Project system planned quantiy

Hi all
I maintain the unit cost price and quantity at general cost activity master data but problem is that the quantity is not show in any reports. please guide me. is this any configuration problem......
thanks
shabbir

This is related to project system activity(general cost activity) not controlling activity type.
i need report that show the plan quantity that maintain in ps activity master data .....
thanks

Similar Messages

  • Version 999 Project System Plan Data Issue

    I am using transaction CJ9B to copy the Project System related plan data i.e. plan data at the WBS element level from Version 10F, period 1 to 12  in year 2010 to version 999, period 1 to 12 in year 2010. The transaction CJ9B runs successfully in the update mode. But when report CJI4 is executed for version 999, period 1 to 12 in year 2010 then we do not find plan data in sync with version 10F.
    I analysed this issue, had a meeting with end user and blanked out target version 999 using source version 9ZR for the year 2010. Then I again copied version 999 from version 10F. Still plan data in version 999 do not exist as they are in version 10F. I have checked the version 999 master data in transaction OKEV. Integrated Planning for SPL, COPA, cost center accounting and business process is active. COPY Allowed is also enabled. Version 999 is unlocked as well.
    Hence I am not sure why the copy functionality is not working fine for version 999, period 1 to 12 in year 2010.
    Can you please take a look and revert with your opinion so that this issue can be fixed ?
    Thanks,
    Umesh

    Hi,
    If you want to copy all the plan date from 10F to 999, then in Txn CJ9B
    select the indicator reset and overwrite in target version and execute in test mode.
    Regards,

  • Project System: Plan Version

    Anyone know how many plan version can I have in Project System for 1 project in same year?
    Edited by: ytai on May 25, 2010 11:20 AM

    Hi,
    You can define up to 10 versions (0 to 9). Please, search basic SAP material on help.sap.com
    Regards,
    Eli

  • BAPI project systems actuals versus planned

    Hello,
    I am looking for a BAPI/Idoc for displaying planned versus actuals similar to report s_alr_87013532. I have looked everywhere but cannot find anything. Also checked in OPENPS if there where any BAPI's for getting the information, but also not.
    Can anyone help me?
    Kind regards,
    Nick

    Hi
    Try this
    SAP Project System - A ready Reference ( Part 2 )
    Thanks
    S.Murali

  • Planning Profile for Project System

    Dear All,
    In planning Profile (T Code OPSB) for Project System we can find  RElem.f.billing plan ..field, in this field which cost element we have to assign wheather it is sales revenue or secondary cost element cat.31 or else..plz adives me..
    Thanks and regards

    Mr. Sridhar,
    Thanks for ur reply, here my querry is, i have types of sales revenues like domestic, export, industrial etc.. there is only option is there to maintain revenue cost element, so which revenue cost element i have to maintain in planning profile.
    Regards
    Ramesh

  • Cutover plan on Project systems

    Hi Friends
    Can any one help me to prepare Project systems cutover plan, if you have any cutover plan on Project systems could you please pass me to
    harikrishna underscore sd at yahoo dot com
    Our requirement is we are going to stop the existing client and we are creating a new client and will continue with the same. So how we should update the projects of various stages in the new client and how to close in the existing client.
    Regards,
    Hari

    Hi,
    Plz refer this links it may help u.
    http://sapdocs.info/2008/09/22/sap-go-live-strategy/
    CUTOVER
    http://www.sap-img.com/sap-implementation.htm
    Cutovers
    Different types of testing in a SAP Implementation project
    Regards
    Chandra

  • Project Systems Business Content - Residual Order Plan

    Hi all,
    I a issue which I hope someone can help me with:
    I am lodading data into cube 0PS_C08 and then into 0PS_C04 as per the BC. When I view the BC restricted key figure "residual order plan" i get nothing (blank).
    I look in R/3 I have values for residual order plan. I have looked at the Help on SAP and they say there is some config that needs to be done in SPRO. I dont really understand what config needs to be done can someone help?
    Many thanks,
    Leo

