, Job Type -Load. Could not load project. Please try after sometime.
    <detail><ServerExecutionFault xmlns="http://Microsoft.Office.Project.Interfaces/" xmlns:i="http://www.w3.org/2001/XMLSchema-instance"><Actor i:nil="true"/><LastError>1032</LastError><Message/><Source/><StackTrace/><TargetSite
    i:nil="true"/><ExceptionDetails><errinfo xmlns=""><general><class name="ProjectHasWriteLock"><error id="1030" name="ProjectHasWriteLock" uid="c9095c9e-cfbc-e411-940a-000c299e9fb7"/></class><class
    name="ProjectHasNoReadLock"><error id="1032" name="ProjectHasNoReadLock" uid="ca095c9e-cfbc-e411-940a-000c299e9fb7"/></class></general></errinfo></ExceptionDetails></ServerExecutionFault></detail>
    2) Second error are showing in Queue like "Skipped for Optimization" and "Failed But Not Blocking Corelation"
    Please give me the ultimate solution to solve this.
    Thanks and Regards
    Saikat
    Consultant.

  • Discussion About The Use Of Project Server 2013 Timesheet Custom Billing Categories (Post SP1 and April 2014 CU Install)

    In support of a consulting company using timesheet custom billing categories to designate project time as billable onsite, billable offsite, and non-billable, I've encountered a series of issues which appear to be associated with the custom billing category
    timesheet lines.  These issues cause timesheet users to get frustrated, and contribute to misalignment between project actuals and timesheet actuals.  We're in Single Entry Mode, no pre-population, SP1 and April 2014 CU Installed.
    I'll enumerate the issues here and pose the question to the community as to whether others are experiencing any/all of these things, and if so,  ask if any workarounds have been discovered.  We're working with Microsoft to validate these independently,
    but I am posing the questions to the community to gather additional information, and hopefully save some folks time in troubleshooting similar issues.
    1.When time is entered on an assignment into timesheet lines of multiple billing categories, only time entered since the last save is getting saved and ultimately sent, on timesheet submit, to the approval center.  Although the previously entered and
    saved time appears in the application interface when the timesheet is re-opened, only data since last save is actually saving to the server or processing through the approval center.  We believe this is the primary cause for timesheet and project actuals
    being out of alignment.
    2."_ Error Loading".  When assignments are added, deleted, or changed after a timesheet has been created, standard timesheet lines are added, deleted or changed (i.e. synchronize) with the assignments. However, for custom billing category
    timesheet lines, they do not change when the assignments change, and they aren’t removed if the assignment is removed.  We believe this causes secondary errors, like the "_Error Loading"  (and others as will be described below).
    3.When a timesheet with time in a non-standard billing category is deleted and recreated, time is arbitrarily moved to standard timesheet lines for the same assignment. If the task assignment is subsequently removed, the timesheet line causes the timesheet
    to break.
    4."Error Communicating with Server". When trying to submit a timesheet, a pop-up box appears indicating that there is an error communicating with the server.  This error appears because a timesheet line is no longer associated with a project.
    In order to submit the timesheet the orphaned timesheet line must be identified and manually removed. One technique we found which helps to identify an orphaned timesheet line is to select a task and submit task progress. Repeat for all timesheet lines until
    you get an error.  The timesheet line(s) with the error can be manually removed from the timesheet, fixing the error.
    5. Unable to Open Specific Timesheets without Error. There are certain scenarios when the "Remove Task" feature is used or an assignment is otherwise removed after creation of a timesheet with custom billing category lines, which causes orphaned
    timesheet lines. These orphaned lines can cause issues when trying to open a timesheet. The issue can appear when timesheets are in progress in multiple periods. In the problematic scenario, time is entered and submitted in one period and subsequently
    the task is 'removed' from another period before the PM processes the first approval request. Process governance can certainly help here, but improvement in the way synchronization occurs between project assignments and custom billing category timesheet lines
    would be great. The error can often be resolved by re-adding the assignment for the problematic timesheet user to the project (which creates a new assignment), and then allows you to open the timesheet.  Then time can be moved from the old timesheet
    line to the new timesheet line, and the old one can be removed.
    In 4 and 5, sometimes we can't open a timesheet without error, and other times we can open it but not submit it. We are not 100% clear on all the different causes for each. Each of these issues are suspected to be contributing the the misalignment of
    data between project actuals and timesheets, which can be a real problem for external projects for which time collected through timesheets are being used to generate invoices.
    Although these may seem like separate issues, warranting separate questions, I decided to post them together because they all seem to be related to synchronization of project assignments and timesheet lines for custom billing categories.
    Any thoughts or suggestions from the community would be appreciated.
    Best regards,
    Justin
    Justin Naughton

