Project stock against a particular WBS element

How can i get the opening & closing stock value (not quantity) of project stock against a particular WBS element?
Regards,
Indranil

Hi,
Hiu2026
Im adding to above replies.
Prerequisites
You can only set the Closed status after Released status.
If u want to close the project/wbsu2026plz follow
Technically completed (TECO)
We can use this status for WBS elements that are completed from a technical point of view, but where you still expect costs to accrue.
Cj20nu2026Editu2026..Statusu2026.Complete technicallyu2026..set./undo(revoke)
Closed (CLSD)
We can use this status for a work breakdown structure or WBS element that has been completed from both a logistic and an accounting point of view.
Cj20nu2026.Editu2026..Statusu2026.Closeu2026..set./undo(revoke)
Both status can revoke.
Refer this link
http://help.sap.com/saphelp_erp60_sp/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm
pherasath

Similar Messages

  • Project stock linked to 2 WBS elements

    Dear experts,
    We are doing the implementation of SAP into a telco company and we have got the following issue for purchases of networks links. The special thing about network links is that refer to materials that have to be build into two locations, and therefore, from a controlling point of view, each location has to be tracked separately (there are separate project stocks and the
    materials end up in different fixed assets) However, they are purchased as a single unit. The key question is: how do you specify an accounting object for this single item?
    In SAP, links would be assigned a (single) WBS element, which is essentially a cost collector for one specific location, it cannot be used for two locations. Furthermore, using multiple account assignment doesnu2019t work either because it is not compatible with accounting category Q.
    Any idea how can we solve this issue?
    Thank you very much for your help,
    Luis

    There are two options to cater to your requirement:-
    First,Do the Project wise procurement by running an MRP for each WBS element and for each WBS element you can have network assigned which has the Material attached as componenet for that particular network and than procurement element can be created automatically by MRP .
    Secondly if you still want to adopt the multiple account assignment than follow as described below:
    You can have multiple account assignment category configured for Account assignment Cat. Q  by changing the ID:Account  Assignment Screen from 1 TO 2(Multiple account assignment.
    This configuration change has to be done SPRO >Purchasing >Account Assignment> Mantain Account  Assignment Catgory and here select Q account assignment catgeory and make relevant changes as explained above.

  • Travel Expenses settlements against Service Order/WBS Element/Project Ord

    Hi Experts,
    I have one req. in Travel Expenses, i.e. need to settle travel expneses against Service Order/WBS Element/Project Order.
    Can you guide me how to do this req.
    Thanks & Regards
    Rajesh

    Hye mate,
    This is possible for sure what you need to do is to go at travel request . In travel Request there is an option of Enhanced Travel cost/ Alternative master cost center. if you click on it . you would find an option of cost assignmnet click on it
    there you would have option , like an excel sheet like fields of  the cost centre, wbs element, profit center, order number what eve is requred and save it.
    now the cot of trip would go that particulat cost center or der numbe or WBS rather then the cost center assigned at master data in ifototype 0027.
    Regards
    Waqas Anwar

  • T Code for Project Stock for a particular period

    I want to check my project stock for a particular period, is there any Standard T Code, if not how to find the solution. Please revert me the solution.
                                                                                    Thank you.

    Hi
    Please check the following Report
    S_P00_07000140 - Inventory and Raw Material for Special Stock Report
    To access the report, from the SAP Easy Access menu, choose Accounting >> Financial Accounting >> General Ledger >> Reporting >> Tax Reports >> Thailand >> Inventory and Raw Material for Special Stock Report
    OR
    please try to create a Query by using the following tables..
    MSPR
    MARA
    MAKT
    Tnx.
    Abdul

  • How to Get project definition and description  by WBS element

    Hi All,
    Is there any way to get  project definition and description  by providing WBS element.
    Please help .
    Salman Zahir

    Hi,
    These r the tables
    PRHI Work Breakdown Structure, Edges (Hierarchy Pointer)
    PROJ Project definition
    PRPS WBS (Work Breakdown Structure) Element Master Data
    RPSCO Project info database: Costs, revenues, finances
    MSPR Project stock
    Thanks,
    Anitha

  • How to find for a particular WBS element thourgh which budget has consumed

    Hi ,
           I have a WBS element C-09864/001/002. In CJ33  system is showing Budget amount 90,000 and distrbuted 90000. So total budget has consumed. Now if i want to know how the budget has consumed ,means in what ways it has consumed like PR or POs and what are those  PR& PO doucment numbers.
    Apart from PR & PO s directly by posting FI documet also , is there chance for consuming budget .If yes how to find ?
    Thanks & regds
    ramachadra

    Apart from PR & PO s directly by posting FI documet also , is there chance for consuming budget .If yes how to find ?
    -> transaction MIRO, CJ88, KO88
    You can use the steps I have provided to check this.
    Regards, Gordon

