Project stock Material Sell to Customer

Dear Gurus,
I Created the Project , WBS Element, Activities,WBS BOM.
Then Raw material procurement process, Subcontracting process, Production order for the Finished material to get the Stock has been covered under the Project.
So now I have a Project stock at my Plant of say 10 Quantity..
Now I want to sell the same Stock material to One of the Customer ( Who developed this Project material). The revenue should be covered in the Project itself. How can I proceed for this.
As for as I know I have done customization in OPSB -- Automatic Revenue planning & assigned the Account & selecte the check box for Sales order.
I created the Sales order & assigned the WBS Element in the account assignment tab, then I did the Delivery in VL01N then when I am doing the billing for this delivery I am getting the error Item is not relevant for billing.
How to go about this. Please provide the process how to sell the Project stock material to Customer with Revenue generation from Project.
rgds
gsc

Ohh come on...
Just mark the WBS as a billing element.
Go to change project... select the required wbs and check the Billing element indicator.

Similar Messages

  • Project stock material for subcontracting

    Hi,
    I want to send project stock material (special stock with 'Q') for subcontracting vendor. Pl elaborate the procedure.
    Subcontracting PO is with account assignment category 'Q'.
    Pl revert.

    Hello Sachin
    We had similar requirement but in a different way. i.e sending material for subcontracting work for materials returned by customers getting it reworked bringing the reworked material back to plant stock and then sending to customer.
    We had used alltogether different transactions ADSUBCON is the transaction code. Prerequsite is you will have to implement BADI BADI_ADSUB_MVT_TYPES of enhancement specefe ES_BADI_ADSUB_MVT_TYPES.
    Regards

  • Valuated project stock not allowed with customer stock.

    Hi,
    I am trying to create invoice correction request for credit with the reference of invoice
    the invoice data is not copying into sales order. I am getting the error "Valuated project stock not allowed with customer stock".
       My question is can we have any routine in copy controll to fulfill my requirement or do i develop a new routine?
    Thanks in advance.
    Regards,
    Narayana

    Hi
    Did you find any sloution for this problem?
    I am facing the similar error.
    Inputs will be helpful
    Thanks
    Regards
    DDP

  • Project Stock - Material document Cancellation

    Hi
    Iam facing Below problem, Pl help me to resolve,
    I done GR for Project stock Material to Q.I, then done usage deceision from
    Quality and moved to unrestricted stock.
    Now i want to cancel the GR material document, When iam trying in MBST for
    the material document no, Iam getting error message that deficiate of stock in
    Quality inspection.
    How should i solve this problem , Pl suggest me asap.
    MM

    Actually you have moved the stock from QI to unrestricted so there is no stock left in QI so you'll get a deficit error.
    If you want to reverse that GR you need to move that stock back to QI from unrestricted stock and then do the reversal.
    Regards
    Noopur

  • How to issue the non stock material to the customer place through delivery?

    Dear All,
                I have created a service order with one operation,and for executing the operation i need one spares material which should be sent to the customer place.So i put that as non stock item in the line item of the order.
    Result : It Creates PR with account assignment and with reference to the PR i craeate a PO with the same account assignment order.
    Now when i take MIGO against the PO,it is directly consumed to the order,wherein i have to send that material to the customer place and then consume.
    How can i handle this process.
    Regards,
    Venugopal

    Hi,
    The material which u sending to Customer place mark those item as return in Purchase order and then do Goods movement by 161. If that material is non val. then No Accounting will generate.
    Vikramraj

  • Projected Stock for a given Material and Location (System: SCM-APO)

    Hello Experts,
    Appreciate, if anybody can help me in getting a time-series key-figure data (Stock-On-Hand for a given Material and Location) for a given period.
    I am working on a report to display the projected stock (Material & Location are known) for a given period (1 month).
    I am able to view the above data in my planning book.
    Thanks in advance.
    Regards,
    Prasanna
    Edited by: Prasanna Gunji on Apr 9, 2010 3:42 PM

    Hi Prasanna,
    9ASOQMQTY - Stock in quality inspection
    9ASOTRSQTY - Stock in transit
    9AAVLSTCK - Projected Stock
    Hope this helps
    Regards
    R. Senthil Mareeswaran.