    There are many causes for each of the errors mention.  It would be best to put one issue to the forum at a time.  For example, some of these issues occur then tasks are deleted from projects but a timesheet has been submitted.   Depending
    on the scenario, some of these issues have been fixed with the latest service pack.
    Other issues are due to bad scheduling habits with the project managers and so first determining what they have done can help resolve some the issues.
    _error Loading, is because something is NULL in the data and the jave is choking when it build the form. Again, these may be because of delete tasks, resources, projects  or someone doing copying and pasting of rows.
    cheers!
    PS.  Train your PM to not COPY and PASTE rows in project schedules.  It can be done, but it can create problems.  There are over 500 fields and some have unique data and the copy paste creates havic.
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Exchange Server 2013 Database not showing in ECP after removal of Exchange Server 2010

    I recently complete the migration of my Exchange 2010 server to Exchange 2013. I then proceeded to uninstall the 2010 server using setup.com /m:uninstall. At the end of the process I received an error that it did not complete the uninstall.
    I checked the server and Exchanged 2010 was removed. When I checked ECP on 2013 it still showed the old 2010 server listed. I used ADSI edit and manually removed the old sever.
    Now when I log into 2013 ECP I only see the one serve but when I go into databases, none are listed. I check under the server itself and it shows the database that it is using but it is not listed under the database tab.
    If I do a search under the database tab I can find it and adds it to the list. I can then open and view details.
    My issue is, after I log out and then back in, I have to run the search to find the database again. In ideas on how to have it show up in the list like it did  before I removed the 2010 Exchange server?
    Thank you,

    Hi,
    From your description, I recommend you verify the following things for troubleshooting:
    1. Please make sure that AD replication is completely by checking the user object's homeMDB attribute. This value should contain the DN value of the Exchange Server 2013 mailbox database.
    2. Wait 30 minutes for the cache on the Exchange Server 2013 Client Access Server to clear or restart the MSExchangeOWAAppPool on the Exchange Server 2013 Client Access Server.
    For more information, here is a kb for your reference.
    Exchange 2013 Redirects to Exchange 2010 for OWA and ECP
    http://support.microsoft.com/kb/2931385
    Hope it helps.
    Best regards,
    Amy Wang
    TechNet Community Support

  • Project Server 2013: Timesheet Managers are able to view and edit all resources' timesheets

    Regarding the Timesheet Managers list, per this
    Office Blog post: "This feature is designed to support scenarios where the regular timesheet approver may be out of the office or any other scenario where a user must submit their timesheet to a different approver each period." 
    In Project 2013, a resource must be added to the Timesheet Managers list in order to be able to approve timesheets.  With that, is there a way to restrict the resources in the Timesheet Managers list from viewing and editing timesheets where they are
    not the resource's designated timesheet approver?

    Hi,
    As far as I know, the users that are in the timesheet manager list will not see all the timesheets but only the ones they have been designated as approvers. Did you experienced a different behavior? Can you detail it?
    Here is an excellent
    blog post which explains in detail how does this feature works.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Plan/Schedule for Project Pro and Project Server 2013 Install

    Looking for a project plan/schedule for a dept. wide install of Project Pro and Project Server 2013. Anyone have one to share?

    In Project Professional 2013 there are two templates:
    Install Project Server 2013 and Upgrade to Project Server 2013.  You may search for either template.
    Here is a direct link:
    http://office.microsoft.com/en-us/templates/results.aspx?qu=project&av=zpj150&queryid=312801ca-a859-48dd-af56-714e81c97cf4#ai:TC103345703|

  • Issue while installing Ms Project Server 2013 on MS Server 2012 R2 with Sharepoint Server 2013

    Hello MS Support Team,
    I installed SQL server 2012 & Sharepoint server 2013 and after that the MS project Server 2013 is not installing on the same server -- pls hv a look the enclosed screenshot. sent at [email protected] and guide me to resolve it on priority.
    A windows poped up - Installation Error - This Project requires MS Sharepont Enterprise edition... (Which is not available on the MSDN Server)..only standard edition available.
    Please reply asap @ [email protected] - Call @ 0120471384
    Kind Regards,
    Vinay Bhardwaj
    Network System Administrator - GREC (IN)
    Rockwell Automation | A-66, Sector 64 | Noida | India
    LISTEN. THINK. SOLVE
    IP : 71384 | E : [email protected] | W : www.rockwellautomation.com

    Hi Siriosus,
    Indeed you do need Sharepoint Server 2013
    Enterprise for Project Server 2013.
    See article below where it is mentionned:
    Project Server 2013 requires the Enterprise edition of SharePoint Server 2013. Prior versions of SharePoint Server and SharePoint Foundation 2013 are not supported.
    http://technet.microsoft.com/en-us/library/ee662114(v=office.15).aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Steps to take in case of any emergency... Project Server 2013 backup and restore

    Hi There !
    We have a Project Server 2013 environment which is scheduled for daily backup on a recovery server. Just wanted to know what will be steps  that we should follow if we were to face a situation in which production is down and we have to look to recovery
    server.
    Your help is much appreciated !
    Thanks

    This will do the Project Sever 2013 rollover -
    https://pwmather.wordpress.com/2013/05/02/projectserver-2013-environment-migration-rollover-steps-powershell-ps2013-msproject-sp2013/
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS |
    MVP | Downloads

  • Resource filter is not working on 'Timesheet Adjustment' page. in project server 2013

    Environment : Project Server 2013
    In Time-sheet approval page, Time sheet manager unable to filter the resource time-sheet.
    In time-sheet adjustment page time-sheet manager unable to filter the data as per resource.
    Please help to resolve the issue.