  • Reserve stock against one particular sales order and issue the same

    Hi,
    My client wants that he should he able to reservestock for a particular sales order only, so that during availability check, the stock is not issued against any other sales order.
    I have tried to do stock reservation by using t-code MB21, then the stock gets transferred from Unrestricted stock to restricted stock.
    When i Do the PGI, it is still reducing the unrestricted stock and the reserved stock is unaltered.
    My client is not a manufacturing unit, they are basically into only trading of goods.
    Can some one please suggest what steps can i do?
    Also if tehre is any alternative to accomplish the same?
    You can mail me any documnettaion regarding the same, is any on       [email protected]
    Thanks'
    Priyanka

    see when ur changing the stock from restricted use to unrestricted use then
    its fine but as u mentioned while doing particular moment type you want the stock to get reduced from restricted use but not from unrestricted use
    for this u need to change the moment type from 651 to some thing else because the moment type 651 will reduce the stock from restricted use and allocate to the customer
    so maintain a diff moment type for ur particular order type ( means this particular order type has an itme cat which detrmines a schedule line cat in thth schedule line cat maintain a diff omnt type instead of 601)
    well try 231

  • Moving Average Price does not get updated for Project Stock

    Hello Experts
    We have an Engineer-to-Order implementation for our client. Accordingly procurement is done per project. Each Project issues its PRs which are then converted to POs and recieved into Project Stock.
    While assigning the material to the Network activity in Project (using material component) the system uses the price found in the material master (MAP or STD) as a planned cost appended to the project.
    Problem:
    while procuring the material, when we receive it into Project Stock (Mvt 101 Q + ) the Moving Average Price in the material master does not get updated. this way all newly created material master will never have a moving average price, thus whenever we try to assign them to the project we receive an error message (Cost for Material Component ###Mat.Num### cannot be determined.
    Question:
    How can I get the system to update moving average price (for all types of stock) based on procurement for project stock.???
    Your help is kindly appreciated.

    I'm sorry for the confusion
    Case:
    The T-code is CJ20N Project Builder in PS module
    we are assigning material components to network activities under a certain WBS element in the project.
    there is a function in the Project Builder to calculate the cost of a network. it uses the costing variant assigned to the network which is PS02 (We get the error here)
    The costing variant has a valuation variant which lists a series of strategies  to get the material price. Planned 1 if not then STD if not then MAP. (you can choose between many options via a drop down menu) you can choose 5 consequent options.
    The MAP that the valuation variant is coded to get is the Plant Stock MAP -- Or the Project Stock MAP but only Per WBS element.
    The MAP that the Actual postings update is the Project Stock MAP only Per WBS element.
    This means that if you use a material component to purchase material 123 Acc.As. Q for WBS X for 10 $ then you try to assign a new material component with the same material 123 to WBS Y, the system will not get a MAP. because it's stored in QBEW per WBS element.
    This way the system will never get the MAP right.
    However, we don't always use project stock to procure for projects, for some requirements we can assign and use plant stock as well for Projects. that way we need the MAP from plant stock.
    In the Valuation Variant you can use a User Exit Strategy. The user exit's name is COPCP005
    My Suggestion is:
    Use the User Exit COPCP005 to calculate the { Total value / the total quantity (MAP) from QBEW + Total value / total quantity (MAP) from MBEW } / 2
    which is the MAP for both plant and project stock together, since that we are going to use both.
    Q: Is this correct !?

  • 1 project definition with several wbs elements or several project definitin

    Hello
    I need projects as account assignment elements in CO (when entering vendor invoices for costs). Should I have 1 project definition with all projects /wbs elements underneath, or should I have 1 project definition uniquely defined for each project/wbs element? Some projects are not settled to assets und construction, some projects are settled to assets und construction.
    kind regards
    Arjan

    Arjan
    I don't think you can have Projects as account assignment objects. You can have WBS element as account assignment object.
    One alternative I can suggest, if you want to see project costs at higher level instead of breaking down the project into many WBS elements. Create a project with one WBS element only and use that WBS element as account assignment object.
    It is only possible to have a project with one or more WBS elements. I don't think you can define projects within projects.
    letus put it this way assume WBS elements are projects within a project. But make sure all the WBS elements are related to one project
    Hope you are clear now.
    Thanks
    Prasad

  • Adding WBS element to level-2 in existing project

    Hi all,
    I have a new WBS Element created in a project which already has 2 wbs elements created in a level 2 hierarchy before . Now , this new element is created at level-1 by default .I want to modify the project hierarchy adding the newly created element in a level 2 . I'm trying to do this using BAPI_PROJECT_MAINTAIN but the function returns to me an error:
    hierarchy is not consistent Termination: Too many errors (more than 10% of methods) Data cannot be saved
    Please suggest .
    Thanks
    Deepika