  • Required reference document to issue the material from project stock

    Hi All,
    we have procure the project stock material with Acct. assignment Grp as "Q", now the material is laying in project stock.
    the things is we can issue the warehouse material with reference to Project Reservation similarly my client wanted to use some SAP document for records purpose to issue the material from project stock.
    i have checked this functionality in SAP which is not available except straight way issuing the material from project stock using MB1A( 221 Q).
    please help me out to resolve this requirent.
    manoj singh
    we can

    Hi,
    Did you implement PS module in your system?  How were your project stocks reserved?
    Cheers,
    HT

  • Project stock issue?

    dear ps experts,
    kindly let me know what is the right process in dealing with Project stock items issue for customer project.
    1. Is it thru MIGO-Goods Issues to Project against Reservation number
    2. Delivery thru Sales order - Delivery thru VL01N - PGI from project stock
    We are successful thru sales order - delivery thru vl01n - pgi and unable to settle the Reservation number in Project, which is still showing as "Reserved" through MMBE against the same material after delivery thru
    Pl help in clarifying us the right process.
    Regards
    Srihari

    Hi
    I meet the same problem before. and i can share the experience.
    generally speaking, we use CNS0 to deliver the finished or semi-finished products from the project.
    then we use VL01N to create the delivery note.
    if you only use VL01N, the project will generate reservation again (planned order or PR ) when MRP runs. one way to avoid this is to tick "final issue" in the Proc Para. tab of the material (in the project builder) as soon as you create the deliver note using VL01N. then the no extra reservation will be generated.
    if you use CNS0 to deliver, the final issue will be ticked automatically.
    it will help you to understand.
    Judy

  • How to transfer the stock form Project stock to Sale order stock

    Hi
    How to transfer the stock form Project stock to Sale order stock
    I tried to do this with movement type 413Q
    System is giving me error
    Valuated project stock not allowed with customer stock.
    Message no. KI346
    How to do this
    Thanks
    NK

    You can use Mov Type 412-Q
    412     Q     Transfer posting project to own - reversal
    Thanks
    Rajesh

  • Tables for Stock and project stock

    Hi Friends,
                               I have to create a report consists of Material No. Stock Qty, WBS Element, Batch NO..So Please convey the Tables and fields.
    Regards

    Hi Prasanna,
    Find below the details for
    1. Project stock:
    Material No. MSPR-MATNR
    Stock Qty -> MSPR-PRLAB (Unrestricted), MSPR-PRINS (QI stock), MSPR-PRSPE (Blocked), MSPR-PREIN (Total stock of all restricted stock)
    WBS Element -> MSPR-PSPNR
    Batch NO -> MSPR-CHARG
    2. Stock:
    Material No. MARD-MATNR
    Stock Qty -> MARD-LABST (Unrestricted), MSPR-INSME (QI stock), MARD-SPEME (Blocked), MARD-EINME (Total stock of all restricted batches)
    Hope the above helps.
    Regards,
    Vivek

  • Project Manufacturing just to stock material based on Projects

    Hello Dina / Experts,
    I am in situation where customer is in Real estate business using construction of properties and giving it on rentals or sell.
    Customer has a unique requirment to stock the material related to constructions based on the projects. I guess only project manufacturing can fulfill this requirment Am I correct? But does it advisable to iimplement project manufacturing only for this requirment? Is there any other cost effective approch to fulfill this requirement?
    Does there any white paper available on Oracle Project Manufacturing Functionality and setups avaialbe with you or NET?
    Please help.
    Thanks
    Edited by: oracle_samba on Mar 8, 2013 1:15 AM

    Hi
    when Customer wants to stock material and correspond to project, ideal scenario is to use Project manufacturing and perform PJM setups
    refer for setups Oracle Project Manufacturing setups
    with regards to construction project manufacturing setups are minimal, it is pretty clean with cost effective and control if you use Project manufacturing and Project costing
    Thanks
    Krishna

  • Moving avergae price updation in material master for project stock

    Dear All,
    My query is pertaining to updation of MAP( moving average price) for project specific procurement ( as project stock) for valuated project stock.
    As  definelty the cost of procurement gets consumed by project .but i want to know does the project stock procurement still updates the moving avergae price or not.
    Ex:-Suppose MAP in material master is 10 USD ( with qty 1)and i procure the same material ( qty 1)for project with account assignment Q for 9 USD . now will the MAP in material master becomes 9.5 USD or it remains 10 usd.?
    Please reply urgently
    Regards
    Amit

    Hi Amit,
    If your Project Stock is valuated, then, the valuation data for it is stored in a different table: QBEW.
    The normal, anonymus warehouse stock (the unrestricted use stock which is not assigned to any project or to any sales order) has its valuation data stored in MBEW.
    The "Accounting 1" view in the Material Master MM03 ONLY displays the data of MBEW.
    In the material master you will never see the valuation data of the valuated project stock (table QBEW) or the valuated sales order stock (valuation indicator "M" - table EBEW).
    The valuation data for the tables QBEW and EBEW can be seen in SE16 or in the transaction MBBS.
    Also note that these valuated special stocks are managed independently of the normal stock. If, for example, you change the Moving Average Price of your normal stock in MBEW, this will not have any influence on your project stock, as the data is under a totally diferent table QBEW.
    I hope this helps you,
    Esther.