    Hi,
    We are searching for project versions(project systems) business content :
    Base tables :
    VSAFVC_CN     Version: Operation in order
    VSAFVV_CN     Version: Quantities/Dates/Values in order operation
    VSAUFK_CN     Version: Order master data
    VSEBAN_CN     Version: Purchase requisition
    VSEBKN_CN     Version: Purchase requisition account assignment
    VSJEST_CN     Version: Individual status per object
    VSJSTO_CN     Version: Information on status object
    VSKBED_CN     Version: Capacity requirement records
    VSKBEZ_CN     Version: Additional data for table KBED (ind. capacities)
    VSKBKO_CN     Version: Capacity requirements header for an order
    VSKOPF     Version: Header - general data for a version -
    VSKPER_CN     Version: Workforce Planning
    VSMLST_CN     Version: Milestone
    VSNPTX_CN     Version: PS texts (network)
    VSPRHI_CN     Version: WBS, edges (hierarchy pointer)
    VSPROJ_CN     Version: Project definition
    VSPRPS_CN     Version: WBS element (work breakdown struc. ele.) mast. data
    VSPRTE_CN     Version: Scheduling data for project item
    VSPRTX_CN     Version: PS texts (WBS)
    VSPSTX_CN     Version: PS texts (header)
    VSRPSCO_CN     Version: Cumulation table for project reporting
    VSSTEU     Version: Control table - one entry per version object -
    I didn't find any relevent business content for above tables.
    If anybody extracted these ,please let me know where and how they extracted.I will assign points.
    Thank you,
    GSR

  • Plan hours in Project System

    Hi SAP Gurus,
    In project system as i can plan my cost, can i plan my hours?? If yes how?? where in SAP?
    I am in service industry and my billing happen on hours..
    Please help, its urgent
    Pritam

    Hello Smile,
    Yes, You can plan your man hours in project many ways
    1. Plan manhours in network activities using work centers
    2. Plan manhours in network activities using workforce planning ( integration with HR Module)
    3. In some companies, many departments work on a project and they plan manhours on cost centers and not on Project. In other words, many department provide services to projects.
    Here I will assume that you want to plan manhours in Project without workforce planning.
    The following are the pre requisite for planning man hours in project network activities.
    1. Work center ( may be person or group of persons, machine or group of machines. Workcenter reflects skills and capacities in cost center)
    2. Work or duration ( based on the calculation key either one is calculated)
    3. Activity type ( Type of service)
    Behind the screen,You have to have a cost center attached to the workcenter (CNR1/CNR2) and activity type. Combination of cost center and activity type will decide the rates. Use transaction KP26 to enter the rates.Activity prices are valid for a certain period of time only. They are entered for either months or a year.
    The budget for the cost center should be used as a base to calculate the hourly rate for each activity type.
    When you enter a work in the network activity, system calculates the costs for the manhours.
    Eg: You create engineer as workcenter. He is asked to go to site and did installation of equipments.
    Attach workcenter ABCD to network activity, activity type "Engineer" and work 100 hrs.
    If the engineer rate is $50 per hour given in KP26.
    Then the planned cost for manhours is 100 X $50 = $500
    The same engineer can provide supervison service at your workshop. For that, his rate may be $20/hour. If you plan for supervison then the planned costs will be $200
    FATMAN

  • Where does Plan Version field store in SAP project system table?

    Hi,
    I would like to know where where does Plan Version field store in SAP project system table.
    The plan version that I m refering is the Plan Version 1 in the menupath u201COn the Project Info System: Progress Analysis: Initial Screen, Choose Settings > Value display > Plan versionsu201D.
    T-Code: CNE5
    Thanks.

    hi,
    try table TKA09
    regards

  • Overhead planning in Project System- Result Analysis

    Hi .. I want to plann over head for project system. Please suggest me the procedure.

    Hi .. I want to plann over head for project system. Please suggest me the procedure.

  • Sales order in Project system

    Hi All,
    Can u tell me please how can we create  a sales order,Quotation in projects and what are tcodes for that.
    As i am here involved in Capital projects i dont have any idea of customer projects ican u pleease let me know the customizing part too.
    Assured of rewarsd points
    Thanks in Advance.
    Regards,
    Abraham.S

    Hi,
    to create quote from project system there is quite a bit of PS ( project system ) SD integration is required. i will try my best to deliver with whatever time i have right now.
    1. t-code -CKCM - your will define easy cost planning here whihc will be your pricing factor in in sales order.
    2. ODP1- you define DIP profile here you will also define your costing elements here. this DIP profile is attached to sales doc type. and on main menu you will find button that says quotation. click on that. this willd irectly take you to quote and from there u can take it forward.
    I hope it helps u little. Though i know its not enough.