    Hi Deepika..
       Check ur BAPI , I think u missed any Impot  and Export Parameter. In BAPI if u  missed anythink also it wont work..
       Share ur error , So i can  tel u the problem..
       CALL FUNCTION 'BAPI_PROJECT_MAINTAIN'
    EXPORTING
    i_project_definition = gs_project_definition
    i_project_definition_upd = gs_project_definition_upd
    IMPORTING
    return = gt_return
    TABLES
    i_method_project = gt_method_project
    i_wbs_element_table_update = gt_wbs_element_table_update
    i_wbs_element_table = gt_wbs_element_table
    i_wbs_hierarchie_table = gt_wbs_hierarchie_table
    e_message_table = gt_message_table.
    Regrads
    Prabu K

  • (ABAP-FI)How to get project definition from agiven WBS element

    Hi,
    I have to update some columns of PRPS table relating to a WBS element.
    While using  BAPI_BUS2054_CHANGE_MULTI it wants project definition to be passed as an input parameter.
    Is there any means to know project definition for  a given WBS element of PRPS table.
    Thanks in advance.
    Regards,
    Sourya Prakash.

    Hi,
    why don't you display table PRPS in SE11 to see what fields you have there? It's not that hard to see that there is a field PRPS-PSPHI with description "Current number of the appropriate project". Yes, there is a link from WBS element to project definition.
    Cheers

  • Project WBS element cost allocation

    Dear All,
    In a project we have created 10 WBS elements out of which one is used for common expenses and rest other or individual works carried out in the project. Now i want to allocate the Common cost of one WBS element to other nine WBS elements.
    Can anybody explain how this can be done and is there any possibilites of costing gets doubled in the project if the cost transffered to other WBS elements.
    Thanks and regards

    Thanks for the reply,
    I have another query also, i had transferred the WBS element cost to other WBS element cost in the same Project.Whether it will double the Revenue or Cost incurred
    For ex, WBS Element A got 100 and i had settled to WBS Elements B and C , now B and C got 50 50 each
    now my project will have
    a) WBS Elements A-100, B-50 and C-50   or
    b) WBS Elements A-0, B-50 and C-50 ,  for my understanding option (b) will be right. Your views pls
    Edited by: aspirefico on Apr 30, 2009 12:59 PM

  • Return to vendor from Blocked Project stock - Line rejection

    hi
    I have a problem in doing line rejection for return delivery from a blocked project stock.
    we had modified F5 notification for Project related senario to FQ and using the same for doing line rejection return delivery directly from project stock with the help of action box.
    While the include is accessing MSPR table for picking up the project stock.
    the steps involved are as below.
    1. create FQ notification (Similar to F5) by giving inputs as Material to be rejected,Plant, Defect code from existing code group and assign the purchase order.
    2. Tranfer the project stock to blocked projection stock ie.rejection stores using 344 movement type. while doing this 344 we give input of WBS element, storage location and Batch.Stocks against this WBS are picked from MSPR table and trasnferd to rejection stores.
    3.After this while doing return to vendor we give the reason code and post 122 document.
    the problem is if the material is having two WBS elements it and both have stock in rejection stores this follow up action is unable to pick the Exact stock for which the WBS element is assigned to notification while 344 movement.
    please suggest me as how the WBS element can be retrived from a notification which was used for earlier actions in action BOX.
    regards
    NVB

    Hi
    If u want to return the material to the vendor. In MIGO itself select return delivery against the material document with movement type 122 u can send it.
    This is irrespective of material lying in quality or blocked. From quality or from blocked status u can send the material back to vendor.
    No need for quality to Un restricted or Blocked to Un restricted.
    Regards,
    Raman

  • Report to show breakdown of a particular WBS number

    Hi SAP Experts,
    Is there any report in SAP that I could see a breakdown of costs posted against a particular WBS number.
    So in other words, I have a WBS number refering to a project and I want to run a report to show me what invoices have been posted to this WBS.
    This report could be in SAP or BW.
    Many thanks
    Alex

    Hi,
    Please check S_ALR_87013532 to 87013541

  • Assign Multiple equipments to WBS element

    Hi all,
    Can anybody tell me how to assign mutilple equipment to single WBS elements. As far as i know we can assign only one equipment to WBS element.
    My requirements is to assign more than one equipment to particular WBS elements. How should i do?
    Please help me
    Thanks

    Hi to the best of my knowledge you can not assign more than one equipment to a WBS in standard SAP
    It would all depend on how you structure your project in the past I have seen
    Project with first level WBS and then folliowing on from there you can have multiple WBS elements below this one for each equipment. This would then allow for reporting etc at both levels of the WBS.
    If you can supply a little more information I will try and help further.
    Jim