  • Moving Average Price for Sales stock and Project stock of a material

    Hiya Gurus,
                     I am developing a report to display inventory details. My requirement is that I have to display the Moving average price of a material for all Valuation type. I also need to display the Moving average price if a material has got Project stock or Sales stock.
                     In MBEW table I can get the Valuation type and its Moving average price, but how can I find the moving average price for the same material if it has got Sales stock and project stock. Please let me know the table and field where I could get the relevant data.
                    Kindly help me on this, it would be deeply appreciated.
    Cheers,
    ZIa

    Hi
    can you look at tables
    EBEW                             Sales Order Stock Valuation
    QBEW                             Project Stock Valuation
    Nat

  • In case of Non Stock Material - Different GL for projects from WRX

    Hi Gurus,
    While doing MIGO for non stock material in case of projects, system is crediting account from WRX in OBYC with blank valuation class. but how can we give different GL for projects in this case.
    Please revert asap.
    Thank you

    >
    sapmm99 wrote:
    > For non valuated material, material  master is required or?
    >
    > As per my knowledge material master is mandatory only for stock materials. not for not valuated and non stock materials usually we never maintain master data for non stock and non valuated materials
    >
    > if i am wrong please advise me
    Its upto you if you want maintain material master record or not for non valuated material. With material master you have a material code to input in the field of PO, without material master you put in short text.

  • Material procurement as Project stock

    Hi,
    I have assigned a Non Stock Material (N) to WBS activity ---> converted the PR (created for network) to PO --> now i want to do GR for this PO and update the material recieved as Project stock on the correspondign WBS.
    I am using movement type 501Q when doing GR, and i expect that the corresponding WBS should automatically be populated or i should be able to add the WBS manually? but WBS field in MIGO screen when doing GR is greyed out?
    Any pointers to address this will be helpful?
    Thank you.
    Regards,
    Jatinder

    Hi,
    >>>>>>
    But now for one project i dont want to take material from store, but want the material to be supplied by supplier directly at project site, also i dont want to show the material supplied as directly consumed but want to show it first as WBS stock and then do GI to show consumption? how can we achieve this??
    <<<<<<<
    If you are intended to ship directly to site, then change procurement scenario as Drop shipment. In that case material never see the warehouse, what I mean no GR. Hope this make sense.
    for other requirement, discuss with your WM guys who should have fictious GR for that material. In that case you have to use material account assignment as Q (project stock). the only thing is you are not physically bringing material into warehouse but still you have GR for that material.
    Why you want to follow suck kind of routing, directly use drop ship procurement scenario which makes your life easier without any risk. By doing this you encouraging some kind of malpractices in system where users may misuse.
    Any have its your call and take decision accordingly.
    Regards,
    PSR

Maybe you are looking for

  • IGS for BW 3.5- Chart showing as column only

    IGS for BW 3.5 Hi All, We've been having problems with our WAD chart, it is showing up only as column chart even though we change the chart type to e.g line chart, bar chart..etc. I found note 653249 but it everything seems okay in our system. IGS te

  • Is the ability to center an inline object with a baseline shift gone in Pages 5.0?

    In the previous versions of pages I was able to center an inline object such as an imported equation with a baseline shift. I cannot find this in pages 5.0. It is gone?

  • Unable to open DNG files in PSE10

    i have tried to open raw files(dng) in elements 10,but cannot. after much reading of the internet it looks as if i need an update to acr but when i try to update ele 10 it says no update available. sys is windows 7 64 bit. Message title was edited by

  • Service Module - Contract Template

    Hello Experts, </p> We plan to implement service module in our SBO8.8 (pl6). I've been reading subjects about it for several weeks and do some testing. We've been using SBO almost about 1.5 years and trying to utilize its capabilities from time to ti

  • PDF printing of web-pages WITH background?

    How do I make it possible to have the background image/pattern/colour etc. of a web-page included when I "print" to PDF? Whenever I print a web page with something in the background other than white it's missing in the PDF file. This happens in my da