  • WBS Elements not getting created in ECC Project System from CRM 7.0

    Dear all,
    We are trying to integrate SAP CRM 7.0 with SAP ECC-PS module. The objective is to bring in the marketing plan and elements data from the CRM system, and to create the corresponding WBS in project system. We have done most of the configuration as recommended by SAP in both the systems, and we see that the BDOCS are getting generated and sent to the ECC system. The following steps have been successfully completed:
    1.       Set up the RFC connections between the two systems
    2.       Selected the connection type as Middleware in CRM system.
    3.       Installed the cProject Add on in CRM box.
    4.       Created a project scenario (with project and network profiles) in the PS system and assigned the same in the CRM system.
    5.       The Project Scenario in PS config has the same name as the Project Type in CRM config.
    6.       Created and released the campaign ids being created in the CRM system.
    As already mentioned, we can see that the BDOCS are coming to the ECC system and are getting stored in BDOC_TRACK table. However the issue is that the corresponding WBS elements are not getting generated in the ECC system. Is there anything that that we are missing in the ECC box which would trigger the WBS element creation?
    Request you all to share your inputs which would be immensely beneficial for us in achieving this integration.
    Thanks and Kind Regards,
    Aditya Shrivastava

    Hello Aditya,
    We too are facing this issue.. if you have resolved the issue could you please let us know the solution ?
    Some inputs related to our system,
    We have upgrade from CRM 4.0 to CRM 7.0 SP07 and R/3 backend system is on 4.7 SP27, earlier we have completed the upgrade on sandbox without any issues which was upgrade to CRM 7.0 SP04 but with SP07 we are facing the problem of WBS Element not getting created in R/3.
    Your help is highly appreciated.
    Thanks & Regards,
    Sumukh Kapoor.

  • Sub-contracting through Project system.

    Hi
    Can some one please help me in understanding how Project system (PS) is supporting sub-contracting scenarios.
    I am looking for activity sub-contracting and also sub-contracting with Project stock materials.
    I am aware of normal sub-contracting through production order and also sub-contracting through MM. I am specifically looking for sub-contracting in PS.
    Thanks and warm regards,
    Jagadeesh

    Hi,
    If requirements for subcontract items (or services) are generated automatically from PS just make sure that the right document category is used (subcontract) then any requisitions or planned orders etc. will have the right category.
    There is no difference between PP, PS and PM effectively, they all use subcontracting in the same way it is just how the requirement is triggered that is slightly different.
    If you need details on how to trigger the right type of requirement through PS then you may need to use one of teh financial forums that cover PS? (is there one?)
    Steve B

  • Report Painter Drilldown on Cost Element for Project Systems

    I am currently working on a report for Project Systems. I am trying to copy the functionality of the Internal Order summary (60I2-001) into report group 6P3. I was able to copy the whole layout and also the values of 6oI2-001 into a copy of 6PP4-001 but when I double click on "Balance" it is bringin up the ALV report that 6PP4-001 is using. I would like to call another report which looks like 6LS0-001 but contains Project System info made in report painter when I double click on Balance. Is this possible? Please let me know how.

    Hi Avinash,
    See my replies below.
    1 a & B: You are planning Qty on NWA and capturing costs - labor & Equipment on NWA elements.
    When  you are having elaborated to NWA-Element level, split your total work on each NWA-element and post labor cost. Thus you will have planned Vs actual costs at one place.
    coming to equipment cost - are you capturing using PO through GR?.
    2.a : Option1- create a separate WBS elements for materials and plan cost at WBS level. That value would be your total planned cost of material procurement as estimated. Under this WBS elements create NWAs and assign the materials. With this set up you can assign material and procure so that will have actual costs coming from GR.
    Option 2: Create a one General Cost activity and assign the total planned cost of material on this NWA.
    When you assign the material components, diligently you have to reduce the equivalent amount from the general costs activity. Also note that on component screen, you have to check box "Cost relevant" so that material cost will add to Cost NWA. Let the different materials  have their own valuation class and have default CEs accordingly. that would not be big issue.
    Please discuss with your MM team to get more information. Also my suggestion is to leave blank CE field in configuration.
    The option2 is very cumbersome and high risk but one have to be very cautious to reduce the value from Cost NWA in order to sustain the planned material costs whenever they added.
    3. I have answered the relevance of Cost relevance check box in above.
    Hope above makes sense.
    Thanks,
    Sudhakar

  • Project System - Report Painter - Cost roll up issue

    Hi,
    We have an issue with the roll up of the costs in Report Painter report in Project Systems. The problem occurs only with those costs which have been settled to an internal order from a WBS element.
    We are using the same cost elements to settle to the Cost Center and Internal order and roll up of the costs work fine for those settled to cost center. But the roll up does not happen for the costs settled to an internal order. Would appreciate if someone can guide on how to fix this issue.
    Raj.

    Here are the values:
    Period/year     000.1900     Remainder 1900     PERIO     Period/year
    Value Type     4     Actual                                                 
    Value Type     10     Statistical Plan                                                 
    Object ind.     P     Project item                                                 
    Object ind.     1     Order plan values: appended, apportioned     9     Order values: not appended, deleted
    Debit type     1     Costs and credit-side payments                                                       
    Thanks for your help.
    Raj/