    Hi,
    As far as I know, this feature which exists since at least PS2007 was never reported as "buggy". Thus I think it is an issue due to which user filters on which timesheets, meaning a visibility setting. It is really hard to debug for you since I
    do not know exactly the steps you went through and your configuration. I would start by testing simple scenarios in a dev environment using delegation sessions to check from the timesheet manager point of view what he can see. It is also important to check
    the timesheet status.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Send email is not working in share point desinger 2013 for project server 2013 workflow

    Hi,
      How to configure email for project server 2013. i have created workflow where i am sending email. It is not sending it.
     i have set outgoing mail setting. Tasks are created in my workflow but mail is not sending.
    Thank you for helping us.
    Thank You
    Vinay

    Hi,
      How to configure email for project server 2013. i have created workflow where i am sending email. It is not sending it.
     i have set outgoing mail setting. Tasks are created in my workflow but mail is not sending.
    Thank you for helping us.
    Thank You
    Vinay

  • How to get timesheet information in a javascript (Project Server 2013)

    Hi all,
    In Project Server 2013, I'm trying to customize the Timesheet ribbon. This far, I've been able to add a new button and tie an event to it. All is working well. This is all done using elements.xml and a javascripts.
    Now the problem is that I want to get some informations about the timesheet (the Guid for example) and, for now, I've got no success. I know that there is an object called PS.TimeSheet, but when I try to use some PS.TimeSheet's methods I get an error.
    Note that i'm in the page http://servername/pwa/timesheet.aspx (there is not Guid in the address) and all the treatments should be done in the javascript (no call to another aspx page)
    Thanks !

    Finally, I've found the solution.
    My goal was to add a button in the timesheet ribbon to launch a special report showing some data about the timesheet. The report has the timesheet Guid as parameter.
    To customize the Sharepoint ribbon, you have to do it via an xml file and a javascript (a lot of explanation is available in the internet that explains how to do it). So I had to call a function in the javascript to launch the report (which is a SSRS report).
    When you are in a javascript you have access to many global variables. When the timesheet.aspx is displayed, there is a global variable called "timesheetComponent".
    Using this variable we can call the method :
    timesheetComponent.m_consumedApi.get_Impl()
    to get an implementation of the current timesheet. This implementation has an attibute that has a lot of nice stuff about the current user and the current time sheet. This attribute is 
    _headerInfo
    _headerInfo is a structure that includes tsUid which contains the timesheet Guid I was looking for.
    Finally, the function attached to the button goes like this :
    function _LaunchReport() {
    var tsUId;
    var rptPath;
    var tsImpl = timesheetComponent.m_consumedApi.get_Impl();
    try
    if (CONST_REPORT_PATH == null || CONST_REPORT_PATH == "" ) {
    alert("Constant CONST_REPORT_PATH is not defined")
    else {
    tsUId = tsImpl._headerInfo.tsUid;
    rptPath = CONST_REPORT_PATH + 'TimesheetDetails&rs:Command=Render&rc:Parameters=false&TimesheetUID=' + tsUId;
    window.open(rptPath);
    catch (Err) {
    alert(Err)
    CONST_REPORT_PATH is the path to SSRS defined elsewhere
    I hope this will help some other poeple !

Maybe you are looking for

  • Apple 20-inch with a 12-inch Powerbook = Constant Fan

    Just picked up a 20-inch display for use with a 12-inch Powerbook.. I also have an Apple Bluetooth Keyboard and Mouse that I use.. The fan runs constantly when the powerbook is connected to the Apple Display.. Can anyone confirm if this is normal or

  • Alv Grid method get_grid_modified

    Hi, Method get_grid_modified is returning true after  making  any changes in Grid. Please help me to make it working. Regards, Venkat

  • Install CF8.01 on Windows Server 2008 64bits

    Hello, I have a new machine whith Windows server 2008 x64 and i installed on it CF8.01. For installing, no problems and the service work fine. But, when i launch one page on the web server, a .cfm or a classic html the IIS 7 return a error 500.21 : H

  • IPhoto '11- Cannot Export using "File Export"

    I just upgraded from iPhoto '09 to iPhoto '11. I imported photos off my iPod touch and edited them. After editing them however, I can't export them to anywhere on my computer. Even before editing I cannot export them. I've tried: -Creating a folder m

  • Random wifi problems on macbook pro

    Hi, I have a macbook pro currently running snow leopard 10.6.4. Most of the time I am able to establish a good fast connection through my wireless network but at least once a day it stops working and I cannot connect. Resetting the router sometimes h